Building Excellence

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Final Three Phases Underway on Florida DOT’s Extensive 95 Express Program

by: Debra Wood
Crews pour concrete on one of the bridges. (Photo courtesy of Archer Western Construction and Trey Cambern Photography)
Crews pour concrete on one of the bridges. (Photo courtesy of Archer Western Construction and Trey Cambern Photography)
de Moya crews pour concrete for a bridge foundation on Phase 3 of the 95 Express program in Fort Lauderdale. (Photo courtesy of Archer Western Construction and Trey Cambern Photography)
de Moya crews pour concrete for a bridge foundation on Phase 3 of the 95 Express program in Fort Lauderdale. (Photo courtesy of Archer Western Construction and Trey Cambern Photography)
Archer Western - de Moya crews install the new westbound SR 84 bridge over I-95. (Photo courtesy of Archer Western Construction and Trey Cambern Photography)
Archer Western - de Moya crews install the new westbound SR 84 bridge over I-95. (Photo courtesy of Archer Western Construction and Trey Cambern Photography)
Crews lift a girder into place for one of the flyovers. (Photo courtesy of Archer Western Construction and Trey Cambern Photography)
Crews lift a girder into place for one of the flyovers. (Photo courtesy of Archer Western Construction and Trey Cambern Photography)
Crews remove a bridge on Phase 3B-2. (Photo courtesy of the Florida Department of Transportation)
Crews remove a bridge on Phase 3B-2. (Photo courtesy of the Florida Department of Transportation)
Foundation work progresses in Phase 3B-2. (Photo courtesy of the Florida Department of Transportation)
Foundation work progresses in Phase 3B-2. (Photo courtesy of the Florida Department of Transportation)
Form work takes place on Phase 3B-2. (Photo courtesy of the Florida Department of Transportation)
Form work takes place on Phase 3B-2. (Photo courtesy of the Florida Department of Transportation)
Crews build a sound wall during Phase 3B-2. (Photo courtesy of the Florida Department of Transportation)
Crews build a sound wall during Phase 3B-2. (Photo courtesy of the Florida Department of Transportation)
A bridge is raised in place during Phase 3C. (Photo courtesy of the Florida Department of Transportation)
A bridge is raised in place during Phase 3C. (Photo courtesy of the Florida Department of Transportation)
Work on the final three sections of the Florida Department of Transportation’s (FDOT) 95 Express project is under way and will help keep traffic moving on this 29-mile stretch of the congested South Florida interstate highway.

The local 95 Express projects are part of a regional network of Express Lanes. Goals include improving mobility and emergency evacuation in an area known for hurricanes and accommodating future growth and development.

The entire Phase 3 runs from Stirling Road in Broward County to Linton Boulevard in Palm Beach County. It will connect with Interstate 595 to and from the west. FDOT broke the project into segments and let them as funding became available. Construction began in 2016 and is scheduled for completion in 2025.

The largest contract is Phase 3C, a $457 million, 9-mile segment through a densely populated area in Fort Lauderdale, Florida. It will connect the 95 Express lanes with general lanes on I-595. 3C runs from Stirling Road to south of Broward Boulevard along I-95 and along I-595 from SR 7/U.S. 441/Turnpike Interchange to I-95.

Phase 3C
Archer Western Construction of Atlanta and the de Moya Group of Miami received the design-build contract for Phase 3C and began work in the summer of 2019. BCC Engineering of Fort Lauderdale, Florida, and GAI Consultants of Palm Beach Gardens, Florida, serve as the engineering partners.

“The most interesting part of this project was the fact that Florida has run out of room at this location,” says Archer Western Senior Project Manager Bernie Conway. “In order to widen the highway, we had to be rather ingenious with the design.”

Takeuchi Mfg Ltd
Your local Takeuchi Mfg Ltd dealer
Brandeis Machinery

FDOT was not able to take any additional right of way. Therefore, the Express Lanes had to be constructed in the existing footprint and with the highway’s old elements.

Work for this section includes adding an additional Express Lane in each direction, plus entrances and exits; additional lanes along I-595; creating new ramps to the Florida Turnpike; widening and painting the bridges; and adding tolling gantries, signage, and sound walls.

The team is building three flyovers to connect the 95 Express Lanes to I-595. Portions of two of the flyovers are in place, and the contractors expect to start the third one, over I-95 in August 2022. The nearness of Fort Lauderdale-Hollywood International Airport presented some challenges.

“We could go no higher than the existing structures due to the proximity of the site to the airport,” Conway reports. “We have one flyover that is so low, we are going to be lowering the Interstate 95 mainline by 2.5 to 3 feet, so there will be enough clearance for the new bridge.”

In another section of the project at the SR 84 interchange, Archer Western and de Moya are building northbound lanes directly underneath bridges running in the same direction as the highway.

“With the lack of space, there was no room to widen the highway, so we are going underneath,” Conway says.

Komatsu Dealer Program
Your local Komatsu America Corp dealer
Brandeis Machinery

Crews jacked up the bridges, built most of the four new piers, and placed the existing bridge in a temporary position while they completed construction of the pier caps. Then crews lowered the bridge into place above the highway.

On I-595, crews will be removing an existing pier to make way for a new connection road to flow underneath it. The pier will be replaced with a straddle bent.

In this section, there will be two entrances to the 95 Express Lanes and three exits, including local lanes to the airport, to I-595, and to get to a park and ride parking lot.

The work also includes installing new signage. The lettering is larger than on the old road. The larger signs require enormous foundations.

One lane is closed during the day, and on nights and weekends additional lanes can be closed. Working so close to active traffic presents risks. One or two vehicles unexpectedly enter the work area and crash into protective devices each week. Fortunately, no workers have been injured.

Wirtgen America Inc
Your local Wirtgen America dealer
Brandeis Machinery

This project was about 60 percent complete in July 2022 and is scheduled to finish in the fourth quarter of 2024.

Phase 3A-1
The $153 million, 6.7-mile-long Phase 3A-1 runs from south of Broward Boulevard to north of Commercial Boulevard. The de Moya Group received the contract and began work on this phase in October 2015. The project will add an express lane, convert the high-occupancy vehicle (HOV) lane into two express lanes in each direction, and extend the existing express lanes north from south of Broward Boulevard to north of Commercial Boulevard. Completion is expected in Spring 2023.
Phase 3B-2
Phase 3B-2 runs from south of Glades Road to Linton Boulevard in Palm Beach County and Glades Road from northwest 22nd Way to West University Drive. Prince Contracting of Tampa received the $148 million design-build contract for this 5.8-mile project. Work began in November 2019.

The project includes adding a lane and converting the HOV lane to express lanes; reconfiguring the SR 808/Glandes Road interchange into a diverging diamond interchange; adding ramp signaling; reconstructing the Clint Moore Road Bridge over I-95; and widening the Glades Road bridge over the South Florida Regional Transportation Authority railroad tracks and Military Trail and the I-95 bridge over the C-15 Canal, between Peninsula Drive and Linton Boulevard.

This section will consume about 7,000 linear feet of piles and 10,000 cubic yards of concrete. The work is scheduled to finish in late 2023.

The Express Lanes are tolled with the amount charged varying on traffic volume.

Once the projects are done, drivers in the Fort Lauderdale area will have additional options when driving north and south on this busy corridor.

Earlier Projects
Phase 3A-2, 7 miles from north of Commercial Boulevard to southwest 10th Street, entirely in Broward County, began construction in January 2016 and finished in 2019. Prince Contracting of Tampa, Florida, completed the $154 million project on time. In addition to extending the Express Lanes, the work during this phase added a general purpose lane and converting the high-occupancy vehicle (HOV) lanes to two express lanes in each direction. The project also included adding signals and noise walls, installing an intelligent transportation system and tolling equipment, and widening bridges.
Epiroc
Your local Atlas Copco CMT USA dealer
Brandeis Machinery

Construction began in early 2018 on Phase 3B-1, 4.8 miles from south of SW 10th Street to south of Glades Road. Prince also received the $102 million contract for this section, which included widening and converting the HOV lanes to Express Lanes. The number of general purpose lanes remain the same in this segment. Other work included reconstruction of I-95 on the approaches to the Hillsboro Canal bridges and construction of auxiliary lanes. The project was complete in October 2021.

Leeboy - Pavers/Asphalt
Your local LeeBoy dealer
Brandeis Machinery
Wirtgen America Inc
Your local Wirtgen America dealer
Brandeis Machinery
Epiroc
Your local Atlas Copco CMT USA dealer
Brandeis Machinery