New England Construction

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Middlebury Bridge and Rail Project Receives PCI Design Award

Middlebury bridge and rail project receives award
Middlebury bridge and rail project receives award
MIDDLEBURY, VT — Originally constructed in the 1840s, the Vermont Railway winds through the bustling downtown of Middlebury, Vermont, splitting the downtown and Town Green area in half. Two bridges that spanned the 20-foot-deep rail corridor, with a service life already exceeding 100 years, had deteriorated to the point where their structural integrity was threatening safety for vehicles, bicyclists, and pedestrians above, and the operation of the railroad below. The railroad corridor had also been plagued by drainage issues, poor track conditions that contributed to a 2007 train derailment, and vertical and horizontal clearance restrictions.

Because of its location and the constant road and rail traffic, the project was going to be a challenge and the need for speed was critical. As lead designer, VHB ushered the project through all phases of public outreach, permitting, design, and construction inspection. The Middlebury Bridge and Rail project was recently recognized by the 2022 PCI Design Awards program.

To pull off the accelerated construction period required years of preparation, including negotiation of the first-of-its-kind train detour allowing Vermont Railway to operate over a competitor’s line. The project also constructed a new drainage system by microtunneling through solid rock 30 feet below grade and included a number of significant mobility accommodations throughout town, allowing for continued access to downtown and its businesses while construction raced forward.

“We knew that working around the railroad schedule was going to be a challenge,” said Aaron Guyette, Transportation Lead for VHB. “Accelerated bridge construction (ABC) using precast concrete was the perfect solution to keep the project on schedule.”

This is the largest Vermont Agency of Transportation (VTrans) infrastructure project to date that takes place entirely within the National Register-listed Middlebury Village Historic District. It increased the vertical clearance for the railroad by more than three feet by excavating downward, while maintaining the existing roadway profiles and avoiding impacts to the adjoining sidewalks and historic buildings.

Esco Corporation
Your local Esco Corporation dealer
Genalco

Working on a 24/7 construction schedule over 10 weeks, tens of thousands of cubic yards of soil and bedrock was excavated; 422 individual pieces of precast concrete fabricated in New York were assembled; 3,500 linear feet of railroad track, cross ties, and ballast was rebuilt; and both Main Street and Merchants Row were reconstructed, including new sidewalks and lighting.

Wirtgen America Inc
Your local Wirtgen America dealer
WI Clark
United Construction & Forestry
Wirtgen America Inc
Your local Wirtgen America dealer
WI Clark
United Construction & Forestry
Develon
Your local Doosan Infracore Construction Equip dealer
Equipment East