Building Excellence

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

North Spokane Corridor Improvements Create Better Mobility for All Travelers From I-90 to US 395

by: Debra Wood
Max Kuney Construction crews pour an abutment on the Wellesley bridge pier as part of a segment of the North Spokane Corridor.
Max Kuney Construction crews pour an abutment on the Wellesley bridge pier as part of a segment of the North Spokane Corridor.
This train mural at Wellesley depicts the heritage of the area.
This train mural at Wellesley depicts the heritage of the area.
Work progresses on the shared use path adjacent to the NSC.
Work progresses on the shared use path adjacent to the NSC.
The Wellesley pier includes a train mural recommended by citizens of the community.
The Wellesley pier includes a train mural recommended by citizens of the community.
Max Kuney Construction is using a Link-Belt crane to build the Wellesley bridge towers.
Max Kuney Construction is using a Link-Belt crane to build the Wellesley bridge towers.
Crews construct the Euclid Avenue bridge next to the shared-use path.
Crews construct the Euclid Avenue bridge next to the shared-use path.
Work progresses on the mainline structure over Wellesley.
Work progresses on the mainline structure over Wellesley.
A view of rebar on the Euclid Avenue deck.
A view of rebar on the Euclid Avenue deck.
Progress is happening on the latest segment of the 10.5-mile-long North Spokane Corridor (NSC), including construction of a new interchange with roundabouts.

“This project is for safety and will get a lot of the freight traffic off the local streets of Spokane,” says Project Engineer Jody Qualley, with the Washington State Department of Transportation (WSDOT). “It will be better mobility for all travelers, including pedestrians.”

Funding From Many Sources
The NSC will improve north and south mobility through Spokane from Interstate 90 to U.S. 395 at Wandermere, decreasing congestion and travel times. The state began discussing the project in the 1940s, but proposals did not succeed until an Environmental Impact Statement in 1997 started the project moving.

Groundbreaking on the NSC took place on August 11, 2001, grading from Hawthorne Road to U.S. 2. Then in 2003, the State Nickel Gas Tax Package provided $321 million to the project – enough to complete design, right-of-way acquisition, and construction from Francis to Farwell, the U.S. 2 Wandermere interchange, and U.S. lowering projects.

The Transportation Partnership Act, in 2005, provided $152 million for more right-of-way purchases and design. A $45 million federal Transportation Investment Generating Economic Recovery grant paid for construction of the southbound lanes, the Parksmith Road interchange and the first Burlington Northern Santa Fe (BNSF) Rail Realignment. Multiple projects have been completed since then. The first 5.5 miles, from Wandermere to Francis Avenue, opened in 2012 and the Francis Avenue bridge over the BNSF railroad and future NSC opened in 2014.

The Connecting Washington package, passed in 2015, provided $879 million to finish the project and take the NSC to I-90. That work included realigning more of the BNSF railroad tracks, in some places 120-feet toward Market Street, to make room for the road in that right of way.

Takeuchi Mfg Ltd
Your local Takeuchi Mfg Ltd dealer
Brandeis Machinery

WSDOT designed the NSC. The department held several community meetings throughout the design process to seek input. Community members asked for decorative murals so at Wellesley a mural was commissioned to depict trains, which have been a large part of the neighborhood. “They are remarkable, the design and how they look,” Qualley says.

The current $64 million project, including change orders related to the soils associated with the train station contamination, extends the NSC south from Columbia Avenue to the Spokane River.

“We knew there would be some contamination, but not this much,” Qualley says.

The Current Segment
Max Kuney Construction of Spokane received the $51.6 million current contract. This project represents the fifth NSC contract for company, founded in 1930.

“It’s unique to build a project of this size that is an all new alignment,” says Kelly Griffith, Senior Project Manager with Max Kuney Construction. “We are not dealing with traffic control or staging.”

Work began in April 2021 on the U.S. 395 - NSC Spokane River to Columbia segment.

Sennebogen LLC
Your local Sennebogen LLC dealer
Brandeis Machinery

The 2-mile-long project includes constructing four new bridges, two with steel girders and two with prestressed concrete girders; more than 5,500 linear feet of cantilevered retaining walls; two roundabouts; and placing more than 2.5 miles of concrete pavement.

Qualley reports that roundabouts have proven safer than signalized intersections and provide for better traffic flow. The department plans on introducing more roundabouts.

“What’s unique are the large retaining walls,” Griffith reports. “They are 32 feet tall. You do not see walls like that anymore.”

Those retaining walls required many large concrete pours. The project includes more than $1 million in single-use form liner for bridges with the decorative murals. Kuney is using large cranes to lift sizable formwork panels.

“It was challenging in that it is all on the Burlington Northern’s property,” Griffith says. “We are running parallel to the tracks.”

Kleemann
Your local Wirtgen America dealer
Brandeis Machinery

Crews have had to work around active trains. Everyone must follow railroad safety and inspection requirements. Griffith says the work is very intricate. When crews are working next to the tracks, a BNSF flagger is on site to let construction personnel know when a train is approaching.

During the summer of 2021, crews began working on the Wellesley Avenue interchange. In April 2022, they started setting the concrete girders on the bridge spanning Euclid Avenue. By September, Euclid was open so work could progress on Wellesley.

The bridge at Wellesley has steel girders. All of the foundations are concrete. The deck has multiple angle points and three grade breaks. Wellesley is temporarily closed as the work continues.

Kuney is using machine grading and GPS. “There is very little survey for roadway, no hubbing, everything is off GPS,” Griffith says.

This segment is scheduled to finish in fall 2023, but with a possible opening for Wellesley traffic earlier in the summer of 2023.

The Shared-Use Trail
Leeboy - Pavers/Asphalt
Your local LeeBoy dealer
Brandeis Machinery

In addition to the NSC, work is progressing on the Children of the Sun Trail, a shared-use path adjacent to the highway. The current $15.3 million project extends the trail from Columbia Avenue to Carlisle Avenue. It will include three pedestrian bridges.

Graham Contracting of Seattle received the design-build contract in May 2021. The project is scheduled for completion in 2023. Kuney coordinates with Graham daily to avoid any conflicts.

The Upcoming Projects
The department plans to advertise for construction of the Spokane River Crossing bridge – connecting segments already under construction – in the winter of this year, with construction expected in 2023.

That will be followed by projects to extend the freeway to Sprague Avenue. It includes a southbound off ramp to SR 290 and a northbound on ramp from SR 290.

A final phase will bring the NSC from Sprague to I-90, with an interchange still under design. Construction is scheduled to start in 2024.

The entire project is scheduled for completion in 2028. When finished, “it’s going to benefit everyone,” Qualley concludes.

Vogele
Your local Wirtgen America dealer
Brandeis Machinery

Photos courtesy of the Washington State Department of Transportation

Komatsu Dealer Program
Your local Komatsu America Corp dealer
Brandeis Machinery
Kleemann
Your local Wirtgen America dealer
Brandeis Machinery
Leeboy - Pavers/Asphalt
Your local LeeBoy dealer
Brandeis Machinery