The generators will power a water treatment plant and an intake plant for WEB Water, which has a service area that reaches customers in 17 counties, 14 counties in South Dakota and three counties in North Dakota. Each generator will run approximately 300 hours per year.
“The intake plant consists of six pumps, where they pump water out of the Missouri River and then it gets pumped three miles up the hill to the treatment plant where the water is treated,” said Steve Bruce, Customer Account Manager at Butler Machinery. “From there it is fed out down a line to the customers.”
The delivery and installation of the generators took two days total, with the help of six people from the trucking company, four from the crane company, two from the electrical contractor, and four from Butler Machinery.
“Any time you have an oversized load like that, it does require pilot cars, one in the front and one in the back,” Bruce said. “Also, it’s a route that the state of South Dakota dictates which highways they have to take so they don’t have any problems hitting power lines or bridges.”
Your local Link Belt dealer |
---|
Hayden-Murphy Equipment Co |
TJ Potter Trucking had to use custom-built trailers to be able to transfer the large generators from point A to point B. The weight and width of the trailer could be adjusted to accommodate the load.
“When you get a load like that, there are very few companies that have the equipment to haul that. … It took TJ Potter all day to drive 300 miles, and then we started the loading the following Monday,” Bruce said. “The location at the treatment plant was relatively easy to get them there, but for the intake plant they had to go down a gravel road, down a steep incline next to the Missouri River. Thankfully, the weather was good, so we didn’t have any mud to deal with.”
The truck carrying the generator headed to the intake plant had to be transferred over to a shorter trailer in order to safely navigate the gravel road. The truck traveled nearly three miles at less than 5 mph, around a hairpin turn, in order to get to the site at the water’s edge of the Missouri River.
“The trailer they originally had it on was too long for the roads,” Bruce said. “So they actually had to put it on a trailer that was not as long as the one that they used to haul it up there. So that took a little bit of extra time to transfer it over to the other trailer, but we were still able to do it in a day.”
“The crane company had to do an eight-point pick, which requires two spreader bars located on the crane,” Bruce said. “From the spreader bars, straps come down, and there are four lifting points on each side of the enclosure. So they had eight total points that they had to pick off of. Once they had that hooked up, they were able to pick the generator straight up and set it on the pad…It was a long day, but we were able to pick both up that day and get them set on the pad.”
Your local Volvo Construction Equipment dealer |
---|
Nuss Truck & Equipment |
The delivery and installation of the Caterpillar generators was a first-of-its-kind project for Butler Machinery, because of the physical size of the units.
“The length, width, and height of them – these are definitely two of the biggest generators that I’ve been involved with,” Bruce said. “They’re also the first Tier Four Final generator sets that Butler Machinery has done in that size.”
Butler Machinery offers products and services to support a variety of industries, including construction, agriculture, governmental, demolition and scrap handling, mining, landscaping, and power generation. The third generation family-owned company serves North Dakota, South Dakota, and Clay County, Minnesota.