Granite Construction Streamlines Replacement of the Arlington Avenue Bridges in Reno, Nevada

by: Larry Bernstein
Crews are fully reconstructing the Arlington Avenue bridges in the middle of downtown Reno, Nevada.
Crews are fully reconstructing the Arlington Avenue bridges in the middle of downtown Reno, Nevada.

Situated on a small island in the middle of the Truckee River, Wingfield Park is accessible via the Arlington Avenue bridges in downtown Reno, Nevada’s Riverwalk District. Work is underway to replace the bridges through a project taken on by the Regional Transportation Commission of Washoe County, the City of Reno, and Granite Construction.

A Century of Change

In the early 1900s, the three-acre natural island was transformed into a park that has since been a go-to spot for Reno residents. According to the Reno Historical website, the park featured a dance hall, a 700-seat open-air theater, and small boat rentals in 1911, with a roller skating rink being added later in 1912. In 1920, George Wingfield purchased the island and donated it to the city, and the city council named Wingfield Park in recognition of his contribution.

Today, the park offers many activities, including concerts, plays in an outdoor amphitheater, picnic areas, swimming, tubing, and kayaking.

Separated by the island, the two Arlington Avenue bridges serve as a major link to Wingfield Park. The northern bridge was built in 1921, while the southern bridge was constructed in 1939. Over their long life span, the bridges became deficient and no longer meet today’s safety and size standards.

The condition of the bridges has been shaped by both their age and their location in the Truckee River, which has led to scour. The river runs for 121 miles and is an outflow of Lake Tahoe.

The website of nonprofit, One Truckee River, says that the river has “wide fluctuations in annual runoff volumes, ranging from high water year averages of about 2 million acre-feet to about 115,000 acre-feet in low water years.” The Truckee River is also “home to a vibrant ecosystem of plants and animals and is critical to maintaining Pyramid Lake’s endangered Cui-ui Lakesucker and threatened Lahontan Cutthroat Trout.”

Building New Connections

The primary element of the project is the construction of the bridges. The team is demolishing the abutments and piers and fully reconstructing the bridges.

The new northern bridge will be a 125-foot-long single-pier structure. It will include two overlooks. The 53-foot-long southern bridge will be a clear span structure. Both bridges will be 71 feet wide with three lanes, including a turning lane. The bridges will include a sidewalk overlooking the river.

Some utilities will be placed in the girders to improve aesthetics, as the original bridges had utilities hanging on the exterior of the bridge. Granite also installed empty conduits for future use so that new utilities can be installed later without having to remove and replace new concrete improvements.

Other work on the project includes: