Building Excellence

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

A.L. St. Onge Replaces Post-Flood Gilead Brook Bridge

by: Paul Fournier
A.L. St. Onge workers use a Terex crane to strip EFCO concrete pier forms for the new VT12 Gilead Brook Bridge being built in Bethel under $6.4 million contract with VTrans. Photo courtesy of Brian Richardson, A.L. St. Onge
A.L. St. Onge workers use a Terex crane to strip EFCO concrete pier forms for the new VT12 Gilead Brook Bridge being built in Bethel under $6.4 million contract with VTrans. Photo courtesy of Brian Richardson, A.L. St. Onge
One of Vermont’s oldest bridges is being replaced after comprehensive engineering studies concluded it could not be repaired and brought up to today’s standards. Built in 1928 during the presidential term of Vermont-native Calvin Coolidge, the historic structure carries VT 12 over Gilead Brook in Bethel. The contractor, A.L. St. Onge, is replacing the bridge under a $6.4 million contract with the Vermont Agency of Transportation (VTrans).

The historic Gilead Brook Bridge was one of many built following Vermont’s Great Flood of 1927, generally considered one of the worst natural disasters in the state’s history. Three consecutive days of rain in November spawned a deluge that killed 84 people and caused devastating private and public property destruction. Transportation infrastructure was decimated, with more than 1,250 bridges destroyed or severely damaged.

Located approximately 4 miles north of the intersection of VT 12 and VT 107, the Gilead Brook Bridge was unique – a multi-span Warren deck truss bridge. Only four of these were built in the aftermath of the storm. A relatively simple design, a Warren truss configuration produces strength while using less materials, and thus can be lighter and less expensive than other types of trusses subjected to the same design loads. This trait is especially desirable for a long narrow structure located on a steep road such as the segment of VT 12 undergoing bridge construction. The Gilead Brook Bridge is called a deck truss because the road is placed on the top chord of the trusses.

Not an ABC Candidate
According to VTrans, the Bethel VT 12 Bridge has a nonstandard width and is nearing the end of its 100-year design life. The four-span, two-lane structure has a length of 326 feet and a roadway clear width of only 20 feet. Its twin 120-foot, 2-inch interior spans are the original steel deck trusses, held together with rivets, and the 43-foot approach spans consist of rolled I-beams stiffened by extra plates on the lower flange. The bridge has a concrete deck – not the original, which was replaced in 1971 and needs to be replaced again.

VTrans evaluated several alternative methods for replacing the bridge, including no action, rehabilitation, and complete bridge replacement. The agency determined that strengthening the truss members to meet design loads was not economically feasible. This problem was exacerbated by its age and overall poor condition, prompting VTrans engineers to recommend a complete bridge replacement.

The new bridge is being built a few feet west of the existing structure. The bridges are oriented roughly north-south, with Gilead Brook flowing approximately west to east at this point. Traffic is being maintained on the old bridge during construction of its replacement. Accelerated Bridge Construction methods were not considered practical for this project for a number of reasons: shutting down VT 12 would significantly affect first responders and the traveling public; the new bridge is 38 feet longer and 11 feet wider than the old; VT 12 has a relatively steep slope of about 4.35 percent; and the road is more than 40 feet above the streambed.

Epiroc
Your local Atlas Copco CMT USA dealer
Brandeis Machinery

Also, the substructures and superstructures of the two bridges couldn’t be more different. Two concrete hammerhead piers support the new bridge, compared to three bents each comprised of a pair of concrete obelisks that support the original bridge. Moreover, the new bridge is designed with welded steel girders.

Stronger and More Durable

The new three-span VT 12 Bridge has weathering steel plate girder superstructure, and for aesthetic reasons, features parabolic haunched webs at the piers. The frame typically consists of four 66-inch welded steel plate girders spaced 9 feet, 2 inches apart that are braced with crossframes. Weathering steel meets AASHTO grade M270 50W, which means the uncoated (or unpainted) steel exhibits higher resistance to atmospheric corrosion than other steels, because it forms its own thin protective surface layer that regenerates continuously when subjected to weather. In other words, the steel is allowed to rust in order to form the protective coating.

The new bridge is 364 feet long including two approach spans of 110 feet and a center span of 144 feet. Its 35-foot fascia-to-fascia width provides ample space for two 11-foot travel lanes; two 4-foot, 10-inch shoulders; and galvanized steel guardrails. An 8-1/2-inch-thick high-performance concrete deck – designed to be more durable and stronger than conventional concrete – is topped with a 3-inch bituminous concrete pavement to complete the roadway.

In a move that recalls the Gilead Brook Bridge listing on the National Register of Historic Places, VTrans specified the addition of an ornamental steel lattice railing similar to that of the original bridge. Composed of crisscrossing 2x¼ steel bar stock and L3x2x¼ angles, the lattice is attached to the outside face of the highway guardrail.

Mobilizing Equipment to Restore Site
VTrans awarded the $6.4 million contract to A.L. St. Onge on April 11, 2019, with a target schedule running from June 14, 2019, to fall 2020 completion. The contractor’s project team includes Brian Richardson, Project Manager, and brothers Artie St. Onge and Randy St. Onge, Project Co-Superintendents and company owners. Key personnel for VTrans are Carolyn Carlson, Project Manager, and Thomas Chase, Resident Engineer.

Almost immediately after the contract was awarded, the contractor began work to restore a large portion of the northwest embankment of the original bridge, which had been washed out by a recent heavy storm. St. Onge fielded a number of heavy construction equipment pieces for the earthmoving, among them: two Caterpillar off-road trucks, three excavators (Caterpillar 320, 330 and 345), and a Caterpillar 928 Loader. This effort included bringing in to the site some 2,500 cubic yards of riprap and soil. In line with earthwork, project specifications call for the contractor to manage its construction activities to limit earth disturbance to 2 acres or less at any given time, while adhering to a construction sequence proposed in the documents. This requires precise control of earthmoving operations.

Efforts Turn to Substructures
As work shifted focus from earthmoving to erecting concrete substructures, St. Onge brought in a contingent of lifting and material-handling equipment. This entailed a Grove HL-150 Lattice Boom Crane on wheels; a Demag AC180 Hydraulic Crane on wheels; a Terex HC125 Lattice Boom Crane on crawlers; a Genie S-600 Boom Lift; and a Link-Belt HSP 8050 Rough-Terrain Crane.
Sennebogen LLC
Your local Sennebogen LLC dealer
Brandeis Machinery

Major structural work began with Pier #2, the northern one of two support substructures that tower some 40 feet above the streambed. Located near the edges of the existing brook channel, the piers have 8-foot-diameter columns and 34-feet-wide by 8-foot, 6-inch caps. Pier construction was facilitated by the use of EFCO concrete forms for the columns and caps. Each pier is set on a 5-foot-deep, 26-foot by 26-foot concrete footing. Carroll Concrete supplied about 1,150 cubic yards of high-performance concrete for all substructures and superstructures, with an estimated 192,000 pounds of rebar provided by Dimension Fabricators Inc.

Following Pier #2 construction, crews built Abutment #2, and wingwalls. Then, proceeding southward, they built Pier #1, Abutment #1 and its wingwalls. The 34-foot-wide by 13-foot-deep abutments are supported by HP 12x84 steel piling embedded at least 2 feet into the concrete. With concrete substructures completed, the contractor prepared to erect bridge girders.

Casco Bay Steel Structures supplied approximately 215 tons of weathering steel and about 350 linear feet of steel pilings for this phase of the work.

Project Manager Richardson indicated the job has progressed very well towards a fall 2020 completion.

“We started this job in June 2019, and we had already built the piers and abutments and set the steel by the week before Christmas,” he said.

Kleemann
Your local Wirtgen America dealer
Brandeis Machinery
Wirtgen America Inc
Your local Wirtgen America dealer
Brandeis Machinery
Kleemann
Your local Wirtgen America dealer
Brandeis Machinery
Komatsu Dealer Program
Your local Komatsu America Corp dealer
Brandeis Machinery