Midwest Contractor

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Empire Paving Inc. Jacks Flood Control Culvert Under Amtrak in Meriden

by: Paul Fournier
An Amtrak train passes close to support-of-excavation steel sheeting as CRS Contractors jack Permalok steel pipe under railroad tracks for Harbor Brook Overflow Culvert, which is under construction in Meriden, Connecticut, by Empire Paving.
An Amtrak train passes close to support-of-excavation steel sheeting as CRS Contractors jack Permalok steel pipe under railroad tracks for Harbor Brook Overflow Culvert, which is under construction in Meriden, Connecticut, by Empire Paving.
The construction of a new culvert to help alleviate chronic flooding in downtown Meriden, Connecticut, involves the installation of twin large-diameter pipe only a few feet beneath live Amtrak railroad tracks.

Empire Paving Inc. (EPI) of North Haven, Connecticut, has a $2.9 million contract with the City to build the Harbor Brook Overflow Culvert near Amtrak Bridge MP18. Two sets of Amtrak tracks pass through the middle of this community and over the 120-year-old bridge. Owing to its deep plate-girder construction, the old structure provides only limited clearance above Harbor Brook, presenting an obstacle to stormwater flows. The City has spent more than $20 million in flood control work over the years, including the current EPI contract, to rectify the problem.

Jacking Allows Track Use
“The City of Meriden hired AECOM to design a bypass overflow culvert as a more economical alternative to raising the bridge,” said Gene Zwicharowski, Superintendent of Empire Paving’s Underground Utility Division, and a 45-year construction veteran.

“The culvert will carry overflow from Harbor Brook under the embankment that carries two active Amtrak railroad tracks, and discharge the overflow back to the Brook downstream of the Amtrak bridge. The pipes in the bypass culvert upstream of the bridge are being installed by the trenchless jacking method, with the jacking pit located in the adjoining parking lot, while conventional open-cut methods are used for the remaining culvert. Employing pipe jacking allows the continuous use of the railroad tracks during construction.”

AECOM called for the following installations: two high-density polyethylene (HDPE) pipe overflow culverts from upstream of the Amtrak Bridge at Harbor Brook to a point downstream of the bridge; steel casing pipes jacked under the Amtrak Railroad and grouting in place; HDPE water carrier pipes sleeved within the steel casing pipes and grouting in place; a concrete junction chamber; and construction of headwalls plus reconstruction of the parking lot in which the pipe culvert and jacking pit are located.

The HDPE carrier pipe have smooth 60-inch inside diameter and 67-inch corrugated outside diameter. Set 9 feet center-to-center, each carrier pipe is installed in a permanent 73.5-inch outside diameter steel casing pipe. The two 50-foot-long steel casings, comprised of joined 10-foot lengths, have a 3-foot clear distance between them, and are oriented at a 60-degree skew to the railroad track alignment.

Running Into Walls
Two existing retaining walls, comprised of stone, concrete and masonry units, run approximately parallel to, and on each side of, the railroad embankment. The contractor is demolishing portions of both walls at each end of the culvert to allow pipe penetration, while protecting the structural integrity of the walls at all times. At the upstream end of the culvert the annulus space between the steel casings and the masonry wall must be infilled with grout to accomplish a permanent, stable, water-tight penetration.
Gehl Co - Loaders/SS
Your local Gehl Co dealer
Star Equipment LTD

Zwicharowski said that EPI is self-performing most of the work such as driving steel sheeting and soldier piles, installing open cut pipe, dewatering where necessary, placing ready mix concrete, and performing site excavation, grading and paving. The pipe jacking was subcontracted to CRS Contractors – formerly Cruz Contractors – of Colts Neck, New Jersey.

While digging the jacking pit, EPI crews realized that the actual elevation of one of the existing walls differed from that shown on project plans, requiring a support-of-excavation system to be set up.

“We contracted Seifert and Associates of Naugatuck, Connecticut, to design a system to permanently support the stone wall,” he said. “This came with complications since ledge was not far below the bottom of excavation, limiting the amount of toe we were able to achieve on the steel sheeting.”

Another difficulty presented itself when some contaminated water was encountered. “We immediately contacted Recon Outfitters of Sturbridge, Massachusetts, and they came and solved the problem with a mobile water treatment system,” Zwicharowski said.

“After we dug the jacking pit and installed the earth support system, CRS set up to jack the two steel casings, which would be followed by insertion of 60-inch Sanitite Polypropylene Pipes manufactured by Advanced Drainage Systems. The pipes were supplied by Ferguson Waterworks of Newington, Connecticut,” he said. He indicated that jacking is taking place one casing at a time, and that it is a difficult procedure calling for crews to work around the clock.

Preparing to Jack
“One major challenge is installing the casing under the railroad track in a space providing only 5 feet of cover over the pipe. This requires us to use heavy, 1-1/4-inch-wall steel casing manufactured by Permalok, a Northwest Pipe Company based in Vancouver, Washington,” he said. According to the manufacturer, the thick-walled Permalok casing utilizes an interlocking push-joint system designed to withstand jacking forces and eliminate the need for butt-fusing in the field.
LBX Link Belt Excavators
Your local Link Belt dealer
Kirby Smith Machinery

“In addition, before jacking could take place, we had to install a continuous remote settlement monitoring system. This involved mounting over 40 prisms on the train tracks and soil over the proposed pipeline. The system is supplied, operated and installed by Freeman Associates of Hartford,” he pointed out.

Crews also needed to be ready to improve the stability of soft or unraveling soil if encountered. By working closely with Avanti International, the construction team was able to select a grout to improve soils stability that could be applied by injecting the earth face from inside the tunnel. They also sought and found a way to excavate soil within the tunnel that was superior to conventional mechanical or hand digging. CRS contracted Badger Daylight to employ Hydrovacs to excavate the earth. Badger Hydrovac trucks use highly pressurized water to liquefy the soil, creating a slurry type mixture. Simultaneously, this mixture is extracted by the Badger vacuum system into a truck-mounted debris tank.

How It Works
In general, pipe jacking is a technique for installing underground pipelines, ducts and culverts, according to the Pipe Jacking Association (PJA). Powerful hydraulic jacks are used to push specially designed pipes through the ground behind a shield at the same time as excavation is taking place within the shield.

PJA notes that to install a pipeline using this technique, thrust (jacking) and reception pits are constructed. A concrete thrust wall is often constructed in the pit to provide a reaction against which to jack, or a structural framework such as piles, ground anchors or other methods for transferring horizontal loads can be built. To ensure that the jacking forces are distributed around the circumference of a pipe being jacked, a thrust ring or a jacking frame is used to transfer the loads. The jacks are interconnected hydraulically to ensure that the thrust from each is the same. Furthermore, a reception pit for removal of the jacking shield is normally required at the completed end of each drive. The initial alignment of the pipe jack is obtained by accurately positioning guide rails within the thrust pit on which the pipes are laid. To maintain accuracy of alignment during pipe jacking, it is necessary to use a steerable shield.

Thick Cutting Steel Plus Powerful Jacks
For the Meriden project, CRS is utilizing a custom-made tunnel shield for 73.5-inch-diameter pipe. Measuring 110 inches long, the shell of the shield is made of 2-inch steel. It has an inside diameter of 70 inches and outside diameter of 74 inches. The 24-inch-wide shield front hood is reinforced with an additional 1/2-inch steel plate, providing a 2-1/2-inch thick cutting surface. A 10-foot length of Permalok pipe is butted up against the back of the shield and a hydraulic jacking frame capable of pushing with a force up to 584 tons is snugged against the back end of the pipe.

As the pipe advances, the encapsulated soil is removed by the Badger Hydrovac. Four hydraulic jacks inside the steering shield are operated to keep the pipe on line and grade as the jacking frame’s larger jacks push the assembly forward. At the end of the 10-foot drive, the jacking frame is backed off to allow the placement of the next length of pipe, then the procedure is repeated.

First Casing Pokes Through
By mid-July 2020, CRS had completed its 50-foot drive for the first casing. When the front of the jacking shield reached the wall, the CRS crew inside the shield removed a circular section of wall large enough to allow passage of the shield. And with a final push from the jacks, the shield poked through the wall. Workers retrieved the shield as it passed through the wall into Harbor Brook. Next, they went back to the pit to set up for jacking the second, parallel casing.

Once jacking has been completed, the carrier pipes will be inserted inside the casings, and the annular space between the pipes and the walls will be grouted for watertight seal. A 50-ton precast concrete junction chamber supplied by United Concrete of Yalesville, Connecticut, will be installed inside the jacking pit. In operation, this structure will direct overflow from the carrier pipes within the casings, to twin 60-inch carrier pipes previously installed by EPI using open-cut-and-cover means. This essentially completes the bypass culvert loop to the outlet at the downstream end of the Brook. There is still plenty of work to be done, but the job is on schedule, according to Zwicharowski.

Manitou
Your local Manitou dealer
Star Equipment LTD
Manitou
Your local Manitou dealer
Star Equipment LTD
Topcon Construction Products
Your local Topcon Positioning Systems Inc dealer
Star Equipment LTD