“We have concrete pavement that is old and has gone through its complete life cycle,” says Nicole Passuello, Project Development Supervisor, with the Wisconsin Department of Transportation (WisDOT) Northwest Region in Eau Claire. “We’re at a place where we have to replace the pavement.”
The 59-mile stretch of I-94 between Hudson and Eau Claire was dedicated on October 29, 1959, according to WisDOT historical records. That same day, the 41-mile stretch of interstate between Hudson and Menomonie was opened to motorists waiting to try out the new concrete four-lane freeway.
WisDOT opted for concrete pavement again, because it lasts longer on high-volume interstates, Passuello says. More than 36,000 vehicles travel on this section of highway daily, with a heavy concentration of truck traffic.
“The concrete pavement withstands the truck traffic and provides longer durability and is resistant to rutting,” Passuello said.
Your local Trimble Construction Division dealer |
---|
SITECH Northwest |
SITECH Rocky Mountain |
SITECH Southwest |
The current 8.4-mile project follows an adjacent 4-mile long pavement replacement to the east on I-94, which finished up last year. The projects shared the same prime contractor Hoffman Construction Co. of Black River Falls, Wisconsin.
Peter Hoffman and Anna Hoffman founded the company in 1915 and incorporated in 1927. The company remains family owned and has grown. It employs about 400 people and operates a fleet of scrapers, dozers, off-road trucks, backhoes, and dump trucks. Jim Hoffman serves as the current CEO. The company manages between 30 and 50 major highways and site development projects annually.
“We’ve asked the contractor to do a lot of work in a short amount of time,” Passuello says. “The biggest thing is the contractor was able to get the work done successfully last year, without major traffic disruptions.”
Hoffman has worked days, nights and Saturdays to keep on schedule, particularly through the wet weather in 2019, says Chad Sell, Project Manager for Hoffman Construction, adding, “It’s a very aggressive schedule. There’s a lot to get done.”
Sell reports, Hoffman has experienced “a lot of cooperation with the department in planning and bouncing ideas and switching things around. It was definitely a cooperative effort.”
Your local Case Construction Equipment Inc dealer |
---|
Century Equipment |
“If we didn’t build temporary roads and bridges, we would have significant backups in traffic,” Passuello says. “The drivers appreciate it.”
Preparing to build the 6-mile-long temporary road, crews found wet and soft material in the median that had to be excavated. The company removed 90,000 cubic yards of material. Then Hoffman brought in 275,000 cubic yards of borrow and good, rock materials to fill in the median and create a stable base. Once the project wraps up, crews will break up the temporary road and haul the asphalt to a recycler. Then at the end of the job, the company will bring in top soil to recreate the median.
A concrete barrier separates the construction activity from live traffic. “Once we get traffic out of our way, we can utilize working days, nights, weekends to make up time,” Sell says. “We are not restricted by lane closure times.”
In 2019, on the western portion of the project, traffic shifted to the two temporary lanes, while crews rebuilt the two lanes of westbound interstate. Then when those first two westbound lanes were complete, traffic shifted to the new pavement and work began on the eastbound permanent lanes in 2020.
Knapp Hill, on the 2 miles at the eastern end of the project, limited staging options, Passuello says. The steep hill has a deep ravine in the median and precluded building the two temporary lanes. Therefore, this portion of the project will have traffic flowing on what is called a three plus one counter flow. Two lanes will flow in one direction and one lane will go in the opposing direction on one side of I-94. On the other side, the other opposing lane will remain open while work proceeds on the other lane.
Your local Gomaco dealer |
---|
Faris Machinery |
Tri-State Truck & Equipment Inc |
“We are building that piece of roadway half at a time,” she says. “It’s not a great way to do the work, but we were limited by the hill. It has a huge ravine, and it would have taken millions of dollars to fill in the ravine.”
Plus, the department would have run into environmental concerns, trying to fill in a natural ravine. The current work had no significant environmental concerns and is being constructed within the existing right of way.
After removing the old pavement, Hoffman uses an onsite portable concrete crusher to recycle the old concrete pavement and asphalt into gravel for the base for the new road.
“The contractor was able to crush the material and keep the material on site,” Passuello reports.
The I-94 project will require 255,000 square yards of concrete paving and 150,000 tons of hot-mix asphalt for the temporary road and permanent shoulders.
Your local Volvo Construction Equipment dealer |
---|
Faris Machinery |
The project remains on target for a November 2020 finish, including removal of the temporary roadway and structures.
“The contractor has been able to keep the work on track and provide us with a quality roadway,” Passuello says.