Road Reconstruction - Wayne County
ID - 82022-201225
ID - 82022-201225
Location: MI Wayne County County 07032 District
Bid Date/Time: Nov. 21, 2025, 8:30 p.m.
Project Type:
Status: Awarded
Description:
10.49 mi of concrete reconstruction, concrete pavement repairs, interchange reconfiguration, concrete inlay, drainage, traffic signal upgrades, signing, freeway lighting, guardrail, ITS, landscaping, noise wall, pavement markings and rehabilitation of 24 structures on I-94 from Wayne Road to east of Greenfield Road and M-39 from I-94 to Outer Drive in the cities of Romulus, Taylor, Allen Park, Dearborn Heights, Dearborn, and Melvindale, Wayne County. This project is an Alternate Pavement Bid project. Alternate 1 (Section 2) is a Hot Mix Asphalt Alternate with 16 inch OGDC. Alternate 2 (Section 3) is a Hot Mix Asphalt Alternate with 6 inch CTPB and 10 inch OGDC. Alternate 3 (Section 4) is a Concrete Alternate with 16 inch OGDC. Alternate 4 (Section 5) is a Concrete Alternate with 6 inch CTPB and 10 inch OGDC. This project includes two 5 year materials and workmanship pavement warranties, a 2 year concrete surface warranty, a 5 year epoxy performance warranty and a 2 year bridge coating warranty. ** 364729 B or 364729 Cb or 364729 Ea **In addition to the above minimum prequalification requirement for prime contractors this project includes subclassifications Ea and either B or Cb. If the prime contractor is not prequalified in those subclassifications it must use prequalified subcontractors. Those subcontractors must be designated prior to award of the contract to the confirmed low bidder.
10.49 mi of concrete reconstruction, concrete pavement repairs, interchange reconfiguration, concrete inlay, drainage, traffic signal upgrades, signing, freeway lighting, guardrail, ITS, landscaping, noise wall, pavement markings and rehabilitation of 24 structures on I-94 from Wayne Road to east of Greenfield Road and M-39 from I-94 to Outer Drive in the cities of Romulus, Taylor, Allen Park, Dearborn Heights, Dearborn, and Melvindale, Wayne County. This project is an Alternate Pavement Bid project. Alternate 1 (Section 2) is a Hot Mix Asphalt Alternate with 16 inch OGDC. Alternate 2 (Section 3) is a Hot Mix Asphalt Alternate with 6 inch CTPB and 10 inch OGDC. Alternate 3 (Section 4) is a Concrete Alternate with 16 inch OGDC. Alternate 4 (Section 5) is a Concrete Alternate with 6 inch CTPB and 10 inch OGDC. This project includes two 5 year materials and workmanship pavement warranties, a 2 year concrete surface warranty, a 5 year epoxy performance warranty and a 2 year bridge coating warranty. ** 364729 B or 364729 Cb or 364729 Ea **In addition to the above minimum prequalification requirement for prime contractors this project includes subclassifications Ea and either B or Cb. If the prime contractor is not prequalified in those subclassifications it must use prequalified subcontractors. Those subcontractors must be designated prior to award of the contract to the confirmed low bidder.
Project Roles
Owners
- Owner MICHIGAN DEPARTMENT OF TRANSPORTATION, 400 TRANSPORTATION LN LANSING MI 48822
Bidders
- Bidder Dan's Excavating, Inc., - $342,508,618, 12955 23 Mile Rd Shelby Township MI 48315
- Bidder Toebe Construction LLC, - $394,446,074, PO Box 930129 Wixom MI 48393
Apparent Low Bidder: Dan's Excavating, Inc.
| Your local Trimble Construction Division dealer |
|---|
| SITECH Michigan |