Michigan Contractor & Builder

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Speedy $16M Expansion of COVID-19 Test Kit Factory Wins ABC Award for JM Coull Inc.

by: Paul Fournier
Allain Sitework Inc. uses Doosan and John Deere excavators for earthwork at JM Coull’s $16 million expansion of Web Industries’ COVID-19 test kit manufacturing facility in Holliston, Massachusetts.
Allain Sitework Inc. uses Doosan and John Deere excavators for earthwork at JM Coull’s $16 million expansion of Web Industries’ COVID-19 test kit manufacturing facility in Holliston, Massachusetts.
JM Coull completed the plant’s two dryrooms within 100 days, enabling Web Industries to achieve a production capacity of 2 million COVID-19 test kits per week.
JM Coull completed the plant’s two dryrooms within 100 days, enabling Web Industries to achieve a production capacity of 2 million COVID-19 test kits per week.
Allain Sitework Inc. uses Doosan and John Deere excavators for earthwork at JM Coull’s $16 million expansion of Web Industries’ COVID-19 test kit manufacturing facility in Holliston, Massachusetts.
Allain Sitework Inc. uses Doosan and John Deere excavators for earthwork at JM Coull’s $16 million expansion of Web Industries’ COVID-19 test kit manufacturing facility in Holliston, Massachusetts.
Innovative Air Technologies air filtering equipment is lowered on pad at Holliston plant.
Innovative Air Technologies air filtering equipment is lowered on pad at Holliston plant.
A worker on a Genie S-65 Telescopic Boom Lift checks roof beam connections.
A worker on a Genie S-65 Telescopic Boom Lift checks roof beam connections.
A concrete buggy is used to place ready mix over dowels in cutout section of existing floor slab.
A concrete buggy is used to place ready mix over dowels in cutout section of existing floor slab.
A mini-excavator stacks cutout sections of floor slab for disposal.
A mini-excavator stacks cutout sections of floor slab for disposal.
JM Coull Inc. of Maynard, Massachusetts, has been recognized for its rapid expansion of a COVID-19 test kit manufacturing facility in Holliston, Massachusetts. The company received an Excellence in Construction Award (EIC) at the ABC Massachusetts annual EIC Awards evening, held November 17, 2021. EIC Awards recognize overall excellence in project execution, craftsmanship, safety, innovative elements and challenges, and client satisfaction.

Dubbed Project Enterprise, the Holliston undertaking was urgent due to spiking COVID-19 cases in the United States. Coull employed a design-build turnkey delivery model, combining all design and construction services into one contract with a single point of responsibility. The contract called for the retrofit of the existing COVID-19 Test Kit Manufacturing facility to boost its shipments from 200,000 kits per week to 2 million, playing a significant role in the ongoing battle with the virus.

Project Enterprise also simultaneously upgraded the building’s personnel capacity from 50 employees to 500.

Coull’s Senior Project Manager, Mark Sargent, headed up the 70,000-square-foot Design-Build Renovation, Addition, and Parking Expansion. Project Enterprise had an original guaranteed maximum price of $17 million, but was delivered at $16 million while incorporating a new parking expansion without a change order. The total construction duration was eight months, which includes the 100 days devoted to delivering the core of the project – two large dry-rooms. Coull selected a significant number of key ABC member subcontractors for the Web project including:

  • Contractors Risk Management (CRM)
  • Controlled Environment Structures (CES)
  • DECCO
  • Hampshire Fire Protection
  • Interstate Electrical Services Corporation
  • MP Masonry, Inc.
  • Northstar Construction Service
  • Pioneer Valley Concrete
  • Sterling Concrete
  • Tech Mechanical Systems, Inc.
  • Tim's Fabricators, Inc
Production During Construction
The building expansion and ten-fold production rise had to be accomplished in a few months, with Web Industries’ employees producing an ever-increasing number of kits even as Coull’s team worked in and around a manufacturing facility that was active 24/7 at full capacity. As each week of production passed, the client needed to produce more test-kits than the previous week.

The heart of the project was the construction and commission of two large production and packaging dryrooms – low humidity spaces in which temperature and moisture levels are controlled together with filtered air and other variables. Dehumidification is critical to the manufacture and handling of a wide range of products, anything from lithium-ion batteries to medical supplies, such as COVID-19 test kits. One of the dryrooms contains two massive, concrete pad-mounted dehumidifiers, while several temporary dehumidifiers were on hand as backups if necessary.

Deere SS
Your local Deere & Co dealer
AIS Construction Equipment

The dryrooms had to be designed, permitted, built, and commissioned within 100 days, a period ending November 15, 2021. Commissioning, alone, is a complicated process that can consume valuable time. In general, building commissioning is an integrated, systematic process to ensure that all building systems perform interactively according to the “Design Intent”. The commissioning process establishes and documents the often numerous “Owner's Project Requirements”. Criteria for system function, performance expectations, maintainability, verification, and document compliance apply throughout all phases of the project. And this includes design, manufacturing, installation, construction, startup, testing, and operations.

The Scope of Work for this contract was expansive yet it was packaged as a single project. Within the one project, however, they had to track 19 separate jobs, including the following:

  • Two large production and packaging dryrooms
  • A quality control lab expansion
  • Multiple room and area renovations
  • Numerous mechanical, electrical, plumbing, and fire protection upgrades
  • Mezzanine office area
  • Breakroom addition to accommodate hundreds of new employees
An Abbreviated Schedule
One of the greatest challenges of Project Enterprise was the speed with which these tasks had to be accomplished to stay within the abbreviated schedule. The clock began ticking the moment Coull was selected as the project’s Design-Builder. Time was a valuable commodity due to the urgency attached to delivery of the plant’s end-product. In the interest of time, equipment that would normally have lead times of three to six months, needed to be approved, released, built, and delivered, in just a matter of weeks. Multiple pieces had to come together to make this goal a reality, including procurement of specialized HVAC equipment, working inside a fully occupied, multiple-shift facility, working in every area of the building and coordination and collaboration of multiple teams. All told, 36 subcontractors worked on the site.

In addition, Coull worked directly with town officials, creating more than 20 different permits or subcontracting jobs. Each separate area of the building was inspected individually to be granted Certificates of Occupancy, in lieu of one permit, one final inspection, one certificate of occupancy and a delay of several months for new production areas.

With so much going on, Sargent called a meeting to ensure good communications among town officials, Web Industries and the Coull on-site team. The town assisted by expediting permitting and approvals. The dryrooms met specification and were fully commissioned on time to allow for the installation of Web’s critical automated assembly equipment, which was delivered and installed over a two-week period before test kit production could begin. Coull’s on-site team attended to almost constant cleaning, to abide by COVID-19 protocols as well as to make certain the test kits would not be contaminated prior to packaging.

The goal of Project Enterprise had been to increase production of COVID-19 test kits from 200,000 to 2 million per week, and therefore speed up distribution to the market. Mission accomplished.

SITECH
Your local Trimble Construction Division dealer
SITECH Michigan
Deere SS
Your local Deere & Co dealer
AIS Construction Equipment
Deere SS
Your local Deere & Co dealer
AIS Construction Equipment
Deere SS
Your local Deere & Co dealer
AIS Construction Equipment