HONOLULU, HI — The Honolulu Authority for Rapid Transportation (HART) announces the successful completion of Pier 732, the first guideway column of Skyline’s Segment 3, which stretches from Middle Street to Civic Center Station in Kakaako, Hawaii.
“The completion of Pier 732, the first of 148 columns in Segment 3, represents a significant accomplishment for the entire HART Ohana, and our contractor, Tutor Perini, and is symbolic of all the collaboration and hard work it’s taken to get to this point,” HART Executive Director and CEO Lori Kahikina said. “Over the coming months, the public will start to see more columns in the downtown and Iwilei areas, and eventually, by the middle of next year, sections of elevated guideway. We’re very pleased with the progress the project team is making and will continue to push as we enter this next phase of construction.”
Pier 732 is located near the intersection of Nimitz Highway and Fort Street in downtown Honolulu and is supported by an underground shaft that reaches a depth of over 100 feet. The column measures 8 feet in diameter and required approximately 300 to 400 cubic yards of concrete to construct (equivalent to roughly 30 to 40 truckloads). Once the guideway structure is complete, it will stand at a height of approximately 43 feet along Nimitz Highway. The guideway height will vary along the alignment.
As noted, this is the first of 148 columns that will be installed to support the guideway along Segment 3. To date, 18 column foundations have been completed. In addition, early stage construction and foundation work has begun at the Chinatown Station, located at Nimitz Highway and Kekaulike Street.
Construction of the guideway and stations is scheduled to be complete in 2030, with Segment 3 anticipated to open for passenger service by summer 2031.














































