The scope of work included demolition of an existing concrete relieving platform, dry excavation, combi-wall bulkhead installation, construction of the new wharf which included wharf piling, mechanical and hydraulic dredging, mudline/shoreline protection system, and mooring and breasting system, plus the rehabilitation of the existing Berth 7 fender system. McCarthy self-performed all aspects of the project except for hydraulic dredging, electrical, and crane rail installation.
Over 1,400 steel piles were installed on this project. The new berth also had to be constructed without disrupting access to Berth 7, requiring careful coordination while vessels were docked. McCarthy also worked to protect the shoreline, using a grout-filled mattress system in lieu of the originally designed 30-inch riprap, thereby preventing future maintenance dredging obstructions.
For one of the unique aspects of the project, McCarthy built a roll on/roll off (RORO) dock structure which allows for vehicles and large equipment to unload and load from a vessel to the wharf. This structure can be adapted to become a ship-to-shore crane rail berth when post-Panamex gantry cranes are installed. This flexibility ensures the new dock has the ability to meet the diverse needs of Port Freeport.
“McCarthy has extensive experience in building and rehabilitating port and marine projects on the Texas coast, and this project once again allowed our team to showcase our expertise,” said Fitz O’Donnell, Senior Vice President of Operations for McCarthy. “We were honored to work with Port Freeport on such an important project as they work to support commerce in the region.”
Your local JCB North America dealer |
---|
Monk JCB |
South Star JCB/Meinecke |
ASCO Equipment |
BOSS JCB |
Berth 8 was dredged to minus 51 feet, matching the depth of the Freeport Harbor Channel Improvement Project, allowing it to handle newer, larger container vessels transiting the expanded Panama Canal.
Port Freeport is ranked nationally 6th in chemicals, 19th in total tonnage, and 26th in containers. The Freeport Harbor Channel serves Alliera, Atlantic Container Lines, AMPORTS, BASF, Chiquita Fresh N.A., Dole Fresh Fruit, The Dow Chemical Company, Enterprise Products Partners, ExxonMobil, Freeport LNG, Ford Motor Company, General Motors, Glovis, Grimaldi Lines, Hoegh Autoliners, Kirby Marine, Liberty Global Logistics, Mammoet, MEGlobal, NYK RORO, Oceanus Line, Phillips 66, Riviana Foods, Inc., Sallaum Lines, Tenaris, U.S Department of Energy, Volkswagen Group of America, and Vulcan Materials Company.
McCarthy has worked at various ports along the Gulf Coast for more than 30 years. McCarthy’s experience in marine construction spans an array of project types including petrochemical liquid terminal facilities, bulk cargo handling terminals, deep water container terminals, and ship docks. McCarthy undertakes complex projects for public clients such as Port Freeport, Port Beaumont, and Port Houston, as well as for private mid-stream clients and EPC firms servicing oil and gas and petrochemical clients.