Building Excellence

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Oregon DOT Completes Major Improvements to I-105 Bridges in Eugene

by: Mark Bird
Crews from Wildish Standard Paving Co. worked with Oregon DOT to reconstruct aging bridges and overpasses on I-105 near Eugene.
Crews from Wildish Standard Paving Co. worked with Oregon DOT to reconstruct aging bridges and overpasses on I-105 near Eugene.
The Interstate 105 Bridge Preservation Project, recently completed by the Oregon Department of Transportation (ODOT), has rehabilitated several I-105 bridges and associated ramps between the Delta Highway Exchange and downtown Eugene, bringing the structures up to current standards. The bridges, built in the late 1960s and early 1970s, were in need of major repairs and upgrades – including guardrails that meet current crash standards, structural deck paving overlays, seismic retrofits, joint replacements, and new lighting to replace the old.

Eugene, home of the University of Oregon, is a thriving town, and I-105 is one of two primary routes from the north end to the downtown area. While most of the traffic along the route is during commute hours, it also serves as a freight route and route for tourists to the Oregon coast. The average daily traffic (ADT) through the project area is 60,000 vehicles (per 2016/2017 data), and the ADT is projected to be 66,100 vehicles by 2038.

The Bridge Preservation Project began in October 2018 and was complete in October 2020. It is an ODOT Bridge Program Bridge Preservation project using State and Federal funds; the total project cost is approximately $19.6 million. The contractor on the project is Wildish Standard Paving Co. and the designer/engineer is OBEC Consulting Engineers (now known as DOWL).

Bridge Project was Completed in Multiple Stages
Angela Beers Seydel, ODOT Public Information Officer, explained that the project was broken up into three main construction stages, with each stage having multiple phases to organize the work:

Stage 1: September 2018 Through March 2019

“This stage focused on the removal of an obsolete bridge which was no longer needed and was in need of repairs,” said Beers Seydel. “Because this bridge was for a route that will not be built, and because it needed repairs, the decision was made to remove the structure. By using cellular concrete, and with the limited vertical clearance, the fill was able to be placed up to the bottom of the steel girders before traffic had to be moved off of half of the structure for staged removal. This minimized the disruption time to traffic for this work.”

Kleemann
Your local Wirtgen America dealer
Brandeis Machinery

Stage 2: November 2018 Through October 2020

Overhang access began in November 2018, while joint replacement started in December 2018. All portions were complete by November 2019, except for some seismic details and drains under the structures, which were complete October 2020.

“This stage involved five bridges at the west end of the project – commonly seen as on and offramps to I-105,” explained Beers Seydel. “We replaced bridge joints, bridge rail, and moment slabs, installed luminaires, and installed Carbon Fiber Reinforced Polymer (CFRP) bridge strengthening at specific locations. Also, we performed seismic retrofits and resurfaced the bridge decks with PPC (Premixed Polymer Concrete).

“The five bridges at the west end for the viaducts received slip formed concrete bridge rails. The structures are not new, but they did receive new concrete rails to meet current standards. Slip forming the bridge rail saves time over conventional forming, reducing the duration of the impact to traffic. The time needed to set up forms, then remove them, and do this repeatedly is greatly reduced. The concrete supplier also benefits from efficiencies that result from larger pour days.”

Stage 3: December 2019 Through October 2020

Komatsu Dealer Program
Your local Komatsu America Corp dealer
Brandeis Machinery

“This stage focused on the Willamette River Bridge and the Delta Highway on-ramp bridge,” said Beers Seydel. “Work included hydroblasting the bridge deck, performing Class 2 concrete repair, installing new bridge rail, installing new bridge joints, adding CFRP bridge strengthening in specific locations, and resurfacing the bridge deck with High Performance Concrete. Thermoplastic striping is used on the entire project.”

Beers Seydel noted that pre-pandemic, the plan was that no lane closures would be allowed June 19 to 28 or July 24 to 28, for U.S. Olympic Track and Field Trials and the Lane County Fair, both large local events. However, because of the pandemic, the Olympic Trials were postponed until 2021, and the County Fair was cancelled. Thus, traffic was very light, and the project was allowed to move directly into the eastbound closure upon opening westbound.

Project Challenges Addressed Through Planning and Communication
From the beginning, the I-105 Bridge Preservation Project presented unique challenges to the area, Beers Seydel reported. Crews working on the ramps had to be scheduled tightly, to keep the ramp closure times to a minimum. ODOT worked with the contractor to shorten the planned closure times as much as possible to allow access back to travelers as quickly as possible. The overall schedule was altered so that major closures were planned to occur when local schools and the University of Oregon were not in session.

“An additional challenge to the community was a second major intersection reconfiguration project occurring at the north end of the connecting highway, just several miles away,” she said. “Many commuters had to go through both construction zones daily, so coordination between projects has been vital.

“The initial construction plan included months-long closures on each ramp, some at the same time. It quickly became apparent that initial lane closures were having significant traffic impacts throughout the community, even before the ramp closures began. In effect, our messaging was too successful and the community scrambled to other routes the first day, causing traffic jams in places never seen before. The city modified traffic light timing and we provided some upgraded equipment for traffic monitoring, such as new cameras, linking them into our traffic map notification system, TripCheck.com.

“When encouraging people to trust that they would be able to get through the construction zone with short delays most of the day wasn’t enough, we paused the project for a few weeks and reworked the construction schedule in cooperation with Wildish. The result was eight to 12-week closures of ramps, rather than three to six months.

Leeboy - Pavers/Asphalt
Your local LeeBoy dealer
Brandeis Machinery

“We developed and implemented a comprehensive communication plan, partnering with the city of Eugene, Lane County, and the local bus service transportation options group, Point2Point. Our transportation options division of ODOT provided outreach funding and support for innovative partnerships, including transit, bike share opportunities and business outreach. We shared information early and often about the project through direct email, radio advertising, and presentations to schools, business partners, and community organizations.”

Another challenge was keeping the multi-use paths underneath the Willamette River Bridge open on both sides of the river during construction. Protection measures were put in place to ensure the safety of people on the path, Beers Seydel says. “The contractor provided a spotter on the path to keep users safe when working over it. There was a handrail with fabric containment as well as the existing concrete rail base that was left in place.”

Moreover, much of the later project work took place during the pandemic, and then the Oregon wildfires, which both caused much upheaval. Overall, however, the project stayed ahead of schedule, Beers Seydel reports, due to the ability to continue working through the COVID-19 related event cancellations and reduced traffic. “The poor air quality and evacuations from local forest fires caused some missed work shifts. At the end of Phase 2, rain delayed striping about a week.

“The crews have had to be mindful of 6-foot social distancing,” said Beers Seydel. “Wildish implemented new social distancing safety protocols for complying with the pandemic. They also secured a portable hot water handwashing station onsite for crew members. We focused on completing the work needing lane closures before traffic picked up again, to minimize the impacts on the travelling public.”

Completed on Schedule, Project Will Serve Needs For Decades
The extensive I-105 Bridge Preservation Project has addressed the issue of multiple 50- to 60-year old bridges, which were in need of major repair and earthquake reinforcement to ensure they continued to be available to meet the community’s transportation needs. The project was ultimately completed on schedule even with multiple challenges, including retaining traffic flow, COVID-19 restrictions, and wildfire devastation. The challenges of renovating bridges in the heart of a city such as Eugene where there is plenty of proactive involvement were met successfully by Wildish and the ODOT team. Stakeholder input caused stages and work plans to be modified to respect input from the public and local governments.

Tim Hendrix, Manager, Wildish Standard Paving Co. said, “We appreciate the community working with us to get through the multi-year project and expect that now it will be in use for decades to come. U.S. Representative Peter DeFazio, 4th District covering Eugene/Springfield, took a personal interest to provide input for the job team to consider as it searched for ways to minimize and mitigate traffic inconveniences.

Vogele
Your local Wirtgen America dealer
Brandeis Machinery

“2020 was a year of unexpected challenges. The project was completed in spite of learning to perform work with newly developing COVID-19 protocols, in spite of important protests and yet unfortunate riots causing damages to the job, and in spite of delays to some work activities related to unprecedented smoke and air quality issues. All the players and stakeholders should be proud to have worked together to push this project cross the finish line safely, healthily, with superior quality and ahead of schedule.”

Epiroc
Your local Atlas Copco CMT USA dealer
Brandeis Machinery
Leeboy - Pavers/Asphalt
Your local LeeBoy dealer
Brandeis Machinery
Vogele
Your local Wirtgen America dealer
Brandeis Machinery