Building Excellence

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Oregon DOT Repairs Scenic Columbia River Highway and Toothrock Tunnel

by: Larry Bernstein
Oregon DOT is repairing 13 miles of the 75-mile-long Columbia River Highway, which is a popular tourist area near Portland.
Oregon DOT is repairing 13 miles of the 75-mile-long Columbia River Highway, which is a popular tourist area near Portland.
The Columbia River Highway, located in Oregon, is a 75-mile highway that offers views of the Columbia River and Gorge. The gorge, which is 80 miles long and up to 4,000 feet deep, is 30 miles east of Portland. According to Travel Portland, it “… offers amazing views, hiking, mountain bike trails, and more than 90 waterfalls.” The Oregon Department of Transportation (ODOT) is in the middle of a project that focuses on a 13-mile stretch of the Columbia River Highway, also known as I-84.

The main reason for the project is to repair aging and rutting along the road. The repairs are needed to extend the life of the highway and smooth out the ride for travelers. Other work includes resurfacing several bridges and repairing an off-ramp where the bridge surface has deteriorated.

ODOT Resident Engineer Amer Hmidan says the project is ultimately about safety and includes multiple safety improvements including:

  • Installing an impact attenuator that absorbs contact and reduces damage to structures, vehicles, and motorists
  • Replacing weigh-in-motion loops on the freeway
  • Replacing signs to improve visibility
  • Installing and repairing bridge deck membranes and joints
  • Installing durable pavement markings
  • Installing shoulder and rumble strips
  • Replacing some median barriers
  • Improving drainage and addressing drainage issues that cause safety concerns
Tunnel in the Middle
In the middle of the 13-mile project area is the Toothrock Tunnel. The iconic tunnel, built in 1936, is part of the highway. It stretches 837 feet and is 28 feet wide and 16 feet high. The two-lane tunnel serves eastbound traffic.

In addition to fixing the pavement surface of the tunnel, the team is repairing deteriorated and damaged portions of the reinforced concrete Toothrock tunnel liner.

Kleemann
Your local Wirtgen America dealer
Brandeis Machinery

The team is using Premixed (Polyester) Polymer Concrete (PPC) in the tunnel and along the highway. According to Hmidan, PPC is innovative material. It can be placed in thin layers, is a durable and high strength material, but expensive.

However, the team needed to do less grinding of the current concrete to put down PPC, which is a cost savings when compared to full depth concrete replacement. To put down PPC, the surface needs to be dry and the weather needs to cooperate. This is a challenge as the weather in the gorge can change quickly and is often unpredictable.

A Popular Tourist Site
The Columbia River Gorge is a draw for locals and tourists alike. Therefore, keeping the roads open so visitors can get to the gorge is a must.

Despite that, there have been 24/7 lane closures in the tunnel four days a week – Sunday to Thursday. Because the tunnel is tight and the team is doing a full-depth repair in some areas, they have to shift traffic into one lane. “Between grinding, prepping, placing, and cure time for the PPC, it can’t be done on one day a week,” Hmidan says.

“We can’t close it during the summer because it’s a highly frequented area,” adds Paul Scarlett, an Area Manager for ODOT.

The closures caused a few inconveniences as wide loads travel through the tunnel. The average daily traffic count in the vicinity of the tunnel is over 29,000 vehicles. ODOT worked closely with the Mobility Committee to limit the days and duration of lane closures to reduce the impact on the tracking industry and traveling public.

Similarly, the team needed to be thoughtful in how they stage the work outside of the tunnel. During the summer, there have been lane closures while performing paving work and the team has worked at night. Traffic was shifted to the shoulder to accommodate the construction.

Contractor Innovations
Kerr Contractors, prominent pavers in the area, is serving as the general contractor on the contract. The company has worked on multiple ODOT projects in the past. Scarlett says the large company does good work and noted they won third place in the Smoothness Category for the paving work completed in 2022 as part of the Oregon Asphalt Awards for their work on the current project.

One of the subcontractors, Roger Langeliers Construction (RLC), fabricated an innovative side-mounted paving screed for the PPC work in the tunnel. “It allows them to pave narrow swaths of concrete with PPC overlays and inlays,” Hmidan says.

The project cost is $23 million and is currently on budget. Funding for the project was provided by federal funds primarily from the Statewide Bridge and Interstate Paving programs. Hmidan credits the good partnering relationship between ODOT and the contractor, good design, and the contingencies that account for risk for enabling the project to be constructed within budget. He notes that there have been some changes to the project schedule to accommodate freight and mobility restrictions and to accommodate wide loads.

Originally scheduled to be complete in the fall of 2022, at the time of publication the project is now expected to wrap up by the end of June 2023. Scarlett points to the bid award process as one reason the project completion date was pushed back. “It took a while for agency to award the bid. When they did select Kerr, the contractor couldn’t start the project early enough to meet the initial deadline.”

He adds that once the contractor had to close for the season and come back the following year, extra time and costs were incurred. Weather and the mobility restrictions to accommodate freight are other reasons for not being able to complete all the work in 2022.  

When the Columbia River Highway paving and Toothrock Tunnel project is complete, drivers along the scenic highway – including tourists looking to explore the Columbia River Gorge – will enjoy a safer ride. The proactive project also allows ODOT to extend the life of the highway and keep roads in good condition for all motorists.

Wirtgen America Inc
Your local Wirtgen America dealer
Brandeis Machinery
Wirtgen America Inc
Your local Wirtgen America dealer
Brandeis Machinery
Vogele
Your local Wirtgen America dealer
Brandeis Machinery