AECOM, C.H. Nickerson, and SUEZ were selected by the city in March 2018 to design, build, and operate the new 7 million gallons per day drinking water facility. The project is part of the municipality’s plan to improve water quality in line with state regulations. The new water treatment plant recycles its discharge, thus protecting the environmentally fragile Blackstone River – often cited as one of the nation’s most polluted rivers. Previously, the water treatment plant discharged its effluent directly into the river through three outfalls. With the new process, effluent is being piped to the city’s sewage plant for treatment.
Under the DBO contract, AECOM oversees plant design, engineering, planning, and guidance. C.H. Nickerson & Company constructed the plant, while SUEZ has ensured continuity of service by operating the existing plant during construction and now operates and maintains the new plant.
John Finnegan, P.E., AECOM Project Manager, said ground was broken at the plant site late in May 2018, with Steve Emmendorfer and John Mack serving as Nickerson’s Project Manager and Project Superintendent, respectively. Mike St. Pierce is Project Manager for SUEZ, which has a 20-year, approximately $41.6 million contract to operate the new plant and a raw water pump station.
The DBO project delivery model chosen by city officials has several important advantages over traditional design-bid-build or design-build methods. DBO components are procured from the private sector in a single contract. A private entity is responsible for design and construction as well as long-term operation and maintenance. Usually, a public sector sponsor secures the project's financing independently and retains the operating revenue risk. For this project, the Rhode Island Infrastructure Bank is providing Woonsocket with a whopping $55 million loan at below-market rates, resulting in considerable savings.
Your local Gomaco dealer |
---|
American Construction Supply |
Tri-State Truck & Equipment Inc |
Furthermore, the project design can be tailored to the construction equipment and materials that will be used. If a long-term maintenance program is needed, no one knows the job better than the DBO team. They can create a program that is pertinent and practical and lowers the risk of unexpected problems that could develop into costly repairs.
In addition, a tailored maintenance program typically includes project lifecycle costing.
According to FHWA, the benefits of lifecycle costing are particularly important, as most infrastructure owners spend more money maintaining their systems than on expansion. What’s more, the lifecycle approach removes important maintenance issues from the political uncertainties affecting many maintenance budgets, with owners often not knowing how much funding will be available to them from year to year. In such cases, they are often forced to spend what money they do have on the most pressing maintenance.
Most recently, the DBO team was awarded a contract to perform over $65 million in capital improvements to the 40-year-old Lynn, Massachusetts, Regional Wastewater Treatment Plant. This mega-facility treats about 26 million gallons a day and can accommodate up to 100 million gallons during wet weather. It serves 140,000 people, including the 93,000 residents of Lynn, and residents of neighboring communities Nahant, Saugus, and Swampscott.
AECOM earned about $13.3 billion in professional service revenue during fiscal year 2021. The company is No. 189 on the 2021 Fortune 500 roster, one of those muscular companies who taken together generate about $13.8 trillion in revenue – some two-thirds of the U.S. economy. On August 17, 2021, AECOM issued a press release announcing plans to relocate its global headquarters from Los Angeles, California, to Dallas, Texas.
Your local Bobcat dealer |
---|
Pape Material Handling |
Nickerson has successfully employed design-build delivery for several large projects, including a Department of Transportation bus maintenance facility in Stamford, Connecticut; a $30 million water treatment plant also in the City of Stamford; and in conjunction with its joint venture partner AECOM, a $60 million design-build contract for the renovation and upgrade of The Lawton Valley and Station Number One water treatment plants in Newport, Rhode Island.
Subsidiary SUEZ North America, which posted revenues of $1.1 billion in 2020, operates across all 50 states and Canada with 2,800 employees. The company provides drinking water and wastewater treatment, and waste collection services, for nearly 7 million people daily. It treats 560 million gallons of water and more than 460 million gallons of wastewater each day, and also processes 160,000 tons of waste for recycling. In the United States, the company was awarded a series of water and wastewater treatment services contracts worth $212 million, including the operation and maintenance contract for the Lynn, Massachusetts, wastewater plant, worth approximately $155.7 million over 20 years.
SUEZ is also currently operating and maintaining the recently completed Woonsocket, Rhode Island, water treatment plant and raw water pump station under a 20-year, $41.6 million agreement with the city.