Building Excellence

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

OHL Works around Austin’s High Traffic Volumes, Groundwater, and Existing Utilities to Complete I-35 at Oltorf Street Project

by: Julie Devine
Photo courtesy of the Texas Department of Transportation
Photo courtesy of the Texas Department of Transportation
As part of the $42.6 million I-35 at Oltorf Street project in Austin, Texas, general contractor OHL USA, Inc., of Austin needed to demolish a prestressed concrete, box beam bridge across Interstate 35 mainlanes – in an area that sees more than 200,000 vehicles a day – then construct a new, standard box beam bridge.

Using a multi-phased plan, with special measures to maintain stability of the existing bridge during demolition and speed up construction of the new structure, OHL completed the work around live traffic in just four months.

Designed to improve mobility and safety for all transportation modes along and across I-35, the 1.3-mile Oltorf Street project also converted outdated diamond ramps to a braided configuration; extended entrance and exit lanes for mainlanes and ramps; improved frontage roads; added U-turns in both directions of I-35; and enhanced bicycle and pedestrian paths along the frontage roads in each direction. OHL finished the project in June.

Funded by the Texas Clear Lanes initiative, the Oltorf Street construction was the eighth project completed as part of the Texas Department of Transportation’s (TxDOT) Mobility35 program. Enhancements along 79 miles of the 50-year-old interstate address increased congestion and travel-time delays due to population and employment growth.

Ballet of Excavators and Demo Equipment
For the I-35 at Oltorf Street project, TxDOT awarded a low-bid contract to OHL in July 2016. Construction began in February 2017 and bridge demolition started in July 2017. OHL’s crews reconstructed the bridge by the end of November 2017, meeting their contract incentive for a four-month window.

In order to maintain the heavy traffic volumes, “The Oltorf bridge demolition needed to be performed in two phases,” said Zachary Feezel, OHL’s Assistant Project Manager. “Traffic was shifted on the existing bridge to allow demolition of a portion of that bridge and construction of a portion of the new bridge. Traffic was then placed on the new bridge so the remainder of the existing bridge could be demolished and the final portion of the new bridge constructed.”

Kleemann
Your local Wirtgen America dealer
Brandeis Machinery

The phased demolition created some challenges. First, “The design of the existing bridge included transverse post-tensioning strands that ran through the box beams at midspan,” Feezel explained. “These strands had to be cut in the first phase of demolition. In order to maintain the bridge’s integrity, a steel plate system was designed and installed prior to demolition. The system consisted of three plates anchored along the bottom gap between each beam, one at midspan and one at each quarter-span point.”

According to Michelle Romage-Chambers, TxDOT’s South Travis Assistant Area Engineer, “The plate system stitched all the beams together under the bridge and allowed the structure to remain stable over live traffic.”

OHL utilized full mainlane closures in both directions during demolition. “That was for both safety and allowing each phase of demolition to be completed during one weekend,” Feezel said.

Public outreach encouraged travelers to seek alternate routes, and those who didn’t were moved to frontage roads. “In close coordination with the City of Austin, who manages the traffic signals in the area, an extensive traffic control setup was used to keep traffic moving,” Romage-Chambers said.

Despite all the complexities, the demolition work proceeded smoothly. “From beginning to end, it was a well-orchestrated ballet of excavators and demolition equipment,” Romage-Chambers added.

Sennebogen LLC
Your local Sennebogen LLC dealer
Brandeis Machinery

For the new bridge, TxDOT selected a standard box beam design to lessen the impact of construction on the traveling public, Romage-Chambers said. To speed up some steps of the work, OHL used high early strength concrete mix designs.

In addition, “Portions of the retaining walls underneath the bridge were completed after the bridge was built, utilizing special equipment to maneuver and set the panels and copings within low clearances,” Feezel said.

OHL used two large hydraulic cranes to set several of the box beams around overhead power lines. “The beams under the lines were initially picked from the trucks and pre-set on the bridge bents outside the power lines,” Feezel explained. “The cranes were then moved and the booms lowered in order to shift the beams in place under the lines.”

Water in the Way
In the project’s roadway work, “Groundwater was discovered under the pavement, so rock was placed to allow the water to move through the area while providing a stable foundation for the new roadway,” Romage-Chambers said.

Crews also installed two 24-inch waterlines side-by-side underneath I-35 using a boring method. “That required very deep pits with special shoring to protect the work,” Feezel said. In addition, “A large amount of groundwater continuously flowed into the main bore pit, there was an existing waterline thrust block within another pit, and a conflict with new underground utility lines required careful installation of multiple bends on the 24-inch waterline.”

To further complicate the work, “The existing 24-inch waterline couldn’t be shut off and removed prior to installation of one of the new waterlines,” Feezel said. “We had to bypass small portions of MSE retaining walls and then complete those once the existing line was removed.”

Safety Throughout
The finished project now enhances safety throughout the corridor. For instance, by converting the existing diamond ramps to the braided configuration, TxDOT estimates a 35 percent decrease in crashes.
Leeboy - Pavers/Asphalt
Your local LeeBoy dealer
Brandeis Machinery

“The outdated ramps, where entering and exiting traffic had to merge into the same lane, caused major delays in the corridor,” Romage-Chambers said. “The new, braided ramps, where an entrance ramp goes over an exit ramp or vice versa, reduce merging and weaving conflicts on both the frontage roads and the mainlanes by separating incoming and exiting traffic.”

In addition, TxDOT expects the extended entrance and exit lanes between ramps to reduce crashes by 20 percent. Improvements to the mainlanes, frontage roads, and cross streets are anticipated to reduce wait times at frontage road intersections by up to 37 percent and increase travel speeds on I-35 mainlanes by about 17 mph.

The project also replaced conventional lights installed in the 1970s with high-mast lights that are two to three times taller and four times more radiant. The old light poles included one or two light fixtures, meaning more light poles spaced closer together to get uniform roadway coverage. By contrast, high-mast light poles stand as tall as 150 feet, with six, 120-volt LED bulbs. That allows more space between poles and less maintenance. The lights are calibrated using software to evaluate light patterns, and then each bulb is adjusted to avoid creating a halo effect and reduce light pollution.

In this project, five high-mast lights replaced 55 existing light poles. Throughout the 79-mile stretch covered by the Mobility35 program, nearly 600 high-mast lights will be installed.

Epiroc
Your local Atlas Copco CMT USA dealer
Brandeis Machinery
Leeboy - Pavers/Asphalt
Your local LeeBoy dealer
Brandeis Machinery
Vogele
Your local Wirtgen America dealer
Brandeis Machinery