Dixie Contractor

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Double Diamond Interchange Improves Traffic Flow at I-26 Interchange in Tennessee

by: Debra Wood
Crews pave a section of the Boone’s Creek Road interchange as part of the I-26 interchange project in Washington County, Tennessee.
Crews pave a section of the Boone’s Creek Road interchange as part of the I-26 interchange project in Washington County, Tennessee.
The $15.6 million reconstruction of the Interstate 26 interchange with Boone’s Creek Road (State Route 354) in Washington County, Tennessee, has improved vehicle flow, enhanced safety, and supported economic growth in the area.

“Traffic congestion in the area had been an issue, and bridge height has been a problem for years,” says Mark Nagi, Spokesman for the Tennessee Department of Transportation (TDOT).

The bridge height problem was resolved by the installation of a radar, over-height detection warning system, with lights and sirens.

“The structure had been struck by over-height vehicles in the past, and this portion of the project corrected deficiencies and provide warnings in the future to avoid potential conflicts,” Nagi explains. A newly configured interchange has eliminated congestion.

Improving Functionality
The original interchange with three-lane Boone’s Creek Road was built in the 1960s. About 54,000 vehicles drive on I-26 at this interchange daily, and 20,000 per day drive on Boone’s Creek Road. It has become poorly functional with traffic backing up onto the interstate. This section of the road was widened to five lanes, two in each direction and a turn lane.

A double diverging diamond was a primary aspect of the project.

Gomaco
Your local Gomaco dealer
Ring Power Corporation

“This is the third diverging diamond constructed in Region 1 and the first to be designed in house with TDOT personnel,” Nagi reports.

The new configuration provided two lanes in each direction on Boone’s Creek Road. And two signalized intersections were added at either end of the overpass and a shared-use pedestrian and bicycle path with crosswalks and signs was added under the bridge on the opposite side to the creek.

Additionally, the job required completing water and sewer line upgrades, adding retaining walls and making a bridge repair to the steel beams damaged by trucks through heat straightening.

TDOT awarded the construction contract to Summers-Taylor of Johnson City, Tennessee – a fourth-generation family-owned and operated heavy construction firm founded in 1932 by Lines Taylor as a general maintenance and construction contractor. The company grew after World War II and built schools, hospitals, and retail shops. The founder’s daughter married Robert W. Summers, who joined the firm and switched direction of the company to road projects and paving. Subsequent generations entered the utility work and bridge construction business.

Summers-Taylor employs about 550 employees. It operates four asphalt plants and 11 concrete plants in East Tennessee. The company will travel to northern Alabama and Georgia for bridge work and roadwork in North Carolina and Virginia. Summers-Taylor’s motto is “Quality is our shield.”

Bomag - Roller
Your local Bomag Americas dealer
Linder Industrial Machinery

“We have a dedicated workforce, that is experienced and knowledgeable,” says Grant Summers, President of Summers-Taylor. “And we are proud of our work.”

Configuring a Diverging Diamond
The modification of I-26 Exit 17 reconstructed exiting ramps and connector roads to transform the interchange into a double diverging diamond, which Nagi says allowed for increased capacity on wider exit ramps and additional lanes under I-26, without needing additional right of way or reconstruction of the bridge.

“The unique crisscross design allows two directions of traffic to temporarily cross to opposite sides of the roadway in order to travel across the overpass, and then cross back and resume the original travel pattern,” Nagi says. “Concrete dividers, stop bars, traffic signals, and extensive signage guide motorists through the interchange.”

Summers reports that once motorists became familiar with the new configuration, traffic flowed through easily.

Maintaining Traffic Flow
Work began in September 2019. The underground sewer and water lines increased the complexity of the job, Summers says. The sewer line was laid 17 feet below a travel lane in solid rock. “That involved a lot of round-the-clock work,” Summers says.

Summers-Taylor shifted traffic to an outer lane and shoulder while working on the utility relocation, which required temporary connections.

Installing retaining walls for the bike path also presented challenges. Summers-Taylor crews drilled piles for soldier-pile lagging walls.

Traffic was maintained on the interstate for most of the project, with multiple traffic control phases. Summers estimates it took about 15 or 20 traffic shifts.

“The biggest challenge was maintaining traffic flow while the project was under construction,” Nagi says. “Multiple traffic phases were necessary to build the additional lanes, curbing, storm and sanitary sewer installation, and ramp widening.”

The project required a mix of asphalt and concrete paving, and Summers-Taylor performed both. The ramps are paved with concrete and the mainline asphalt.

“The asphalt rides well,” Summers says. “It’s a high-quality project, which we are really proud of.”

A weekend road closure began on March 19, 2021, at 10 p.m., when all traffic exiting I-26 could only turn to the right, while crews poured concrete islands, added a barrier wail, signs, pavement markings, drainage, sewer, traffic signals, and the asphalt surface. The exit opened to traffic on March 22, 2021, at 4 p.m.

Wirtgen America Inc
Your local Wirtgen America dealer
Dobbs Equipment (DXC)
Power Equipment Co

“The contractor had between 80 and 90 different employees working on the project during the course of that weekend, and TDOT had 10 employees working in shifts to ensure contract compliance,” Nagi recalls.

Coordination Creates Success
Before and during the closure, TDOT conducted an extensive outreach initiative, informing local businesses, emergency responders, and legislatures of the upcoming closures. No incidents or accidents were reported as a result of the closure.

“It was a huge coordination effort,” Summers says. “There was a substantial amount of equipment used.”

Summers-Taylor had on-site track-mounted excavators, cranes, track-mounted loaders, rubber-tire backhoes, rubber-tire excavators, articulated trucks, dozers, motor graders, a milling machine, and paving machine.

“We used full GPS-controlled equipment for grading,” Summers says.

Additionally, “shallow intact rock has been an issue with excavation throughout the project work, specifically with deep sewer-line installation. Blasting was required some areas prior to grading activities,” Nagi continues.

Leeboy - Pavers/Asphalt
Your local LeeBoy dealer
Power Equipment Co

The interchange opened to traffic in May 2021. Summers reports that upon opening, the traffic no longer backed up in the interchange.

“I’m proud our team was able to handle this job with its complexity with minimal impact to the public,” Summers concludes. “We were happy to be involved in something this complicated that really makes an impact on people’s lives.”

Photos courtesy of Summers-Taylor

Doosan Infracore Portable Pwr
Your local Bobcat dealer
Pinnacle Central Co Inc
Wirtgen America Inc
Your local Wirtgen America dealer
Dobbs Equipment (DXC)
Power Equipment Co