“Motorists are now seeing lots of progress on the reconstruction of U.S. 49 in Rankin County,” Simmons said. “Motorists are reminded to slow down and be alert for roadside crews working to complete the remainder of this project as quickly as possible.”
Work remains on track to be completed summer 2022. The project was awarded to W.G. Yates & Sons Construction Company.
The project also includes widening along I-20 eastbound and I-55 northbound for the new bridge, roadway realignment, and ramps. Additional work includes slide repairs, slope stabilization along the railroad, and traffic sensor installations within Hinds and Rankin counties.
Crews recently completed placement of the pre-stressed concrete beams, which subsequently led to concrete pouring for the bridge diaphragms and decking. Soil cement treatment is underway, along with asphalt paving on the new and existing I-20 eastbound roadways. The construction of slope revetment and installation of electrical components are also in progress.
| Your local Iowa Mold Tooling Co Inc dealer |
|---|
| Nichols Fleet Equipment |
| Nichols Fleet Equipment |
| Nichols Fleet Equipment |
| Nichols Fleet Equipment |
The $42.2-million project was awarded to Key Constructors, LLC. Work remains on track to be completed summer 2022.
The bridges will be constructed on a new alignment parallel to the existing highway. Once the bridges are constructed, the new roadway will be paved and provide a connection to the upcoming SR 19 four-lane project that extends from Tucker north to Philadelphia.
The $11.7-million bridge replacement project was awarded to Joe McGee Construction Company. Work is scheduled to be completed by fall 2021.
The $35.6-million expansion project was awarded to W.G. Yates & Sons Construction Company. Work on the expansion project is estimated to be completed fall 2023.
The $1.5-million project was awarded to Olympus Painting Contractors. Work is expected to be completed by summer 2021.
| Your local Trimble Construction Division dealer |
|---|
| SITECH Tri-Rivers |
| SITECH Tri-Rivers |
| SITECH Tri-Rivers |
| SITECH Tri-Rivers |
The widened section of roadway has been brought up to grade and the surface paved. Crews have also completed the widening of the north and southbound outside lanes and have moved on to median work for Phase II.
The $2.6-million project was awarded to Walter’s Construction Company. Remaining work is on track for a fall 2021 completion.
Remaining work includes spot milling and failed asphalt pavement repairs. The $3.3-million project was awarded to Dickerson and Bowen, Inc. and is scheduled to be completed this summer.
In Kemper County, a project that consists of scrub sealing and overlaying approximately 5.6 miles of SR 21 between Preston and the Neshoba County line is underway. Work underway includes spot milling and repairing of several failed areas within the project limits.
The $2-million project was awarded to Dickerson and Bowen, Inc. Work is estimated to be completed this summer.
| Your local Komatsu America Corp dealer |
|---|
| Kirby-Smith Machinery |
| WPI |
| Kirby-Smith Machinery |
| WPI |
| Kirby-Smith Machinery |
| WPI |
| Kirby-Smith Machinery |
| WPI |
T.L. Wallace Construction, Inc. was awarded the $1.8-million project. Remaining work is on track to be completed by summer.
The $9.2-million project was awarded to L&A Contracting Company. Work is anticipated to be completed summer 2022.















































