Crews have completed traffic shifts at the 65th Avenue site and the SR 19/39 bridge site. Pile driving efforts are complete and crews continue pouring concrete at each location. The Knight Parker Road bridges have been replaced with roadway fill, and widening of the shoulders at the 65th Avenue bridge and SR 19/39 sites is underway. The lowering of SR 19/39 has been completed with the exception of the final lift of asphalt.
“These improvements are critical and long overdue for Lauderdale County,” Simmons said. “The design-build aspect of the project expedites the ability to get the design done as soon as possible, and each part of this project will further enhance safety and efficiency for motorists and commercial traffic in Meridian.”
The $24.4 million design-build project was awarded to Key Construction Company of Madison with an anticipated completion date of summer 2023.
Traffic has steadily increased along the SR 19 corridor. Since 2017, the average annual daily traffic along this stretch of roadway has increased from 5,600 to 6,600 and is still rising. In addition to expanding to four lanes, the new grading will offer smoother riding conditions, showing significant progress throughout the area.
Your local NPK Construction Equipment Inc dealer |
---|
Kirby Smith Machinery |
WPI |
Several local roads will be realigned to tie into the new four lane roadway, making it a safer and more convenient travel experience. North Tucker Road was recently reopened to traffic after crews completed new alignment onto SR 19. The $36 million contract was awarded to W.G. Yates and Sons Construction of Philadelphia. The project is expected to wrap up in 2024.
Failed area repairs are complete. Milling and paving operations are currently underway. The nearly $8 million contract was awarded to Superior Asphalt of Byram.
On the second bridge, crews are currently working to drive piles and pour bridge caps. Earthwork and clearing operations are ongoing on the remaining two sites.
The $9.6 million project was awarded to L&A Contracting Company of Hattiesburg. Work is expected to be completed by early 2024.
Construction signs have been installed, and traffic signal detection has been upgraded. Sidewalk repairs and ADA ramps are complete, and the repair of failed areas has been completed. Milling and paving operations are nearly complete, with the exception of re-paving the driveway and side road connections remaining.
Your local Gomaco dealer |
---|
Clark Machinery |
The $5.1 million project was awarded to Dickerson & Bowen of Jackson. Remaining work is expected to be completed this winter.
The $6.4 million contract was awarded to APAC-Mississippi. The project is expected to be complete by the end of 2022.
The nearly $8 million project was awarded to Superior Asphalt, Inc. of Byram. The estimated completion date is summer 2023.
“This money will go towards activities such as survey, hydraulic analysis, roadway and bridge design, right of way acquisition, and utility relocation. Once these items have been completed, as funding becomes available, we can move to construction,” Simmons said. “Although construction of this widening project is dependent upon future funding, we are working closely with Flowood Mayor Gary Rhoads and the Legislative leadership to ensure we will have the necessary funding at the appropriate time.”
This 3.5-mile stretch of SR 25 sees an average of 17,000 vehicles daily. With an ever-growing increase in traffic, the design will include safety enhancements throughout the SR 25 corridor.
Your local Komatsu America Corp dealer |
---|
Kirby Smith Machinery |
Power Equipment Co |
WPI |
“I’d like to thank Senators Josh Harkins, Dean Kirby, and the House members representing Rankin County for assisting with funding to widen SR 25. With a preconstruction estimate of $5.5 million, this $4 million will go a long way in funding the beginning stages of this critical infrastructure improvement project,” Simmons said. “This is progress for our state and its transportation infrastructure as we work towards finding innovative ways to build and maintain a safe and reliable transportation network for future generations.”