Safety Improvements at the Intersection of US 285D & SH 9C
ID - C20638R-COMBO
ID - C20638R-COMBO
Location: CO PARK County 2120 District
Bid Date/Time: Dec. 1, 2022, 10 a.m.
Project Type:
Safety
Status: Awarded
Description:
Safety Improvements at the Intersection of US 285D & SH 9C COMBO STA M420-001 (20638-COMBO) with BR 2854-148 (24052) and STM 0091-046 (24253) This Project is located in Region 2 in Park County. The project will include bridge replacement (H-13-A), roadway widening and reconstruction to accommodate additional through lanes and acceleration / deceleration lanes, new traffic light installation, ADA Ramp work in both Fairplay and Alma, storm sewer and drainage improvements, and sidewalk and curb and gutter replacement. Mobilization will be required for the work in Alma.
Safety Improvements at the Intersection of US 285D & SH 9C COMBO STA M420-001 (20638-COMBO) with BR 2854-148 (24052) and STM 0091-046 (24253) This Project is located in Region 2 in Park County. The project will include bridge replacement (H-13-A), roadway widening and reconstruction to accommodate additional through lanes and acceleration / deceleration lanes, new traffic light installation, ADA Ramp work in both Fairplay and Alma, storm sewer and drainage improvements, and sidewalk and curb and gutter replacement. Mobilization will be required for the work in Alma.
Project Roles
Owners
- Owner COLORADO DEPARTMENT OF TRANSPORTATION, 400 SOUTH COLORADO BLVD DENVER CO 80204
Bidders
- Bidder Castle Rock Construction, - $25,412,230, 25436 Spring Street Manhattan IL 60442
- Bidder MYERS & SONS CONSTRUCTION, LLC, - $25,435,907, 45 Morrison Ave Sacramento CA 95838
- Bidder AMERICAN CIVIL CONSTRUCTORS, - $24,091,000, 4901 SOUTH WINDERMERE STREET LITTLETON CO 80120
- Bidder SEMA CONSTRUCTION, INC., - $24,486,896, 7353 S. EAGLE STREET CO 80112-4223 (303)627-2600 TX
Apparent Low Bidder: AMERICAN CIVIL CONSTRUCTORS
| Your local Trimble Construction Division dealer |
|---|
| SITECH Northwest |