Dixie Contractor

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Archer Western, Traylor Bros. Lead $865M Design-Build Project for the Largest Bridge in Florida

by: Larry Bernstein
The team uses a conveyor system to place concrete for the Howard Frankland Bridge project. A concrete truck is on the existing bridge, and the concrete is conveyed over the water and onto the next bridge.
The team uses a conveyor system to place concrete for the Howard Frankland Bridge project. A concrete truck is on the existing bridge, and the concrete is conveyed over the water and onto the next bridge.
A conveyor system is used to place concrete during construction of the new Howard Frankland Bridge.
A conveyor system is used to place concrete during construction of the new Howard Frankland Bridge.
The project includes sheet pile walls, MSE walls, toll structures, three additional pedestrian bridges, roadway, and other miscellaneous structures. (Photo courtesy of Walsh Group)
The project includes sheet pile walls, MSE walls, toll structures, three additional pedestrian bridges, roadway, and other miscellaneous structures. (Photo courtesy of Walsh Group)
The Howard Frankland Bridge is the largest bridge — based on square footage — constructed in the state of Florida. (Photo courtesy of Walsh Group)
The Howard Frankland Bridge is the largest bridge — based on square footage — constructed in the state of Florida. (Photo courtesy of Walsh Group)
UES’ scope included geotechnical exploration, design, PDA testing, pile inspection, and earthwork inspection. (Photo courtesy of Walsh Group)
UES’ scope included geotechnical exploration, design, PDA testing, pile inspection, and earthwork inspection. (Photo courtesy of Walsh Group)
When complete, the project will transform the Tampa area’s longest bridge to eight full lanes of traffic with an enhanced pedestrian experience. (Photo courtesy of Walsh Group)
When complete, the project will transform the Tampa area’s longest bridge to eight full lanes of traffic with an enhanced pedestrian experience. (Photo courtesy of Walsh Group)
Drilling services have been conducted on five barges in the Tampa Bay area. (Photo courtesy of UES)
Drilling services have been conducted on five barges in the Tampa Bay area. (Photo courtesy of UES)
For over a year, the project team has provided drilling services on the Howard Frankland Bridge project. (Photo courtesy of UES)
For over a year, the project team has provided drilling services on the Howard Frankland Bridge project. (Photo courtesy of UES)
Carrying I-275 over Old Tampa Bay, the Howard Frankland Bridge connects Tampa, Florida, and St. Petersburg, Florida. (Photo courtesy of UES)
Carrying I-275 over Old Tampa Bay, the Howard Frankland Bridge connects Tampa, Florida, and St. Petersburg, Florida. (Photo courtesy of UES)
The more than 3-mile-long bridge includes 113 spans supported on two end bents and 112 intermediate piers. (Photo courtesy of Mohammed Al Hasoon)
The more than 3-mile-long bridge includes 113 spans supported on two end bents and 112 intermediate piers. (Photo courtesy of Mohammed Al Hasoon)
UES’ geotechnical exploration and design services determined the foundation support of the piers. (Photo courtesy of Mohammed Al Hasoon)
UES’ geotechnical exploration and design services determined the foundation support of the piers. (Photo courtesy of Mohammed Al Hasoon)
The Howard Frankland Bridge carries I-275 over Old Tampa Bay and connects Tampa, Florida, in Hillsborough County and St. Petersburg, Florida, in Pinellas County. The 3-mile-long bridge opened to traffic in 1960. A parallel bridge opened in 1991, and all southbound traffic was transferred onto the new bridge, while the original bridge (which has been updated over the years) carried northbound traffic. A project — led by a joint venture between Archer Western and Traylor Bros., with BCC Engineering as the engineer of record — is currently underway to replace the northbound bridge.
Out with the Old, In with the New
The old northbound bridge is aging yet remains structurally sufficient. The greater issue is congestion. I-275 is one of the main arteries in the expanding Tampa area. Although two other bridges connect Hillsborough and Pinellas counties, the Howard Frankland Bridge has the most traffic and regularly experiences congestion.

The bridge built in 1960 has four lanes. The new bridge, which will serve southbound traffic while the 1990s-era bridge will be converted to handle northbound traffic, will have eight lanes. There will be four general-use lanes and four express toll lanes (two in each direction).

An additional 12-foot-wide lane will serve as a bike and pedestrian trail. In addition, the Florida Department of Transportation (FDOT) said in a project fact sheet that “the new design improves incident management in emergency response situations and provides additional capacity along a critical evacuation route. A portion of the new bridge is being constructed to hold additional weight and can accommodate potential future transit, up to a light rail transit system.”

According to FDOT’s website, “The additional express lane in each direction will better prepare the Howard Frankland Bridge for the potential of autonomous vehicles. Experts believe that initially, autonomous vehicles (passenger and transit) may operate in dedicated lanes.”

Upon completion, the new bridge will be the largest bridge — based on the square footage of a bridge deck — in Florida, at 2.6 million square feet.

SITECH
Your local Trimble Construction Division dealer
SITECH Tri-Rivers
SITECH Mid-South
SITECH South

Although the bridge is 3 miles, the project length is 6 miles. There is a 2-mile-long causeway on the Pinellas side and a 1-mile-long causeway on the Hillsborough side. This roadwork is necessary to connect the bridges to landbound roads.

Pile Driving and Other Challenges
Pile driving has been the biggest challenge on the job. The geology in Tampa Bay is highly variable. The rock formation is pinnacle limestone, meaning the height at the peak may be 60 feet below the bottom of the bay, while it is 200 feet or more in a valley. The dramatic differences can be as close as 6 feet apart.

“Once you drive into the limestone, the bearing capacity is fairly consistent,” said Greg Fullington, a Program Manager with Archer Western. “Because the location of the limestone layer is highly variable, we performed dynamic testing using Pile Driving Analyzers [PDA] on each to confirm the required capacity is achieved.”

In more consistent underlying soils, the team performs dynamic testing on a few piles, to establish pile driving criteria to use on the remaining piles.

During pile driving, they use a PDA monitor to evaluate the capacity of a pile as it is being driven. The monitor sends a wave of reflection indicating the capacity in real-time.

The lengthy piles are costly and time-consuming to create. “We had to splice pile to get it to the needed length, which takes days,” said Jeffrey Pruett, a Vice President for UES, who served as the geotechnical engineer of record and was responsible for designing and certifying foundations.

As part of the causeway construction, the team built 13,000 linear feet of anchored bulkhead wall to hold the sand and retain it from washing away into the water. The team is installing aesthetics (sails) on the bridge that have foundations when installed on land.

To efficiently place concrete for the project, the team uses a conveyor system. A concrete truck is on the existing bridge, and the concrete is conveyed over the water (110 feet) and onto the next bridge.

“This is a better way to transport the concrete to its point of placement [rather than driving it up on the new deck] for expediency,” Fullington said. Shorter transporting times allow for better control over the quality of the concrete.

Weathering the Storm
Another challenge that can affect every marine project in water is weather, specifically hurricanes — something that Florida is known for. Between 1851 and 2018, records show Florida was hit by 120 hurricanes, the most in the country by far. Of those 120 hurricanes, 37 were Category 3 through Category 5.

“We are constantly watching the weather on the project,” Fullington said.

At its peak, the project had a massive marine fleet (there was also a significant amount of equipment on land), including 27 cranes, seven tugboats, and 74 barges. Moving the marine fleet takes two and a half shifts, while it takes one and a half shifts to prepare the rest of the site.

“We give our people an extra day to [take] care of their personal belongings before a storm,” Fullington said. “We have to make the call [to close down the site] early in the process.”

Altogether, that is five days to prepare for a storm. Fullington estimates it takes three to four days to unpack the equipment after the all-clear sign is given.

The team follows a project specific hurricane plan when preparing for a storm and securing the equipment. So far, the team has had to deal with three hurricanes while performing construction in the water. This necessitated them moving the equipment as described above.

The bridge was designed with hurricanes in mind. According to FDOT’s website, “Hurricane evacuation plans can utilize all the lanes. In the aftermath of Hurricane Irma, this is particularly important for coastal Pinellas County, the most densely populated county in Florida.”

Partnering to Build an Infrastructure Giant
The Howard Frankland Bridge is the largest structure in the area. Upon completion of the $865.3 million design-build project, the bridge will have 113 spans, 22 hammerhead piers, and 90 multi-column piers.

“When you get the opportunity to work on the biggest project in Florida, it’s exciting,” Pruett said.

The project cost has increased since the project began in the spring of 2020. The project value has risen due to enhancements implemented by FDOT, according to Fullington.

“It’s been a fantastic partnership between FDOT, CEI [Construction Engineering and Inspection, who are the owner’s representative and administer the contract], and us,” Fullington said. “We come together to find solutions and keep the project moving.”

The team spends lots of time partnering and on goal alignment. Pruett said the construction team works well together, and having the designer and contractor on the same team makes the process more efficient.

Although the project was awarded in the spring of 2020, the team did significant work on the design before beginning construction in the fall of 2020. The project is on target for its scheduled completion in late 2025. Days have been added to the schedule due to storm impacts.

The Tampa area is experiencing significant growth. The new bridge will accommodate the growth, relieve congestion, and provide multiple benefits for the community.

Iowa Mold Tooling Co Inc
Your local Iowa Mold Tooling Co Inc dealer
Nichols Fleet Equipment
Iowa Mold Tooling Co Inc
Your local Iowa Mold Tooling Co Inc dealer
Nichols Fleet Equipment