Construction News

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

North Carolina DOT Expands Network of Multimodal Options with Rockingham Bypass

by: Larry Bernstein
To combat geotechnical issues on the Rockingham Bypass project, the construction team used reinforced soil slopes to provide stability to embankment fills.
To combat geotechnical issues on the Rockingham Bypass project, the construction team used reinforced soil slopes to provide stability to embankment fills.
The United States interstate system is, among other things, an economic driver. To efficiently facilitate the movement of goods, the interstate system needs to keep up with changing needs. The North Carolina Department of Transportation (NCDOT) Rockingham Bypass project focuses on two economically impactful corridors in the state and region.
Strategic Corridors
North Carolina has deemed 25 corridors as Strategic Transportation Corridors. The Corridors form the core network of multimodal passageways and move large volumes of people and freight across regions of the state and to key markets outside the state. The transportation facilities and services within the corridors connect centers of economic activity of statewide and regional significance. Because of the importance of these corridors, maintaining them at the highest level is one of the state’s top priorities.

The Rockingham Bypass, which will be referred to as I-73/74, is part of two of the Strategic Transportation Corridors. The new 7.2-mile bypass consists of a four-lane, median-divided freeway. The current average daily traffic count in the area is approximately 20,000 vehicles, and the 2040 projected count is 33,000 vehicles.

The City of Rockingham, which is in central North Carolina and near the border with South Carolina, is being bypassed. This project connects I-74 with a high-speed (65 mph) interstate standard facility.

“Currently citizens travelling on I-74 must travel through the city limits with a maximum speed limit of 45 mph and encounter multiple traffic signals,” says Cary Fine, a Resident Engineer with NCDOT. “Removing interstate traffic from signalized intersections and local roads was critical to safe and efficient travel through this corridor.”

Other work includes upgrading the existing U.S. 74 Bypass. The interchange will have six 12-foot travel lanes – previously, there were four – and a 60-foot median. Two new interchanges are also being constructed.

Leica Geosystems Inc
Your local Leica Geosystems Inc dealer
Laser Specialist inc

The team has had to deal with some unique geotechnical issues, including immense rock cuts, groundwater intrusion, and highly plastic soils during their work on the project. They have used innovative tools such as reinforced soil slopes to help provide global stability to roadway embankment fills.

“These reinforced soil slopes use high strength geosynthetics placed horizontally throughout the slope face to provide a stable slope structure,” Fine says. “This design was utilized on numerous large roadway embankments, with the largest being 80 feet.”

Vecellio & Grogan, which is based in Beckley, West Virginia, is the general contractor on the project. The firm specializes in heavy civil roadway construction and has worked on numerous NCDOT roadway projects.

“Vecellio & Grogan has bought experience along with a high level of expertise to the project,” Fine says. “They’ve provided valuable, innovative input on how to efficiently accomplish several challenging construction operations on the project.”

Decades in the Making
The Rockingham Bypass project broke ground in November 2019. However, NCDOT recognized the need for improvements along the corridor many years ago. A feasibility study evaluating initial design options was published in May 1996. A preliminary public hearing followed shortly afterwards.

Other relevant happenings occurred over the years, including public meetings and environmental studies. Right-of-way acquisition began in 2009 and was substantially completed for all sections. Some design changes and utility relocations have required minor additional acquisitions of right of way and permanent utility easements as late as 2019. 

Despite all the preliminary work being completed by 2009, the project was initially slated to begin in 2026. The delay was due to a lack of funding.

Ultimately, the project was accelerated and construction began in the fall of 2019. “The project was accelerated in the State Transportation Improvement Program (STIP) due to need and the fact that the project was shovel-ready for construction,” Fine says. The project was also pushed forward since all the right of way had been acquired, utility relocations were primarily complete, and the project design was finalized.

With the long-planned project finally underway, NCDOT planned for completion data in late 2023. Due to the pandemic, the schedule for the project was backed up. Fine explains that supply chain and workforce issues impacted progress. The Rockingham Bypass is on schedule to be open to traffic by May 2025.

Fully State-funded
The $308 million project is entirely state-funded. Some state funds are from Build NC bonds. Build NC went into effect on January 1, 2019, after being passed by the State Legislature the previous year. The financing tool aims to ensure the NCDOT “can continue strong delivery of critical road projects at the regional and division tiers that do not qualify for a similar federal funding tool.”

According to the Build NC website, “Those projects will benefit residents across North Carolina by providing the infrastructure to better access jobs, health care facilities, and educational opportunities.

Of the $308 million, $146 million was budgeted for construction. The remainder was for preconstruction/design, right of way acquisition, and necessary utility relocations. The project is approximately $15 million over budget. “The increase in project delivery cost is due to significant escalations in material costs experienced over the past couple of years,” Fine says.

When the Rockingham Bypass project is complete, North Carolina will have improved its Strategic Transportation Corridors. This will enhance economic activity, benefiting state residents and people throughout the region. Congestion in and around Rockingham will be lessened, and traffic will flow better since interstate traffic will be removed from signalized intersections, local roads, and highways.

Case  - CE
Your local Case Construction Equipment Inc dealer
ASCO Equipment
Case  - CE
Your local Case Construction Equipment Inc dealer
ASCO Equipment
Epiroc
Your local Atlas Copco CMT USA dealer
Power Equipment Co