Pacific Builder & Engineer

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Iowa DOT Improves Des Moines Bridge Infrastructure with 2nd Avenue Corridor Projects

by: Debra Wood
The team for Jasper Construction Services applies the high-performance concrete overlay on the River Bridge.
The team for Jasper Construction Services applies the high-performance concrete overlay on the River Bridge.
Crews demolish the west half of the Birdland Bridge.
Crews demolish the west half of the Birdland Bridge.
Crews complete pile driving on the western half of the Birdland Bridge.
Crews complete pile driving on the western half of the Birdland Bridge.
Crews pour the deck on the east side of the Birdland Bridge.
Crews pour the deck on the east side of the Birdland Bridge.
Crews place formwork on the west side of the Birdland Bridge.
Crews place formwork on the west side of the Birdland Bridge.
Crews install the north abutment on the west side of the Birdland Bridge.
Crews install the north abutment on the west side of the Birdland Bridge.
Crews drive piles for the new Birdland Bridge.
Crews drive piles for the new Birdland Bridge.
The high-performance concrete overlay is applied on the River Bridge.
The high-performance concrete overlay is applied on the River Bridge.
Crews apply the high-performance concrete overlay on the River Bridge.
Crews apply the high-performance concrete overlay on the River Bridge.
Overlay cures on the River Bridge.
Overlay cures on the River Bridge.
As part of the 2nd Avenue Corridor Construction project in Des Moines, Iowa, the city is replacing one bridge over Birdland Drive and rehabilitating a second structure over the Des Moines River.

“This project will improve the city’s bridge infrastructure for decades to come,” says Ben M. Cole, Project Engineer with the City of Des Moines Engineering Department.

About 19,000 vehicles drive the north-south corridor daily. A traffic study found higher than average crash rates on 2nd Avenue, particularly at intersections. The bridge projects are a precursor to a larger corridor improvement project in the next couple years.

The department hired a consultant to examine both structures and make recommendations for bringing the bridges to current standards and align with the city’s goal of improving transportation for all modes of users.

The team used ground-penetrating radar to confirm the placement of reinforcing steel layout on the river bridge and completed a 3D LIDAR point cloud survey to learn the elevations of the river bridge piers, beams, and other elements.

Doosan Infracore Portable Pwr
Your local Bobcat dealer
Pape Material Handling

Stanley Consultants of Muscatine, Iowa, serves as the engineer of record. There were no environmental concerns.

The approximately $10 million bridge project received $2 million from the Iowa Department of Transportation, which awarded the project to Jasper Construction Services of Newton, Iowa. Jasper, established in 1997 as a paving and flatwork firm. The company evolved in 2009 to also perform bridge rehabilitation work.

“What’s unique about this project is that it includes two bridges close together, with each bridge having a different scope of work,” says Cliff Rhoads, President of Jasper. “The schedule was fairly tight, and we worked over the winter to meet the incentive deadline at the end of May.”

Work began in April 2022.

The 2nd Avenue Bridge
The 500-foot-long, five-span, riveted plate steel girder 2nd Avenue Bridge over the Des Moines River was built in 1936 and was widened in 1985. The project includes reconstruction of the bridge deck, with four 11-foot-wide traffic lanes, a 3-foot shoulder, an 11-foot-wide multiuse trail on the east side and a 5-foot wide sidewalk on the west side of the bridge.

Jasper self-performed most of the river bridge work without getting in the water. The company installed a safe span bridge platform, suspended under the bridge to catch concrete debris while removing the suspended sidewalks on each side of the structure. Then crews used the platform to form up the new suspended sidewalks from the bridge beams, using an overhang bracket system, Rhoads explains.

The work includes adding a new fiber-reinforced, high-performance concrete overlay (HPC-O) on the river bridge. It has a higher slump than traditional overlay mixes.

“The HPC-O overlay has a higher cement content,” Cole says. “It creates a denser and more durable overlay, which is less permeable, leading to lower chloride intrusion. The downside with these HPC-O mixes is the higher cement content in these, which makes them more prone to drying and shrinkage cracking.”

To help mitigate this issue, the department added macro- and micro polypropylene fibers to the mix, which was a first for the city.

Additionally, crews fully sand blasted the existing bridge beams and bearing assemblies and painted the bridge with a new coating system. Minor modifications at the bridge abutments were made to accommodate the revised bridge cross-section and new expansion joints.

Maintenance of traffic presented challenges for the team. The bridge has been reconstructed in stages to allow one lane of traffic in each direction to pass throughout the duration. One sidewalk also has remained open. “We could not just close down the bridge,” Rhoads says.

The west side has been rebuilt and repainted with a nonhazardous paint. Now, work takes place on the east side of the river bridge.

The Neal Smith Recreational Trail runs along the north side of the river and has remained open throughout the bridge construction. A protective scaffolding system was installed to allow safe passage for the approximately 300,000 annual trail users. The trail will be realigned to pass under the new Birdland bridge to decrease closures related to flooding by the river.

The Birdland Drive Bridge
The 2nd Avenue Bridge over Birdland Drive, about 125 feet away from the river bridge, was constructed in 1936 and widened in 1985. The 98-foot, three-span, rigid-frame bridge had deteriorated to the point the department determined it was more cost effective to replace the three-span structure rather than rebuild it. The cross-section and handrails will match the rehabilitated river bridge.

Crews removed one half of the old bridge, dropping it to the ground and hauling the concrete and rebar away.

“Because of its rigid structure, we were able to remove half of it without compromising the overall integrity of the bridge,” Cole says.

Again, crews staged the construction to complete southbound lanes and then the northbound lanes and coordinated with the river bridge work. Birdland Drive, a local road below the bridge, has been closed throughout the construction.

The new 124-foot-long, three-span, concrete-slab bridge has integral abutments, supported by HP 10 X 57-foot steel piles driven to bedrock. HP 14 X 73 steel piles, driven to bedrock, support the bridge. The piers are fully incased in concrete.

“Due to the location of a buried 42-inch sanitary force main under the Birdland Drive bridge, we had some initial concerns with vibration from the new driven H-piles,” Cole says.

The team brought in WJE of Northbrook, Illinois, to monitor vibration during the pile driving of the closest pier. No vibrations above the determined threshold were noted during the construction.

The bridge deck has a traditional concrete slab, poured to a depth of 1 foot, 8.5-inches-thick, with no overlay. Crews poured the concrete in place with falsework, supported by timber piles and steel beams. The engineers were unable to increase the vertical clearance on Birdland Drive under the bridge.

Traffic will start flowing in early summer, and final site restoration is scheduled to finish this fall.

“I’m proud we were able to minimize disruptions to the public by staging the project, to keep one lane open in each direction along 2nd Avenue, find a solution to protect the trail and keep that open for recreation, as well as implement the city’s first fiber-reinforced concrete overlay,” Cole concludes.

Additional Work on the Corridor
Other work is taking place along the 0.75-mile 2nd Avenue corridor, under a $16.5 million contract. As part of the River Bend and King Irving Sewer Separation project – separating the sanitary sewer from the stormwater sewer – crews are placing a new storm sewer on the west side of 2nd Avenue from College Avenue to the Des Moines River. This work required an additional 4 feet of right-of-way and will take place in 2024 and 2025.

Future work includes reconstructing four-lane 2nd Avenue from University Avenue to the Des Moines River. The 9-foot-wide lanes will be replaced with 11-foot-wide lanes, new curbs and 5-foot-wide sidewalks. The intersections with Forest Avenue and Clark Street will be realigned and left-turn lanes added at select intersections to increase safety. The city expects this separate project will begin in 2024 and cost $16.5 million.

Photos courtesy of the City of Des Moines

Superior Industries
Your local Superior dealer
Westate Machinery Co
Superior Industries
Your local Superior dealer
Westate Machinery Co
Volvo CE
Your local Volvo Construction Equipment dealer
PacWest Machinery