The replacement and rehabilitation will be led by contractors from Capital Paving and Construction, LLC., working with the Missouri Department of Transportation. Crews are following the planned schedule below:
- March 9: Crews closed both north and southbound passing lanes to begin construction of median crossovers.
- Early April: Crossovers will be utilized to direct traffic head-to-head in the southbound lanes of I-29 at the bridges. The replacement of the northbound bridge over Hopkins Creek and rehab of the northbound bridge over Route T will begin.
- Early August: Once work on the northbound bridges is complete, traffic will be directed head-to-head in the northbound lanes. The replacement of the southbound bridge over Hopkins Creek and rehab of the southbound bridge over Route T will begin.
- Late December: Work on both bridges is completed, and all lanes of traffic are restored.
- January: Median crossovers are removed, and shoulder work completed.