Complete Concrete Overcomes Complications to Bring New Life to Aging Infrastructure in Hot Springs, South Dakota

by: Larry Bernstein
A retaining wall is constructed near 6th Street for the Hot Springs Urban Reconstruction project.
A retaining wall is constructed near 6th Street for the Hot Springs Urban Reconstruction project.
On the new 6th Street alignment, crews work on a dip bridge tie-in.
On the new 6th Street alignment, crews work on a dip bridge tie-in.
Aerial view of the suspended sidewalk
Aerial view of the suspended sidewalk
Aerial view of concrete placement on North River Street
Aerial view of concrete placement on North River Street
Crews install a storm sewer on North River Street.
Crews install a storm sewer on North River Street.
Curb and gutter installation takes place near the Courthouse Bridge.
Curb and gutter installation takes place near the Courthouse Bridge.
A storm sewer is installed on North River Street.
A storm sewer is installed on North River Street.
Sanitary sewer main upgrades progress near the Courthouse.
Sanitary sewer main upgrades progress near the Courthouse.
The South Dakota Department of Transportation (SDDOT) is nearing the conclusion of the Hot Springs Urban Reconstruction project in Hot Springs, South Dakota. Located in the southwestern part of the state, the town has a population of approximately 3,500. Despite having a small population, Hot Springs is a popular tourist destination due to the springs and its proximity to other attractions like the Black Hills.
Urban Street Reconstruction Project
SDDOT describes the Hot Springs project as an urban street reconstruction project. Work is taking place along a 2-mile stretch on U.S. 385 — which runs from Texas to south-central South Dakota — and U.S. Highway 18. Locally, the route is known as North River Street, Battle Mountain Avenue, Jennings Avenue, South Chicago Street, Jensen Highway, and Fall River Road. The four-lane roadway has an average daily traffic of 5,000 along the project area.

The area has not had a major rebuild in more than 50 years and is at the end of its useful life. The existing curb and gutter are deteriorating, and the asphalt pavement is rutting and cracking. The road surface is rough and traps water in the ruts.

“The lanes are narrow and are difficult to maneuver, and the alignment is not ideal,” said Tim Wicks, a Project Engineering Supervisor for SDDOT. Other issues include the area utilities that need an upgrade.

The project will focus on the reconstruction of the four-lane highway with Portland Cement Concrete (PCC). Wicks said that the team chose PCC Pavement because it is more durable, will not rut, and requires less maintenance. A new suspended sidewalk will also be installed at street level, hanging on the outside of the retaining wall for Fall River.

“The idea was to have an aesthetically pleasing walkway and to make more room for parking and a larger sidewalk,” Wicks said.

Other project elements include:

  • Updating storm sewer equipment in conjunction with the City of Hot Springs’ water and sanitary sewer main upgrades
  • Replacing bridge approach slabs so they can be tied into the concrete pavement
  • Street lighting
  • Curb and gutter

Wicks said that upon completion of the project, the highway will meet current standards for intersections, ADA access, and lighting.

Challenges Along the Way
The Hot Springs reconstruction project is taking place in the heart of the city, making it an urban project.

“In general, urban projects are very challenging because of the presence of existing utilities beneath the roadway surface,” Wicks said. Replacing old infrastructure, including aging pipes (water and sewer) has slowed the project and has been more extensive than anticipated. Sewer backups have frustrated local business owners.

The team has discovered many unknown pipes, vaults, culverts, etc., that did not appear on the plans. One example of this is the existing deteriorated sewer lines that appeared to be left in place on the plans. New storm inlets were placed above these sewer lines with only about 6 inches to 8 inches of cover.

“The exact locations of the utilities are not always available, so adjustments need to be made in real time while the construction is in progress so everything can remain functional and service interruptions are kept to a minimum,” Wicks said.

The discoveries have led to regular changes in the scope. For example, after the project was awarded, the city discovered that an additional 2,000-plus linear feet of water main services needed to be replaced.

A second challenge the team faces is related to the width of the highway. “The narrowness of North River Street is making it difficult and sometimes impossible to maintain two-way traffic,” Wicks said.

The contract requires access to all residences and businesses while maintaining traffic flow and keeping delays as short as possible. In certain places, there is only enough room for one-way traffic. Therefore, each direction takes turns, and the traffic flow is controlled with temporary traffic signals.

SDDOT made these stipulations to help local businesses and keep traffic flowing. The construction crews and SDDOT are in constant communication, and they adjust locations and elevations as soon as possible to minimize the duration of construction.

The working conditions are made more complicated by the area buildings. The over 100-year-old buildings that border the project require 24/7 vibration monitoring and non-typical construction methods. The aged buildings have led the team to use smaller equipment for demolition and removal. They use low-frequency vibration methods for subgrade compaction.

The team has also put extra care into traffic and pedestrian accessibility. According to the City of Hot Springs’ website, Hot Springs began catering to veterans in the early 1900s and became known as “The Veteran’s Town” around WWII. The community has facilities geared toward veterans and includes them “in the everyday lives and activities of Hot Springs residents."

Because of the city’s veteran residents, every temporary route must be ADA-compliant. However, the area outside the project location is not ADA-compatible, which complicates the process for the team.

This project was in design for nearly 12 years before the city put it out for bid. Like everything else, plans age. There have been over 30 revisions to the plan since work began.

Local Contractor
Complete Concrete, Inc., which is headquartered about 60 miles from Hot Springs in Rapid City, South Dakota, is serving as the general contractor for the project. The firm bills itself as an expert in drilled foundations, concrete paving, and general contracting. Complete Concrete also has a good deal of experience with urban reconstruction projects.

The firm has worked with SDDOT regularly for more than 15 years. “Complete Concrete and their subcontractors have the equipment and experience to complete the work that is required for this urban street reconstruction project,” Wicks said. Along with being the lowest bidder, these factors led the contractor to win the project.

Financing and Schedule
The majority ($25 million) of the $31 million project budget is dedicated to the highway reconstruction component. The suspended sidewalk element is $3.9 million. The remaining $1.7 million is for the utilities.

The project is on budget as of the writing of this article. Wicks credits this to the team sticking to the original project design as much as possible. However, the additional water line work drove up the project cost. Wicks said that additional budget approval is available for necessary additions to the work, per the underground utility component of this project.

Begun in March 2021, the original timeline for the project called for a 2022 completion date. Yet, multiple rain and snow storms delayed the projects for days after they took place. This issue and the unanticipated utility issues have led to a new anticipated construction completion date of December 2024. The project is beyond the original schedule.

“The unknowns of the locations and the conditions of the underground utilities along with additional water and sanitary sewer work have been the biggest contributing factor to project delays,” Wicks said.

Upon completing the Hot Springs Urban Reconstruction project, locals and tourists will enjoy a new modernized roadway that should meet the public’s needs for 40 to 50 years with very little maintenance. Pedestrians will also enjoy a new walkway that is ADA-compliant.

Project Partners
  • Owner: South Dakota Department of Transportation
  • Project Engineer: Avid4 Engineering, Rapid City, South Dakota
  • General Contractor: Complete Concrete, Rapid City, South Dakota (concrete paving)
  • Subcontractors: DRM (underground utilities and earthwork), Muth Electric (lighting and signalization), TSC (traffic control), Three Sons (erosion control, seeding, sodding), All Metal (city’s suspended sidewalk)
LBX Link Belt Excavators
Your local Link Belt dealer
Hayden-Murphy Equipment Co
LBX Link Belt Excavators
Your local Link Belt dealer
Hayden-Murphy Equipment Co
Komatsu Dealer Program
Your local Komatsu America Corp dealer
Road Machinery and Supplies Company