Dixie Contractor

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Golden State Bridge Brings a Pair of 65-Year-Old Bridges Up to Standard

by: Larry Bernstein
The California Transportation Authority (Caltrans) is working on a pair of bridges in the far northwest corner of California, just south of Oregon in Del Norte County. The project includes both the Hunter Bridge and Panther Creek Bridge north of Klamath along Route 101. The two-lane bridges, built in the 1950s, do not meet current seismic standards. In addition, they are narrow and past their 50-year design life.

A structural and geological investigation found that the bridges were vulnerable to liquefaction if an earthquake were to strike nearby. According to the U.S. Geological Survey website, this occurs “when loosely packed, water-logged sediments at or near the ground surface lose their strength in response to strong ground shaking.”

So Close, Yet So Far Away
Separated by just 747 feet, the two bridges are in a series. The 168-foot Panther Creek bridge is followed by the 131-foot Hunter Bridge going north.

Both bridges are being torn down and replaced. The new bridges will be seismically sound structures that meet current standards. They’ll also improve accessibility. The old bridges didn’t have pedestrian walkways, while the new structures will have a separate 6-foot-wide lane for pedestrians and cyclists on the west side of the bridge and protected from oncoming traffic. The bridges will also have 8-foot-wide shoulders.

“The bridges are two totally different structures that look different but have many of the same architectural features,” says Clayton Malmberg, a Caltrans Area Construction Engineer responsible for overseeing all construction projects in the area.

The 130-ton steel Panther Creek Bridge is a single-span tied arch bridge. Two structural steel arches support the bridge deck. “We went with this type of bridge because we wanted to span the entire pond without impacting the creek and aquatic life,” explains Malmberg. The creek is a critical fishery habitat for salmon.

Doosan Infracore Portable Pwr
Your local Bobcat dealer
Pinnacle Central Co Inc

A second reason for going with a tied arch bridge is the high water below the bridge. “There’s not enough depth space between the water and base of the bridge, so we couldn’t put in a box girder or steel girder,” says Malmberg. Beneath the bridge’s roadway is a series of fabricated diamond-shaped slope tie-girders, which allow for natural drainage to the pavement above.

The new Hunter Creek Bridge is being replaced with a two-span structure. The bridge has a midspan bent. The bridge segments were built from cast in place concrete slab segments, and post-tension occurred while on site.

Another difference came in the construction of the bridges. For the Hunter Creek Bridge, they had to drive pile length up to an additional 67’ on some piles beyond the expected amount to get to adequate bearing. It took two extra weeks for the team to find bedrock to support the bridges. Malmberg notes the team worked long hours and extra shifts during this period.

Despite being less than .2 tenths of a mile away, the Panther Creek Bridge achieved the required bearing capacity at the original design depth. So, even though both bridges are on creek beds which have silty soils, the team needed to go further down for piling on one more than on the other.

Keeping Things Moving
Traffic had to be handled differently for each bridge. The bridges have an average daily traffic count of 4,580 and the team needed to find a way to keep flowing. On the Hunter Creek Bridge, the team shifted traffic to one side while demoing and constructing the other side. They switched back when completed.

However, on the Panther Creek Bridge it was not possible because the entirety of the old bridge needed to be removed to construct the new tied arch structure. Instead, the team constructed a temporary bridge right alongside the new bridge.

Iowa Mold Tooling Co Inc
Your local Iowa Mold Tooling Co Inc dealer
Nichols Fleet Equipment

Like many other construction projects, getting materials was challenging. The team got creative with scheduling and staging to keep the project progressing. However, the team had an additional challenge related to materials and the workforce. “Being in a rural area, maintaining a skilled workforce and a steady supply of materials required for construction can be a challenge. It’s a challenge to find people and bring them to the site,” Malmberg says. “Getting materials to the site is challenging as well, it being in a mountainous area.”

Contractor, Schedule, and Financing
Golden State Bridge is serving as the general contractor on the project. The remote nature of the work tends to limit the number of prospective bidders. Malmberg, however, is impressed with Golden State Bridge. “They’re great at maintaining communications. They’ve worked through challenges in a culturally and environmentally sensitive area while constructing a unique type of bridge.”

The project was begun in July 2020 and is on schedule to complete in Spring 2023. This is impressive, considering the supply chain issues and delays related to adding additional pile length piling.

The Hunter and Panther Creek Bridges is on budget at $21.1 million despite the challenges. Malmberg credits the contractor, “We have weekly meetings with the contractor and they’re good at letting us know if there are issues.”

The state is funding the project from Senate Bill 1 (SB 1), which California passed in 2017. The $54 billion package is for fixing roads, freeways, and bridges in communities across the state.

When the project completes and the bridges are in use, it will represent an improvement in active transportation in an economically disadvantaged area. Commuters and pedestrians alike will have a safe and up-to-date mode of transportation.

Epiroc
Your local Atlas Copco CMT USA dealer
Power Equipment Co
Epiroc
Your local Atlas Copco CMT USA dealer
Power Equipment Co
Komatsu Dealer Program
Your local Komatsu America Corp dealer
Linder Industrial Machinery
Power Equipment Co