Construction News

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Suffolk Construction Targets 2023 Finish for $300M Northeastern University EXP Building

by: Paul Fournier
J. Derenzo uses a Caterpillar 374 Excavator during site work for $300 million Northeastern University EXP project underway by Suffolk Construction.
J. Derenzo uses a Caterpillar 374 Excavator during site work for $300 million Northeastern University EXP project underway by Suffolk Construction.
Steel sheetpile walls are supported by engineered cross-lot bracing at the site, which is bounded by an active city street and railway tracks. In the background is Northeastern University’s ISEC Building, also constructed by Suffolk.
Steel sheetpile walls are supported by engineered cross-lot bracing at the site, which is bounded by an active city street and railway tracks. In the background is Northeastern University’s ISEC Building, also constructed by Suffolk.
Perimeter foundation walls and the building’s structural cast-in-place core are underway, together with structural steel and Level 1 decking installation.
Perimeter foundation walls and the building’s structural cast-in-place core are underway, together with structural steel and Level 1 decking installation.
With the building mass excavation complete, cast-in-place column footings and the slab-on-grade were installed in coordination with underground utilities.
With the building mass excavation complete, cast-in-place column footings and the slab-on-grade were installed in coordination with underground utilities.
Reinforcing bar installation at the cast-in-place perimeter foundation walls is ongoing.
Reinforcing bar installation at the cast-in-place perimeter foundation walls is ongoing.
Level 5 composite slabs are placed concurrently with steel superstructure erection.
Level 5 composite slabs are placed concurrently with steel superstructure erection.
Bulk excavation and soil hauling take place after all soils were pre-characterized by engineers so that regulated soils could be shipped to appropriate facilities.
Bulk excavation and soil hauling take place after all soils were pre-characterized by engineers so that regulated soils could be shipped to appropriate facilities.
Construction of Northeastern University’s new $300 million research building at the Boston campus has reached the halfway mark and is on schedule for a mid-summer 2023 finish by general contractor Suffolk Construction.

The 350,000-square-foot EXP building joins the Interdisciplinary Science and Engineering Complex (ISEC), a 234,000-square-foot building also built by Suffolk and officially opened in April 2017. Both buildings were designed by Boston architect Payette Associates Inc. The eight-story EXP building includes teaching and research labs, cafe, faculty club, and landscaped green space between the MBTA’s Ruggles Station and ISEC.

As part of Northeastern’s updated development plan, EXP was approved by the Boston Planning and Development Agency in October 2019. Construction began shortly afterwards but was interrupted for several months due to the COVID-19 pandemic. Work was allowed to resume in August 2020.

One of the most challenging aspects of the project is the lack of workspace, according to Denis Garriepy, Suffolk Project Executive, “The project site is within an active, urban campus, immediately adjacent to a major railway artery running through the City of Boston. There is near zero laydown space for the building.”

He indicated another challenging feature of the project is its complex fluidity.

Hitachi CE
Your local Hitachi dealer
CLM Equipment Co
ASCO Equipment

“Suffolk has been tasked with managing evolving programmatic changes in response to the project owner’s needs. And those needs are driven by a building that must respond to the ever-changing needs of future occupants.”

Garriepy is a member of a Suffolk project management team headed by Sean Edwards, Chief Operating Officer, and includes Lisa Kochilaris, Project Executive and Kevin Sullivan, Senior Superintendent. This team works closely with representatives of Northeastern University including:

  • Gilbert Delgado, Associate Vice President - Design and Construction
  • Jeremy Munn, Program Director - Facilities Division
  • Jacqueline Valencia, Senior Capital Project Manager 
  • Paul McAndrew, Senior Project Manager - Design and Construction
Mud Slabs and Lightweight Concrete
Work began with advance soils pre-classification by Haley & Aldrich environmental/geotechnical engineers so that any regulated soils could be shipped to appropriate receiver facilities. This was followed by bulk excavation and soil hauling by J. Derenzo Co.

The building footprint is an irregular polygon requiring a professionally designed earth retention system to protect other nearby structures including the railway system. Designed by McPhail Associates LLC, the system was installed by Hub Foundation Co., and J. Derenzo Co., and consisted of steel sheetpile driven around the 780-foot perimeter. Sheetpile was driven deep enough to form a 20-foot-tall wall and was braced by 36-inch diameter cylindrical steel cross-lot struts.

The area of excavation for the building’s footprint was about 35,000 square feet, while the depth was approximately 25 feet. Derenzo excavated some 32,000 cubic yards of material.

Next a 3- to 6-inch mud slab was placed in the bottom of the excavation. This layer of lean unreinforced concrete provides several benefits – it establishes a level dry working platform, helps maintain the structural integrity of footings, and cleans up the surface of the excavation.

J.L. Marshal & Sons placed a 5-inch regular weight concrete base slab and installed the eight 6-1/4-inch elevated floor slabs which consist of 3-inch deep, 18 gage composite concrete/steel deck topped by 3-1/4 -inches of light weight concrete. The composite slabs are also reinforced with welded-wire fabric. Steel decking was furnished by Beauce-Atlas and installed by Boss Steel, while J.L. Marshall & Sons installed the cast-in-place concrete.

LeMessurier is the project’s structural engineer, with steel fabricated by Beauce-Atlas and erected by Boss Steel. Framing steel ranged from relatively lightweight W8x10s to heavy W24x192s.

Other major consultants include Nitsch Engineering (civil engineer), Stephen Stimson Associates Inc. (landscape engineer) and Arup (MEP/FP engineer).

Dry Labs, Wet Labs
EXP and ISEC complement each other, together providing more than 500,000 square feet of space dedicated to research and academic programs. The emphasis placed on research at Northeastern is evidenced not only by an investment of $525 million in constructing these two buildings, but also by the size of its federal research funding – now reportedly $130 million a year. Correspondingly, over the past 15 academic years, the University has hired hundreds of new faculty in disciplines related to its research goals.

A striking feature of the EXP design is its flexibility – for example, it allows the conversion of “dry labs” to “wet labs” to accommodate research needs – no small task when considering the different demands of each type of facility. Wet labs handle various types of chemicals and potential "wet" hazards, so the rooms must be carefully designed, constructed, and controlled to prevent spillage and contamination. Dry labs on the other hand, are focused on computation, physics, and engineering and require less complicated room design.

In addition to lab convertibility, EXP interior space is arranged to promote collaboration among students across different fields of study. This includes classrooms and dedicated space for work on autonomous vehicles, drones, robots, and makerspace. The entire second floor of EXP is dedicated to the latter. Maker Education, a relatively new concept in academia, involves hands-on, often collaborative, projects-based learning to solve problems. EXP’s third, fourth, fifth, sixth, and seventh floors are dedicated to research and teaching labs and classrooms, while the eighth floor houses executive offices, the faculty club, and a boardroom.

Hamm
Your local Wirtgen America dealer
Kirby Smith Machinery

The exterior of the EXP building was designed to harmonize with the ISEC building and a pedestrian bridge that connects the two buildings. The 317-foot weathering steel bridge, which opened to the public in June 2019, also links Northeastern with surrounding neighborhoods and several Amtrak and commuter rail lines.

EXP students will also have access to ISEC research space and facilities including an MRI. Furthermore, two large research groups are slated to move from ISEC to EXP. The high ceilings (16 feet) of the first story of EXP will support robotics programs, including driverless cars and humanoid robots. In line with this, University researchers are programming a 6-foot, 2-inch-tall humanoid to visit Mars ahead of human explorers. This project is a collaborative effort by Northeastern University, University of Massachusetts Lowell, and NASA's Johnson Space Center.

The Owners
Since its founding in 1896, Northeastern University has expanded from a few buildings on Boston’s Huntington Avenue to a sprawling urban campus. After initially renting space in the Botolph Building and the Boston Young Men's Christian Association (YMCA), the University constructed its first building, Richards Hall, in 1939, and continued to grow from there. A push towards building dormitory spaces in the 1960s helped to transform the University from a commuter college to a residential college. Northeastern pioneered cooperative education (co-op) more than a century ago and the experiential learning program has become the University’s hallmark. Each year students at every level and on every campus participate in a learning model that enables them to alternate semesters of academic study with periods of paid full-time work.
The Builders
Suffolk Construction is privately held and led by founder, chairman and CEO John Fish. Suffolk Construction Company, stylized as Suffolk, is an American construction contracting company based in Boston, Massachusetts, with additional locations in California, Florida, New York, and Texas. Suffolk is the largest construction contractor in Massachusetts and one of the 20 largest in the country. In 2018, Forbes reported that the company is the 148th largest private company in the U.S. The company is contracted for work in the aviation, commercial, education, healthcare, gaming and government sectors. Suffolk currently has about 2,100 employees and revenues of $3.5 billion.
Vogele
Your local Wirtgen America dealer
Kirby Smith Machinery
Power Equipment Co
Hamm
Your local Wirtgen America dealer
Kirby Smith Machinery
Epiroc
Your local Atlas Copco CMT USA dealer
Power Equipment Co