Construction News

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Pennsylvania DOT Upgrades the Connection Between I-80 and I-99

by: Larry Bernstein
An aerial view of a new interchange, which is part of three phases of work on I-80 in Pennsylvania.
An aerial view of a new interchange, which is part of three phases of work on I-80 in Pennsylvania.
The Pennsylvania Department of Transportation (PennDOT) is in the midst of a three-phase project in Centre County. Upon completion, the project will build local access, create a high-speed interchange connection between I-99 and I-80, and make improvements on a local road.
Multiple Phases
The first phase of the project – I-80 Local Access Interchange – will provide direct access between SR 26 and I-80 at a standard diamond interchange and will only be utilized by local traffic destined to SR 26. The goal is to establish a connection for local traffic to Jacksonville Road. The project will feature construction of an interchange, a new bridge over I-80, and a connector road that will connect the interchange with SR 26.

Jacksonville Road Betterment (26/147) is phase two, and crews will reconstruct and widen SR 26 to maintain and support the state roadway network. The completed roadway will feature 11-foot travel lanes and 4-foot shoulders. As this phase is being constructed, commuters will be able to use local access and the interchange, as PennDOT will be phasing out ramps that no longer meet design standards.

Finally, phase three – known as the I-80 High Speed Interchange (I-80/B18) – will provide a direct connection between I-99 and I-80 via the construction of high-speed flyover ramps, eliminating the need to travel along SR 26 to access either highway. The stop-controlled intersections will be eliminated with the project and realigned to service local traffic.

Although the project is broken up into three phases, Steve Fantechi, Assistant District Executive for Construction in PennDOT District 2, says, “It was all or nothing. We could not build the I-80 High Speed Interchange without completing and upgrading the local interchange.”

This is because local access was being cut-off during the construction of the high-speed interchange so phase one and phase two needed to be completed to maintain local access. Also, if funding was not secured for the high-speed interchange the construction of phases one and two were not needed.

Vogele
Your local Wirtgen America dealer
Kirby Smith Machinery
Power Equipment Co

Upon completion of phase three, the project will connect two critical highway and freight interstates. In addition, there will be increased safety. “We had lots of crashes in the area due to the functionally obsolete design,” says Tom Zilla, a Principal Transportation Planner with the Centre Region Council of Governments. “Upon completion, we will have fixed the safety issues and brought it up to modern standards of two interstates.”

Traffic and Environmental Challenges
This project was stopped and started twice with its initial beginning back in 2004. As the project is finally moving forward, some changes have been made.

“When the project was initially scheduled, federal regulations required two lanes of the four-lane highway to be kept open,” says Todd Smeltz, a Principal with engineering firm, Erdman Anthony. “However, now we’re required to maintain four lanes of traffic on I-80.” This required significantly more staged construction.

The juggling also led to other challenges. “The project involves a significant amount of configurations which makes traffic control more difficult,” says Peter Hall, a PennDOT instruction inspector.

As part of the construction along the highway, pipes were replaced. Since the project was done in stages, it was necessary for the team to consider how to maintain drainage and keep the pipes working while only having access to part of the pipe that ran the width of the highway.

Another challenge the team faced was water. The area is home to streams and high-quality watersheds. “There’s lots of infiltration of water which we had to try to control while protecting the local watersheds,” Smeltz says. There’s lots of sinkholes around as well due to the water and the limestone soil.

Gomaco
Your local Gomaco dealer
Clark Machinery

A second environmental concern arose because the area is home to endangered bats, which impacts when the team can cut trees as this impacts the animal’s habitat.

In an effort to eliminate joints and remove potential issues in the future, the team is using a 28-foot-wide paver on both sides of I-80. “We think this will help us get more wear and improve the pavement,” Hall says.

Funding Finally Comes Through
Phase one of the project began in the summer of 2020 and the three construction season project is projected to finish in the fall of 2022. Phase two will begin in spring of 2023 and run into the 2024 construction season. Phase three will begin late spring 2023 and run until the end of 2026. Phase one is currently on schedule and the team anticipates it completing on time.

Securing funding for the project has been a challenge. Hence, the stops and starts. “The project initially started in 2000 but was stopped in 2004 because of funding issues and was started again in 2008 but again stopped in 2010,” says Craig Sattesahn, a PennDOT District 2 Project Manager.

Taken up again in 2018, the project was jump started by a $35 million Infrastructure for Rebuilding America (INFRA) grant from the federal government. The grant comes with certain restrictions according to Sattesahn, “We needed to have the project ready for construction in 18 months. So, we went back to old plans and brought them up to standards.”

The funds from the INFRA grant were only able to be used for phase one. Other monies came from a state match as well as additional federal funds. The cost of phase one is $52 million. The expected costs of phase two is $4.3 million and $135 million for phase three.

Serving as the contractor for the phase one project is local contractor, HRI, Inc. The firm has completed multiple projects with PennDOT in the district over the years.

ASV
Your local ASV dealer
CLM Equipment Co

“We have a good working relationship with HRI,” says Brent Lykens, a Construction Services Engineer with PennDOT. “We have bi-weekly project control meetings and when issues come up, we can engage in open and honest dialogues to get matters resolved.”

Lykens credits this with allowing the work to proceed smoothly and keeping things on track.

When the three-phase project is complete, “Travel between I-99, I-80, Route 26, and other local roads will be safer due to reduced congestion and smoother traffic movements and flow,” says Fantechi.

SITECH
Your local Trimble Construction Division dealer
SITECH Tri-Rivers
ASV
Your local ASV dealer
CLM Equipment Co
NPK Construction Eq Inc
Your local NPK Construction Equipment Inc dealer
Kirby Smith Machinery
WPI