Construction

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Michigan DOT Reconstructs M-37 in Barry and Kent Counties

by: Larry Bernstein
Workers resurface a section of M-37, which part of Michigan DOT’s Rebuilding Michigan program.
Workers resurface a section of M-37, which part of Michigan DOT’s Rebuilding Michigan program.
One of the challenges states face when it comes to growing and maintaining their infrastructure is financial uncertainty. The Rebuilding Michigan program, which runs from 2020-2024, is being financed in part through the issuance of bonds and offers more certainty. The objective of the program is to rebuild the state’s highways and bridges. The priority is on those pieces of infrastructure that are most important for the economy of the state and have the highest traffic. The reconstruction of M-37 in Barry and Kent counties was advanced in the Michigan Department of Transportation’s (MDOT) five-year program by the Rebuilding Michigan initiative.
Key Element
The M-37 highway is a north-south highway in western Michigan. This section of M-37 is in southwest Michigan, just outside of Grand Rapids.

As part of the project, six miles of M-37 are being resurfaced. Over the course of the six miles, the number of lanes varies from two to five. The aim of the resurface and millwork is to create a smooth safe path for motorists, improve operations, and extend the service life of the roadway.

Along the project is three intersections. At one of the intersections, MDOT is putting in geometric improvements. In the past, there were stop signs at the intersection. Traffic turning right would use a SLIP lane, which removes them from through-traffic and allows them to maintain a similar speed during their turn. There were several crashes in the area, and the public called for safety improvements at the heavily trafficked intersection of Finkbeiner/Crane Roads.

In response, MDOT is installing a right turn lane and traffic signal. When completed, vehicles will make a more typical right-hand turn. This will separate through traffic from turning traffic, allowing turning vehicles to slow down without impeding others on the road.

“We project that the geometric improvements and the addition of a traffic signal will increase safety and improve operations through the corridor and lead to less back-ups and congestion in the area since traffic can pass more freely,” says MDOT’s Jacob Alarie, the Project Engineer who is overseeing day-to-day operations on the project.

Bomag - Roller
Your local Bomag Americas dealer
Linder Industrial Machinery

Throughout the project limits, M-37 had been experiencing pavement joint deterioration. There were cracks in the road and the rough surface led to poor driving conditions.

Other Work
The second intersection is being widened with a center left turn lane in both directions being installed. In addition, a right turn lane for southbound traffic is being installed. Each of these additions will allow for more free flow of traffic. At the third intersection, MDOT is adding a traffic signal.

The project also includes a new concrete curb and gutter, new guardrail, culvert replacement, new signs, pavement markings, and bridge improvements at Duncan Creek. The guardrails are being upgraded to the new standards.

Surprises Challenge the Schedule
The project began in May and was to open to traffic in August. “The completion date of all major activity was targeted to coordinate with the opening of schools in the area,” Alarie says. “The goal was to have equipment off the roadway and not effect busing and parents getting children to and from school as well as their commute to work.”

The project completion date was pushed back a few weeks due to rainy weather. This part of Michigan experienced lots of rain during construction season, which impacted work being done on the Duncan Creek bridge. Work included waterproofing beams on the bridge to extend its service life. To do the waterproofing, the bridge needed a minimum of 72 hours of dry weather with no moisture on the box beams. Alarie notes that even a five minute rain resets the clock. “It took two months until we got three straight days of good weather,” says Alarie.

A second challenge was the uncovering of a few items in the field that had to be dealt with. Among these surprises was a culvert headwall. The team had to remove 60 feet of culvert pipe and replace a 36-inch culvert headwall along with 8 feet of pipe. The pipe and headwall detached from the remaining length of the culvert causing the surrounding soils to erode and the headwall to settle.

Besides affecting the schedule, these discoveries impacted the budget. Originally budgeted for $7.4 million, including $5.8 million for the contractor, the budget is projected to come in slightly over. This project combines both state and federal funds.  

Volvo Roadbuilder
Your local Volvo Construction Equipment dealer
Richmond Machinery & Equipment

Michigan Paving and Materials served as the contractor for the project. They were selected by low bid. This was the first time that Alarie worked with Michigan Paving and Materials as the prime contractor – in the past, they were a subcontractor. Regular communication, Alarie believes, is critical to delivering the best possible product. He also notes the coordination between the prime and sub-contractors is key to keeping close to the schedule, despite the challenges.

Traffic Precautions
Because of the high traffic count in the area – approximately 14,000 vehicles daily – Michigan Paving and Materials had an automated flagging system in the work zone in addition to a flagger. The automated flagging system is a mechanical arm, like those that are present at train crossings. With the system, traffic can only flow in one direction.

“The automated flagging system helped to make sure traffic was flowing in one direction at a time which made it safer for the flagger and gave extra warning to motorists,” says Alarie.

Upon completion of the project, commuters in the area will experience increased safety and mobility. In addition, the roadway will make for a smoother safer driving surface that will be in service for years to come.

Topcon Construction Products
Your local Topcon Positioning Systems Inc dealer
Linder Industrial Machinery
Wirtgen America Inc
Your local Wirtgen America dealer
Dobbs Equipment (SC)
Topcon Construction Products
Your local Topcon Positioning Systems Inc dealer
Linder Industrial Machinery