Because of its location and the constant road and rail traffic, the project was going to be a challenge and the need for speed was critical. As lead designer, VHB ushered the project through all phases of public outreach, permitting, design, and construction inspection. The Middlebury Bridge and Rail project was recently recognized by the 2022 PCI Design Awards program.
To pull off the accelerated construction period required years of preparation, including negotiation of the first-of-its-kind train detour allowing Vermont Railway to operate over a competitor’s line. The project also constructed a new drainage system by microtunneling through solid rock 30 feet below grade and included a number of significant mobility accommodations throughout town, allowing for continued access to downtown and its businesses while construction raced forward.
“We knew that working around the railroad schedule was going to be a challenge,” said Aaron Guyette, Transportation Lead for VHB. “Accelerated bridge construction (ABC) using precast concrete was the perfect solution to keep the project on schedule.”
This is the largest Vermont Agency of Transportation (VTrans) infrastructure project to date that takes place entirely within the National Register-listed Middlebury Village Historic District. It increased the vertical clearance for the railroad by more than three feet by excavating downward, while maintaining the existing roadway profiles and avoiding impacts to the adjoining sidewalks and historic buildings.
Your local Case Construction Equipment Inc dealer |
---|
Beauregard Equipment |
Monroe Tractor |
Working on a 24/7 construction schedule over 10 weeks, tens of thousands of cubic yards of soil and bedrock was excavated; 422 individual pieces of precast concrete fabricated in New York were assembled; 3,500 linear feet of railroad track, cross ties, and ballast was rebuilt; and both Main Street and Merchants Row were reconstructed, including new sidewalks and lighting.