Construction Digest

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Archer Western - de Moya Joint Venture Expands the Gateway Expressway

by: Debra Wood
Crews build the elevated sections of the expressway over U.S. 19 and 118th Avenue.
Crews build the elevated sections of the expressway over U.S. 19 and 118th Avenue.
Archer Western - de Moya Joint Venture builds lanes flying into the Roosevelt Interchange on the Gateway Expressway.
Archer Western - de Moya Joint Venture builds lanes flying into the Roosevelt Interchange on the Gateway Expressway.
A view of the express flyover at 49th Street and Roosevelt Boulevard.
A view of the express flyover at 49th Street and Roosevelt Boulevard.
A look at the expressway lanes flying into the Roosevelt Interchange.
A look at the expressway lanes flying into the Roosevelt Interchange.
A curved section of the expressway is shown over U.S. 19 and 118th Avenue.
A curved section of the expressway is shown over U.S. 19 and 118th Avenue.
Crews work on the deck of the viaduct over 118th Avenue.
Crews work on the deck of the viaduct over 118th Avenue.
Crews build the expressway lanes flying into the Roosevelt Interchange.
Crews build the expressway lanes flying into the Roosevelt Interchange.
The Florida Department of Transportation’s (FDOT) nearly $595 million Gateway Expressway project aims to reduce congestion and improve safety, in Pinellas County, with elevated toll lanes on State Road 690 and 686 and express lanes on Interstate 275.

“The Gateway area of Pinellas County is a highly developing area, with a lot of industry located there,” says Greg Deese, Resident Engineer with the FDOT. “That comes with a lot of traffic and an opportunity to create thoroughfares in the east-west and the north-south directions.”

The project adds toll lanes and will separate through traffic onto a limited-access highway away from local traffic. Most of the sections are elevated but in some places the new lanes are at grade. The express lanes are located primarily in the median.

The project includes 25 new bridges, widening of five bridges, replacing a bridge barrier, and adding noise walls, signage, an Intelligent Transportation System, and electronic toll gantries. Many of the bridges have curved steel girders. Six bridges have steel plate I-girders. There are two steel-plate box girder flyovers, 21 Florida I-beam bridges, a flat-slab bridge and one bridge culvert.

“The heavy bridge work on this job makes it challenging and complex,” Deese says.

Sennebogen LLC
Your local Sennebogen LLC dealer
Brandeis Machinery

The department decided to use design-build on this project to accelerate the job when funding became available, but design was not completed.

“Design-build allowed us to go out on the street quicker,” Deese reports.

Archer Western - de Moya Joint Venture received the design-build contract. The partners are Archer Western with an office in Tampa, Florida, and de Moya Group of Miami. BCC Engineering of Tampa serves as the prime designer partner.

The delivery method also offers opportunities for innovation. One of those was reconfiguring the I-275 and Roosevelt Boulevard interchange so another express lane could be added in the future. Additionally, the contractor, under a 16-hour detour, removed the entire 4th Street bridge over I-275.

The contractor participated in workforce development initiatives to bring on local job seekers and introduce them to the industry. After completing a class, participants were offered a job and a couple of dozen succeeded and “started their careers in this industry,” Deese reports. The department hopes to replicate this program on other projects.

Takeuchi Mfg Ltd
Your local Takeuchi Mfg Ltd dealer
Brandeis Machinery

Work began in August 2017 and is scheduled for completion in 2023.

State Road 690
Crews are creating a new four-lane tolled expressway (SR 690) in the median of 118th Avenue North, from U.S. 19 to the west of I-275. The new lanes are elevated over several streets.

A 4,035-foot-long viaduct bridge has 26 spans, with Florida-I 84 and 78 beams, supported on post-tensioned hammerhead pier caps, constructed in three cast-in-place post-tensioned segments to minimize impacts to existing traffic, reports BCC.

The steel-girder flyover bridges have several curved units with spans reaching 320 feet long. At one 118th Avenue bridge, in a portion lacking right-of-way, the contractor is tucking the surface lanes under the bridge.

Overnight, the crews removed the 4th Street bridge over I-275, which had cast-in-place box girders. They removed the entire structure using self-propelled modular transports.

The six transports were rolled under the bridge. Workers cut through the piers. The four jacks per transport roll on 80 tires and moved the entire bridge to a new location. Then crews brought down the foundations.

Deere SS
Your local Deere & Co dealer
West Side Tractor Sales Co

“They jack up the bridge and the mobile transports move it off of the roadway,” Deese says.

An additional challenge for these toll lanes was ensuring a liner at an existing landfill remained intact.

State Road 686A
This new four-lane elevated expressway runs from the Bayside Bridge to just west of I-275 and is being built in the median of Roosevelt Boulevard between the Bayside Bridge and Ulmerton Road, where an interchange will be built. The new lanes will run south through the former Sunshine Speedway property and then merge with SR 690.
Additional Scope
FDOT is adding an express lane in both directions on I-275 from south of Gandy Boulevard to north of 4th Street North and the western end of the Howard Frankland Bridge. The express lanes will offer a direct connection between I-275 southbound express lanes to the Gateway Expressway westbound and eastbound to northbound I-275.

The project also required reconfiguring the roads adjacent to the new elevated sections, including Roosevelt Boulevard and 118th Avenue.

Roosevelt Boulevard from Bayside Bridge to Ulmerton Road is being rebuilt as two one-way surface roads, with new access roads for the St. Pete-Clearwater International (PIE) Airport terminal. Also at the airport, crews will create new ponds, a permanent connection to Fairchild Drive and new signals.

Crews will repave 118th Avenue North from U.S. 19 to 31st Court North and the eastbound off-ramp from SR 690 to southbound I-275. The construction team also will repair or rebuild sections of U.S. 19 and 118th Avenue North, including constructing new ramps and bridges.

Gomaco
Your local Gomaco dealer
Fabick CAT/MO

Throughout construction, crews have maintained traffic on all of the roads involved in the Gateway project. In some sections, capacity has been reduced.

“We are allowing them detours and road closures to fly those beams,” Deese says. “There is a lot of logistic management to do that right.”

The contractor has used automated machine guidance and modeling on this project. Additionally, the joint venture is using the autonomous rebar-tying robot TyBot to machine tie as many as 1,000 bridge deck ties an hour, using robotics and artificial intelligence. The project will consume 10,800 tons of rebar, 8,130 tons of structural steel, 192,000 cubic yards of concrete and 115,000 tones of asphalt.

“It’s been a great job and a really good partnership,” Deese says. “I’m looking forward to getting it done.”

Photos courtesy of the Florida Department of Transportation

Leeboy - Pavers/Asphalt
Your local LeeBoy dealer
Brandeis Machinery
Wacker Compact Equipment
Your local Wacker Neuson Corp dealer
Burris Equipment
Deere SS
Your local Deere & Co dealer
West Side Tractor Sales Co
Gomaco
Your local Gomaco dealer
Fabick CAT/MO