HATTIESBURG, MS — The
Mississippi Department of Transportation (MDOT) continues making improvements to highways in south Mississippi.
“Dozens of projects are moving forward throughout southeast Mississippi, and each one of them is geared toward improving safety and increasing Mississippians’ quality of life,” said Commissioner Tom King, Southern Transportation District.
Completed Lottery Funded Projects Throughout the District
In Stone County, an 11-mile overlay project on State Route 26 from the Pearl River County line to Fairgrounds Street was recently completed. This $2.1-million project was awarded to
Huey P. Stockstill, LLC. In Hancock and Pearl River Counties, a $2.6-million thin lift overlay is now complete. This project was awarded to Huey P. Stockstill, LLC. In Jones County, a $1.2-million thin lift overlay was recently completed on State Route 29. This project was awarded to
Dunn Roadbuilders, LLC. A project to overlay seven miles of State Route 29 from State Route 149 in Stone County to north of the Stone County line in Perry County was recently completed. This $1.5-million project was awarded to
Warren Paving, Inc.Interchange Construction on Interstate 59 at State Route 42 in Forrest County
Work on an interchange construction project on I-59 at SR 42 in Forrest County is moving closer toward completion. All ramps have been opened with the exception of the westbound SR 42 to southbound I-59 loop ramp. Crews are able to begin work on the last ramp now that the old overpass has been demolished. This $24.2-million contract was awarded to Dunn Roadbuilders, LLC. It is estimated to be completed in fall 2021.
Safety Improvement Project on U.S. Highway 49 in Forrest County
Work on a safety improvement project on U.S. 49 continues in Forrest County. The project stretches from the Stone County line to South Gate Road. Currently, crews are performing grading work in the median and southbound outside shoulder. Reconstruction of the existing southbound lanes has begun to remove steep vertical curves. Existing median crossovers are currently being reconstructed at various locations throughout the project limits. Work on drainage culverts is underway as well as the construction of retaining walls. This project was awarded to
T.L. Wallace Construction and is expected to be completed fall 2022.
Reconstruction Project on U.S. Highway 11 in Pearl River County
Work on a reconstruction project that stretches from Cayten Street to Lakeshore Drive on U.S. 11 continues in Pearl River County. Work on drainage structures is nearing completion, and significant curb and paving work still remain. This work is part of phase one, which is expected to be completed fall 2022. This $14.4-million project was awarded to
Barriere Construction Company, LLC.
The second phase will include the construction of a new bridge over the East Hobolochitto Creek and is currently scheduled for construction beginning in 2023. The new bridge will have shoulders and include a protected sidewalk with a concrete barrier for pedestrians. The entire project is estimated to be completed in 2025.
Intersection Improvements on U.S. Highway 90 in Jackson County
Crews continue making headway on an intersection improvement project on U.S. 90 from Pascagoula Street to Chevron Drive in Jackson County. Currently, work on traffic signals continues, and paving work is now complete. This project is expected to wrap up late 2021. This $11.9-million project was awarded to
Mallette Brothers Construction Company, Inc..
Bridge Rehabilitation on State Route 609 in Jackson County
Progress is being made on a bridge rehabilitation of the Fort Bayou drawbridge on SR 609 in Jackson County. Currently, the gears and motors are in place for the north span of the bridge. On the south span of the bridge, the motors and gears are being installed and will need to be realigned. Work on the bridge tender house is still underway. This $20-million project was awarded to
C.E.C., Inc. and is expected to be completed late 2021.
Multiple Overlay Projects Underway Throughout Southeast Mississippi
In Wayne County, an overlay project on U.S. Highway 84 from the Jones County line stretching nine miles east is nearing completion. Currently, paving has been completed and work on permanent striping is underway. This $5-million project was awarded to Warren Paving Inc. and is expected to wrap up late spring.
In Jasper County, work on a $7.5-million mill and overlay on State Route 15 continues. The project stretches 20 miles from State Route 18 to the Newton County line. Currently, clearing has been completed and milling and paving are underway. There will also be work added to repair two landslides along the north end of the project. This project is slated to finish late 2021.
In Jackson County, a $4.8-million overlay project continues on U.S. 90. The project stretches from seven miles from State Route 57 to the West Pascagoula River Bridge. Currently, work is underway to clean and make repairs to the existing drainage culverts; paving will start soon. This project was awarded to Warren Paving Inc. and is expected to wrap up late 2021. This project is being funded by the lottery.