Rocky Mountain Construction

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Nashua Projects Help Strengthen New Hampshire Electric System

by: Paul Fournier
TF Moran Inc. surveys jobsite for modernization of Eversource Energy’s Amherst Work Center in Nashua, New Hampshire, as earthmoving crews prepare site for new line truck garage.
TF Moran Inc. surveys jobsite for modernization of Eversource Energy’s Amherst Work Center in Nashua, New Hampshire, as earthmoving crews prepare site for new line truck garage.
New Hampshire’s largest electric utility is upgrading two aging facilities in Nashua as part of a 10-year, $1 billion investment to improve the state’s electric distribution system.

Eversource Energy’s latest projects in the Granite State’s second largest city (population 90,000) involve renovating the company’s Work Center on Amherst Street, (AWC), which is already underway, and the upcoming replacement of an outdated electric power substation in the city’s millyard area. The AWC project will convert an existing garage into office space, and construct a new garage, while the new 14,000-square-foot power substation will be accompanied by a new access road. Both facilities were built about 70 years ago and are seriously outmoded and undersized.

Concord, New Hampshire-based North Branch Construction is the general/building contractor for the AWC structures, with James Schwartzkopf as Director of Project Management. TFMoran Inc. of Bedford, New Hampshire, is responsible for civil and traffic engineering, land surveying, and landscape architecture services for the two Nashua facilities, with Nicholas Golon, P.E., Senior Project Manager serving as Engineer of Record. Eversource’s Project Manager is Alan Rowe.

Busy Site
The AWC project calls for more than doubling the 7,597-square-foot office space in the existing building by converting the attached garage space of 9,637 square feet to offices, bringing the total new office space to over 17,200 square feet. The refurbished office building will be 25 feet tall. North Branch is also building the new 14,500-square-foot garage, which has a footprint of roughly 98 feet by 148 feet and is about 21 feet tall.

Located at 370 Amherst Street, the AWC jobsite measures about 4.8 acres – not overly large when considering the amount of work that has to take place there. The jobsite is accessed through a single stabilized construction entrance for trucks, equipment and materials from one of the busiest thoroughfares in the city. Amherst Street, also serving as NH Route 101A, experiences about 30,000 vehicles each day in the vicinity of the AWC. The jobsite is essentially a square formed by Avard Street, Cotton Road, and two nameless private streets. It is delineated by a 6-foot chainlink perimeter fence that eventually will be replaced by an 8-foot security fence.

Controlling Stormwater

Before construction could get under full steam at the site, work crews created a 50-foot by 20-foot stabilized entrance roadway for the trucks and heavy equipment that would soon be transforming the appearance of the AWC grounds. Workers formed the entranceway by placing a spun bound filter cloth over the existing ground and topping the cloth with 12 inches of 3- to 6-inch stone. With the construction entrance taken care of, their attention turned to wrapping the entire site with a compost-filled silt sock for erosion control. For additional environmental protection, the engineers had called for the establishment of bio-retention areas at three corners of the site.

Case  - CE
Your local Case Construction Equipment Inc dealer
Century Equipment

Bio-retention areas remove contaminants and sedimentation from stormwater runoff. While the design of these areas may vary from site to site, generally they consist of a grass buffer strip, sand bed, ponding area, an organic or mulch layer, planting soil, and plants. Stormwater passes over and through the sand, which slows down water flow and spreads it along the length of the ponding area. The ponding area is graded with a depressed center, forming a shallow pool. Ponded water gradually infiltrates the bio-retention area, is evaporated, or absorbed by plants. The bio-retention area is usually graded to divert excess runoff away from itself.

Equipment Fleet Prepares Site
Before engaging in new structural work, construction crews prepared the site by removing or demolishing existing poles, trees, concrete aprons, asphalt pavement, buried and overhead utility lines and numerous other items. Furthermore, a substantial volume of existing soil had to be stripped and stockpiled on site for possible screening and later reuse. All of this site preparation required the use of sizeable pieces of heavy equipment including a dozer, loaders, excavators, and soil compactors (see accompanying sidebar). In addition to this, site traffic typically includes trucks transporting demolition and construction debris to state-approved off-site disposal areas, while other trucks enter the site with materials and equipment for new construction. Some materials are offloaded via forklifts and other material handling equipment at designated staging areas, or in the case of ready mix concrete, emptied into forms for the building footings, foundation walls and floor slabs. Moreover, steel erection for the new structure calls for the use of cranes and boom lifts.

While construction proceeds, stockpiles grow, some construction materials are placed in storage areas till needed, and mobility becomes more challenging for equipment operators and construction team leaders charged with managing project logistics.

Stabilization Protects Disturbed Areas
As site preparation continues, environmental protection is a top priority. For example, all areas of disturbed soil must be stabilized as soon as possible and no more than 45 days after initial disturbance. If an area is not slated for paving, “stabilized” means it has to have established vegetative cover plus stone, riprap or erosion control blankets in place. In areas that are to be paved, “stabilized” means that base course gravels that meet New Hampshire Department of Transportation standards for road construction have been installed. In line with this, the paving that takes place during the final construction phase is designed for heavy loads. The pavement structure consists of 15 inches of bank run gravel, 9 inches of crushed gravel, and 4-1/2 inches of bituminous concrete (2-1/2 inches of binder, 2 inches of wearing course). Much of the pavement – about 2800 square yards, is for approximately 125 10-foot by 20-foot parking spaces.

After installing environmental controls and performing general earthmoving, work crews began installing underground utilities. This involved numerous trench excavations for 12-inch HDPE plastic stormwater pipe, 6-inch SDR35 PVC 6-inch sanitary sewer pipe, 6-inch ductile iron fire-service water pipe, 3-inch ductile iron domestic-service water pipe, and various gas service pipe.

Building construction began at AWC early in 2020 and was well underway as this report went to press.

Investments Modernize Electric System
According to Eversource, the Nashua projects are two examples of the significant investments the company is making throughout New Hampshire to strengthen and modernize the electric system. Eversource provides electricity to more than 519,000 homes and businesses in 211 cities and towns.

One of the company’s largest single investments is the Seacoast Reliability Project (SRP), a 13-mile 115 kV transmission line designed to ensure reliable power for several communities in the coastal region. The SRP, constructed almost completely within existing rights of way between substations in Madbury and Portsmouth, was energized on May 29, 2020. Eversource invested more than $126 million to construct the project.

Volvo Roadbuilder
Your local Volvo Construction Equipment dealer
Faris Machinery

Other projects illustrating company investments include the delivery of new switchgear equipment to the Emerald Street substation in Keene in mid-April 2019 as part of a project to modernize its electric system, and delivery of a new transformer and installation of new automation technology to the company’s Messer Street substation to enhance reliability for customers in the Laconia area. Both projects are designed to improve Eversource’s ability to remotely isolate trouble spots and quickly re-route power to customers.

SITECH
Your local Trimble Construction Division dealer
SITECH Northwest
SITECH Rocky Mountain
SITECH Southwest
SITECH
Your local Trimble Construction Division dealer
SITECH Northwest
SITECH Rocky Mountain
SITECH Southwest