With an average daily traffic count of 370,000 vehicles a day, the I-405 in northwest Orange County at the border with Los Angeles County is one of the most heavily traveled highways in the nation. Both the regular lanes and carpool lanes are congested during rush hour and on the weekends and the traffic is expected to increase by 30 percent by 2040.
“The I-405 Improvement Project is critical to accommodate the expected growth in employment, population, and housing throughout the region,” explains Darrell E. Johnson, CEO of OCTA.
The project will cover a 16-mile stretch of highway which passes through nine cities with a population of about 1.1 million.
One regular lane in each direction of I-405 is being added along with a second lane in each direction that will combine with the existing carpool lanes to create the 405 Express Lanes.
Your local LeeBoy dealer |
---|
Brandeis Machinery |
In addition to the added lanes, the project involves reconstructing more than 18 bridges that span the freeway and improving interchanges and local streets. Improvements are being made to freeway entrances and exits. Finally, retaining walls and sound walls will be constructed at certain points along the interstate.
There’s also coordination with multiple public and private partners. Johnson elaborates, “This project involves close coordination with state and local agencies, such as Caltrans, the County of Orange and the South Coast Air Quality Management District, as well as the neighboring cities. It is estimated that more than 200 sub-contractors and 300 material suppliers will have worked on the job over the life of the project, with 130 currently active subcontractors and consultants.”
Over the course of construction, the team has come across several unexpected issues along the site. Contaminated soil, groundwater, and other differing site conditions have arisen. To deal with these issues and mitigate potential delays, OCTA has worked closely with Caltrans, the cities, OC 405 Partners, and others to quickly gain consent to revise construction plans.
OC 405 Partners, a joint venture between OHL USA and Astaldi Construction, USA, is the contractor for the project. OCTA also relies on the contractor to find ways to make up time in other areas of the project.
Johnson gives an example of a strategy the team has put into place to keep the project on schedule. Some of the bridges that are being reconstructed as part of the I-405 Improvement Project are being demolished and reconstructed one half at a time, while others are being fully demolished and rebuilt in one stage. “To help save time on the overall project schedule, we worked with our contractor, Caltrans and the cities to convert four bridges that were originally planned to be rebuilt in two stages, to one stage,” Johnson says.
Your local Atlas Copco CMT USA dealer |
---|
Brandeis Machinery |
Utility relocation has also proven to be a challenge. During the planning phase, it was determined that certain utilities would not need to be relocated. However, as work on the project progressed, it became apparent that some of them would need to be moved. To maintain the schedule, OCTA has partnered with various utility owners to expeditiously relocate these utilities in time for work to continue.
Enabling a continuing traffic flow both on the interstate and local streets during construction has also been a concern. No surprise since the project includes replacing 18 bridges, widening four bridges, constructing four new bridges, reconstructing approximately 50 on- and off-ramps, widening the freeway itself, and constructing a significant amount of new retaining and sound walls. Therefore, OCTA developed a transportation management plan to minimize the impacts to drivers and improve safety and regularly updates it as needed.
Another challenge has been getting the word out about construction to the thousands of diverse residents and businesses near I-405. The team has used the traditional communication methods, including e-blasts, the project website, social media, and distributing fliers to homes and businesses. They also use geofencing campaigns to target residents and commuters that live and drive through specific areas of the I-405 Improvement Project.
“This method of advertising allows OCTA to select a 1-mile radius near major construction work,” Johnson says. “If someone enters that zone with their smartphone, laptop or tablet, they may begin seeing I-405 Improvement Project construction alerts on the apps they use.”
The breakdown of sources and funds is the following:
- Measure M: $1.3 billion,
- TIFIA: $629 million,
- State: $89.8 million,
- Federal: $45.6 million
Your local Wacker Neuson Corp dealer |
---|
Burris Equipment |
The TIFIA loan is financing the 405 Express Lanes. Toll revenue collected beyond what it costs to repay the TIFIA loan will fund transportation improvements for the 405 corridor. The project is currently on budget.
The project began in early 2018 and is on schedule to be complete in late 2023. Johnson says the keys to keeping the project on schedule are communication and closely monitoring progress against the baseline project schedule.
“If work at any critical location is hindered, it may cause delays to the overall project,” Johnson says. “The project team closely monitors progress throughout the project on a weekly basis, anticipating future potential risks and preparing mitigation plans to keep the project on schedule.”
Upon completion, the project will help ease traffic congestion for commuters. It will also help improve traffic flow in the communities near the 405 Freeway, with improvements being made to local streets and freeway on- and off-ramps. Pedestrians and bicyclists will appreciate the project’s results as well since every bridge replacement includes adding sidewalks and bike lanes on both sides of the street, making it easier and safer to bike and walk through these communities.
Construction Started: 2019
In Progress
Anticipated to Open: Early 2022
Bolsa Avenue Bridge
Construction Started: 2019
In Progress
Anticipated to Open: Late 2022
Your local Wirtgen America dealer |
---|
Brandeis Machinery |
Bolsa Chica Road Bridge
Construction Started: 2019
In Progress
Anticipate to Open: Late 2021
Brookhurst Street Bridge
Construction Started: 2020
In Progress
Anticipated to Open: Mid-2023
Bushard Street Bridge
Construction Started: 2019
Complete
Opened: October 2020
Edwards Street Bridge
Construction Started: 2019
In Progress
Anticipated to Open: Late 2021
Edinger Avenue Bridge
Construction Started: 2020
In Progress
Anticipated to Open: Late 2021
Your local Wirtgen America dealer |
---|
Brandeis Machinery |
Fairview Road Bridge
Construction Started: 2019
In Progress
Anticipated to Open: Early- to mid-2022
Goldenwest Street Bridge
Construction Started: 2018
In Progress
Anticipated to Open: Early- to mid-2022
Harbor Boulevard Bridge
Construction Started: 2019
In Progress
Anticipated to Open: Mid-2022
Heil Avenue Pedestrian Bridge
Construction Started: 2020
In Progress
Anticipated to Open: Mid- to late-2021
I-405-SR-73 Express Lanes Connector
Construction Started: 2021
In Progress
Anticipated to Open: Mid- to late-2023
Your local Takeuchi Mfg Ltd dealer |
---|
Brandeis Machinery |
Magnolia Street Bridge
Construction Started: 2018
Complete
Opened: May 2021
McFadden Avenue Bridge
Construction Started: 2018
Complete
Opened: October 2020
Newland Street Bridge
In Planning
Anticipated to Close: Late 2021
Santa Ana River Overcrossing
Construction Started: 2019
In Progress
Anticipated to Open: Late 2021
Slater Avenue Bridge
Construction Started: 2018
Complete
Opened: August 2019
Your local Komatsu America Corp dealer |
---|
Brandeis Machinery |
Springdale Street Bridge
In Planning
Anticipated to Close: Early 2022
Talbert Avenue Bridge
Construction Started: 2019
Complete
Opened: April 2021
Ward Street Bridge
Construction Started: 2021
In Progress
Anticipated to Open: Late 2022
Warner Avenue Bridge
Construction Started: 2021
In Progress
Anticipated to Open: Mid-2023
Westminster Avenue Bridge
Construction Started: 2019
In Progress
Anticipated to Open: Mid- to late-2022
Your local Bobcat dealer |
---|
O'Leary's Contractors Equipment & Supply |