“These projects — some of which were recently completed or nearing completion — are a major investment into our infrastructure system that will make Mississippi a safer place to live and work,” Simmons said. “These projects will greatly improve safety and efficiency throughout the western part of our state.”
Crews are making headway on the construction of approximately nine miles of four-lane highway known as the U.S. 82 Greenville Bypass from State Route 1 to Leland. Work began on the major construction project last year.
Six box culverts have been constructed with work on two others underway. Crews are now preparing to pour deck on the Kuhn Road bridge, driving piles for the Old U.S. 61 bridge, pouring columns for a Black Bayou bridge, and paving the mainline from Kuhn Road to Old U.S. 61.
“Once complete, the Greenville Bypass will greatly alleviate traffic congestion, increase safe driving conditions, and enhance business and economic opportunities in Greenville, Leland, and surrounding areas,” Simmons said. “It is exciting to see such progress on this massive construction project in Washington County. I consider this project one of the greatest in many years in the Mississippi Delta and look forward to seeing it through.”
Your local Hitachi dealer |
---|
CLM Equipment Co |
The $137 million contract was awarded to Eutaw Construction of Madison. Work is on track to be completed fall 2025.
Crews recently completed a capacity project in Vicksburg that will improve safety and mobility in the area. The project called for the construction of the I-20 south frontage road extension to U.S. 80 in Warren County.
“The project also included repairs to five bridges within the Vicksburg city limits, further preserving infrastructure in western Mississippi,” Simmons said.
The $17.3 million contract was awarded to T.L. Wallace Construction, Inc. of Columbia.
The $39 million project was awarded to APAC-Mississippi of Jackson. Work is estimated to be completed by spring 2024.
Your local Iowa Mold Tooling Co Inc dealer |
---|
Nichols Fleet Equipment |
A project that provides improvements to the intersection of U.S. 61 and State Route 553 in Jefferson County is wrapping up. Most work is complete as the contractor awaits permanent signage to install.
The $2.7 million project was awarded to G. Rayborn Contracting of Natchez. Remaining work will wrap up by the spring.
A project to replace a bridge on State Route 27 over the Big Black River in Warren County is making headway. Clearing operations are complete, and borrow material is being hauled in to construct the new alignment. Drilled shafts are being constructed on the south end of the bridge. Crews are beginning to pour caps on the north side of the Big Black River.
The $19 million contract was awarded to Key, LLC of Madison. Work is estimated to be completed this fall.
The $4.9 million contract was awarded to Joe McGee Construction Company of Lake. Work is anticipated to be completed by spring 2024.
Your local Trimble Construction Division dealer |
---|
SITECH Tri-Rivers |
Another bridge replacement project on SR 27 is underway over Maxie Creek in Hinds County. Traffic has been moved onto the detour bridge. Crews are currently driving piles for the new bridge.
The $5.6 million contract was awarded to Key, LLC. The project is expected to wrap up this fall.
A mill and overlay of 11 miles of I-55 from the Lincoln County line to Hazlehurst is progressing in Copiah County. All clearing operations along the interstate are complete. Crews have completed half of the mainline paving.
The $16.1 million contract was awarded to W.E. Blain & Sons of Mount Olive. Remaining work is on track to be completed summer 2023.