Construction on Highway 60 in Watonwan County is a two-year project that started in June of 2018 and is expected to be complete in the fall of 2019. Thirteen miles of Highway 60 construction includes:
- Resurfacing the existing pavement
- Resurfacing eastbound and westbound ramps
- Constructing a crossover at the west and east end of the project area to accommodate two-lane, two-way traffic
- Removing and replacing road signs
- Constructing a snow fence to mitigate snow drifts on Hwy 60 at the Watonwan River Bridge
- Removing or replacing guardrails
- Resurfacing and upgrades to the Hwy 4/County Rd 27 bridge and County Rd 12 bridge over Hwy 60
PCiRoads of St. Michael, Minnesota, was awarded the project with a bid of $27,500,000.