To better accommodate the new Next Gen cars, the quad-oval track in Hampton, Georgia, needed to be altered considerably, which included modifying the banking on the turns from 24 degrees to 28 degrees and narrowing much of the rest of the track from 55 feet to 40 feet. The surface of the track also includes multiple layers of asphalt with self-draining features.
The project was completed in just six months, thanks to a talented construction team, creative earthwork and paving workflows, an advanced grade control platform, and flexible software.
That education began in 1996. When Bruton Smith, Owner/CEO of Speedway Motorsports, Inc., bought the Bristol Motor Speedway NASCAR short track in Bristol, Tennessee, he sought to significantly expand the venue seating (from 71,000 to 118,000) and parking areas in just a year.
Smith contracted Chad Baker, Owner of Baker’s Construction Services, to work on the parking lots, bleacher expansion and other infrastructure improvements. A few years later, Baker was contracted again to regrade the .25-mile dragstrip located on the Bristol Motor Speedway site.
Your local Trimble Construction Division dealer |
---|
SITECH West |
SITECH Southwest |
Jerran Owens, current Survey and Machine Control Manager for Baker’s Construction Services, was the layout surveyor on the dragstrip project. “We did that with strings,” he recalled. “By 2006, we were contracted to regrade the oval track – that’s when we entered the machine control space.”
At the time, Baker’s Construction Services purchased the Trimble GCS900 Grade Control System for its Caterpillar D6N Dozer and a motor grader. The firm quickly became a leading grading contractor in the region.
“The speedway project was very successful and set us on a course for considerably more racetrack work over the next decade,” said Owens. “It also sparked a commitment to machine control, and particularly 3D.”
Since those early days, Baker’s Construction Services’ technology toolbox has grown significantly to including nine base stations and rovers, 20 machine control systems that include the Trimble GCS900 system, as well as the newer Trimble Earthworks Grade Control Platform and Trimble SPS930 Universal Total Stations (UTS).
“We run all 3D now, whether we’re working on a racetrack or a roadway,” Owens said. “Over the years, we learned how to use these tools to optimize our skills on flat areas, and then translated those lessons learned to extreme conditions like high sloped racetracks.”
Your local Gomaco dealer |
---|
Terry Equipment |
That expertise would prove especially beneficial on the Atlanta Motor Speedway.
“The challenge was achieving an as-designed subgrade to tolerance on those steep slopes,” said Owens.
To begin the effort, the engineer provided a finished grade model. Owens exported that file as a Trimble Terrain Model (TTM) and sent it to an excavator and a dozer equipped with Trimble Earthworks using UTS on the jobsite. UTS proved a better solution than GNSS on the tight turns of the track. Owens continued, “The goal was to achieve a plus or minus .10-foot surface irregularity tolerance on the dirt, and further, the owner didn’t want to see anything above .05-feet on the plus side.”
According to the Baker’s Construction Services team, the Trimble Earthworks ‘Autos’ was particularly beneficial to meeting those specifications. Highly experienced Operator Jessie Buchanan, for instance, relied on the Trimble Earthworks’ Autos functionality on a Caterpillar 336 Next Generation Hydraulic Excavator to dig the subgrade and place the underdrain all around the track.
In addition, the built-in functionality and features of the software helped keep operators within specification. For example, operators used the software to configure offsets independent of GNSS or UTS to assure true offset distances.
Your local Trimble Construction Division dealer |
---|
SITECH West |
SITECH Southwest |
“As we built the steep slope of the banks, we needed to use a perpendicular offset versus a vertical offset to maintain surface smoothness,” said Owens. “On a 28-degree bank the difference between vertical and perpendicular measures could be as much as .12-feet, well outside of the contract requirements. Fortunately, Trimble Earthworks lets us select that option.”
With the ability to select perpendicular or vertical direction for the offset, Baker’s Construction Services’ operators were able to achieve the most accurate subgrade surface.
Baker’s Construction Services attributes its equipment and technology provider SITECH Mid-South for helping the firm’s operator fully understand and utilize the capabilities of the software.
Blake Pressly, a Technology Consultant with SITECH Mid-South, said, “We have a lot of steep slopes in Tennessee, so we train all of our customers who specialize in infrastructure and mining about how to run perpendicular offsets. For any extreme banking condition, our customers have to make sure everything is calibrated, shimmed and tightened up to eliminate all human error possible to meet limits.”
“That was one of the biggest things that made this project possible in the tight timeline,” said Scotty Burke, Project Superintendent and Dozer Operator for Bakers Construction Services. “If not for the Perpendicular capabilities, I believe the dirt work would have taken us much longer because we would have had to keep checking and rechecking to meet the defined specifications.”
Your local Trimble Construction Division dealer |
---|
SITECH West |
SITECH Southwest |
Baker’s Construction Services’ skills with using technology-enabled equipment in complex situations would come in handy when the paving company needed some help on that same banked area.
Sunmount Paving Company was contracted to pave the track once the subgrade was completed by Baker’s Construction Services. The common workflow for paving banks such as the new track is to use a strong arm crane over the top of the track to hold the paving equipment on the steep banks. That wasn’t possible at Atlanta Motor Speedway because of the existing infrastructure along the banked walls.
Sunmount tried to do it from the flat part of the track, but the subgrade is a silty, sandy soil, therefore the paver was prone to slipping, thus losing accuracy and surface quality.
Quick thinking and some collaboration kept the project moving forward. John Rauer, Division Manager for Sunmount Paving Company and Superintendent on the Atlanta Motor Speedway project asked Burke, who was still on site doing cleanup, for ideas.
“He wondered if we could place base stone on the banks with a dozer instead of a paver, which would be easier to hold up on the bank,” said Burke.
Your local Trimble Construction Division dealer |
---|
SITECH West |
SITECH Southwest |
The crews re-surveyed the area and then used the Caterpillar D6K Dozer equipped with UTS. Burke concluded, “It took a little longer to get the job done, but our combined crews and equipment were able to achieve the accuracy that the owner specified.”
The Atlanta Motor Speedway project finished six months after the demo began, and it was ready for the first race on the track in March 2022.