Wright Brothers Nears Completion on Phase Two of Chattanooga’s I-75/I-24 Interchange Overhaul

by: Larry Bernstein
Crews are currently working on phase two of the I-75/I-24 interchange modification project, anticipated to be complete in late summer 2025.
Crews are currently working on phase two of the I-75/I-24 interchange modification project, anticipated to be complete in late summer 2025.

Located in southeastern Tennessee, downtown Chattanooga is just 5 miles from the Georgia border. One of the main routes that drivers take between the two states, Interstate 75 (I-75), traverses the entire state of Tennessee and runs from Florida to Michigan. The route comes together at Interstate 24 (I-24), which runs from Chattanooga to Illinois. At the I-75/I-24 interchange, the Tennessee Department of Transportation (TDOT) and general contractor Wright Brothers are nearing completion on a project that will offer drivers multiple benefits.

Two Projects, One Result

Since it was constructed in the early 1960s, the interchange has been widened. While the widening helped with capacity, the average daily traffic (ADT) in the area continues to grow. In 2023, the ADT on the interchange was 137,000, and it is expected to reach 155,000 in 2043.

The project is needed to improve the interchange operations, including safety, and make it more reliable. According to Daniel Oliver, Assistant Chief Engineer of Region Two, where the project is occurring, a primary safety issue is caused by the weaving that occurs as drivers enter the interchange.

The current I-75/I-24 interchange modification project is phase two, with the first phase being completed in 2021.

“There are multiple factors behind dividing the project into two phases,” said Rae Anne Bradley, Regional Communications Officer for TDOT. “However, the primary reason was funding, as Tennessee is a pay-as-you-go state.”

The scope of the first project included widening each leg of the interchange, constructing a new on-ramp to provide access to both I-75 and I-24, 11 new bridges, and two I-24 overpasses along Spring Creek Road.

“We split the project into two phases to minimize temporary construction as much as possible,” Oliver said. “We didn't want to build something that had to be torn out later.”

The current project has three segments. The first is on I-24, the second is on I-75, and the third, according to the project page on TDOT’s website, is on interstate-to-interstate ramps within the I-75 and I-24 interchange. The website said that “ramps previously reconstructed during Phase I of the project will be resurfaced and restriped to create additional travel lanes. Overhead signs will be adjusted to match the new interchange layout.”

The primary element of the project is to add one lane in every direction. This includes adding a lane to all interchange ramps, a 1-mile-long lane on I-75 in each direction, and a 1.5-mile lane on I-24 in each direction.

Other work on I-75 includes:

  • Improving the southbound entrance ramp to eliminate a merge
  • Replacing median barriers, guardrails, signing, and lighting
  • Rehabilitating existing concrete pavement
  • Replacing the I-75 bridge over the CSX railroad

The additional work on I-24 includes: