“Each of these projects show a vital investment into our infrastructure that will make our state a better place to live and work,” Simmons said. “I look forward to seeing these projects continue moving forward and ultimately increasing safety and mobility for all central Mississippi traffic.”
The nearly $3 million project was awarded to St-Bil Grading, Inc. of Waterford. SR 18 is on track to reopen by the end of 2023, and the remainder of the project is scheduled to be completed spring 2024.
The $24.4 million design-build project was awarded to Key Construction Company of Madison.
The West Rankin Parkway project began as a Local Public Agency (LPA) project years ago. MDOT’s involvement at that time was helping administer necessary federal funds toward the local project. Later, dispersive soil was found throughout the project, forcing crews to go back and perform more dirt work, changing the overall scope of work. That contract was terminated, which allows MDOT to re-bid a different contract that will include repairs to the roadbed and ultimately move forward to the paving phase and open State Route 477 for travel.
Your local Wirtgen America dealer |
---|
Kirby Smith Machinery |
“In an effort to expedite what has been a problematic project, we have worked closely with the City of Pearl, the City of Flowood, the Mississippi Legislature, and the Governor, who signed a bill that gives MDOT more flexibility and funds to get this project to construction,” Simmons said. “Thanks to all the players involved, we have added the project to MDOT’s three year plan and are moving forward with the planning.”
Officials expect plans to be complete in the spring of 2024 and anticipate letting the project later that summer.
Work in progress includes clearing and grubbing, removal of topsoil, installation of erosion control items, excavation, box bridge construction, pipe installation, and soil-cement and lime treatment of the subgrade. The subbase has been treated with soil-cement, and asphalt has been placed in several areas.
The second phase of work consists of rehabilitating portions of the existing SR 19 and reconstructing other areas that require new cross drains and box culverts. The third phase will place traffic in the four-lane configuration, place the final lift of asphalt, and provide permanent striping.
The $36 million contract was awarded to W.G. Yates and Sons Construction of Philadelphia. The project is expected to wrap up in 2024.
Designs include future modifications planned for State Route 885 in Philadelphia. SR 885 connects SR 16 to SR 15 in the vicinity of Tolbert Chevrolet. The connector road will be reconfigured to allow one-way traffic from south to north and will reduce the potential for accidents and delays at the SR 16 intersection.
“I commend Sen. Jenifer Branning, Highways and Transportation Chairman, and the Legislature for working with us and getting this project moving,” Simmons said. “With the circular design, traffic will flow seamlessly, minimizing the chance of severe accidents and improving the overall safety and operation. Along with a smoother traffic flow, drivers will experience reduced wait times, leading to less frustration and easier commutes.”
Once let for construction, the roundabout will replace the existing traditional intersection of SR 15 and SR 16, reducing the risk of high speed, right angle collisions. MDOT officials plan to begin the Right of Way acquisition and utility relocation process later this year.
Intersection modifications at SR 494 and the State Boulevard Extension are complete. Mainline paving is underway.
The $5.4 million contract was awarded to APAC-Mississippi, Inc. Remaining work is expected to wrap up by the winter.