Construction is in Full Swing for Idaho Transportation Department's I-86/I-15 System Interchange Project

Cranes are being placed to begin drilling shafts for bridge piers.
Cranes are being placed to begin drilling shafts for bridge piers.
Water trucks are working to keep dust from construction to a minimum.
Water trucks are working to keep dust from construction to a minimum.
Earthmoving equipment is working throughout the System Interchange project site.
Earthmoving equipment is working throughout the System Interchange project site.
The age of the 1960s era bridges necessitated their replacement.
The age of the 1960s era bridges necessitated their replacement.
POCATELLO, ID — The Idaho Transportation Department’s rebuild of the System Interchange at I-86 and I-15 in Pocatello is in full swing with crews working multiple areas throughout the worksite. As part of Governor Little’s Leading Idaho initiative, the project is changing how the heart of the Interstate in Pocatello appears.

The lowering of the ramp for westbound traffic from northbound I-15 to I-86 is now complete and work on building the new bridges is beginning. Temporary barriers are in place at multiple locations and motorists will also notice changes in lane striping as traffic is shifted away from work areas.

One safety innovation being implemented is the use of a conveyor belt system to move earth fill from one area of the project to another. The conveyor allows crews to move material without using trucks entering and exiting the interstate. That makes for a safer work zone for drivers and work crews.

Soon, cranes will appear on the project and begin drilling shafts for new bridge piers. Excavators and other earthmoving equipment are also working in multiple areas to reprofile the land. Throughout the work zone water trucks are being utilized to keep dust down. Inspectors and engineers are also on-site daily, ensuring safety and compliance with designs. Additionally, pile driving will soon begin in the northern portion of the work area.

The historic rebuild of the I-86/I-15 System Interchange was the outgrowth of a need to replace aging bridges and improve safety. The bridges, built in the 1960s, are currently safe but needed to be replaced due to their age. Failure to do so would result in a need to place restrictive load limits which would hinder commerce.

Volvo CE
Your local Volvo Construction Equipment dealer
PacWest Machinery

ITD also noted an increase in aggressive lane changes and congestion within the interchange, particularly just north of the Pocatello Creek exit. The rapid motion of entering I-15 at Pocatello Creek and crossing to the passing lane to exit toward Chubbuck did not exist when the interchange was built. However, with population growth and associated development that traffic is now significant. Such “exit left” and “enter left” movements do not meet driver expectations, cause confusion, and results in frustration for drivers.

Another much-needed improvement was a redesign of the Chubbuck Road crossing. The old 1962 bridge is narrow and has limited capacity for pedestrians and bicyclists. With the growth of Pocatello and the addition of the Portneuf Wellness Complex, a significant change was needed. ITD’s new design changes Chubbuck Road from being an overpass over I-15 to an underpass beneath the freeway with dedicated bike lanes and wider sidewalks. Removal of the bridge also creates more space for the larger project to handle increased traffic.

Once completed, the new System Interchange will be safer and ready to carry the increased traffic volumes for the fastest growing state in America.

Doosan Infracore Portable Pwr
Your local Bobcat dealer
Pape Material Handling
Doosan Infracore Portable Pwr
Your local Bobcat dealer
Pape Material Handling
Metso Minerals - Recycling Eq
Your local Metso Minerals Industries Inc dealer
PacWest Machinery
Westate Machinery Co