TxDOT Gives Update on Loop 1604 Expansion Project

SAN ANTONIO, TX — The Texas Department of Transportation (TxDOT) is moving forward with plans to improve approximately 23 miles of Loop 1604 from SH-16 (Bandera Road) to I-35 in north Bexar County. The Loop 1604 Expansion Project involves several transportation improvements that are designed to improve mobility, reduce congestion, and enhance safety along the high-traveled corridor.

The project includes the following improvements:

  • Expanding Loop 1604 from a four-lane expressway to 10-lane expressway with the addition of two general purpose lanes in each direction
  • Adding one high-occupancy vehicle lane in each direction
  • Reconfiguring the layout of auxiliary lanes and entrance and exit ramps
  • Removing the cloverleaf connectors and replacing the cloverleaf interchange at IH 10/LP 1604 with a five-level direct connect interchange
  • Adding direct connectors
  • Replacing the signalized frontage road intersections with a continuous flow configuration and upgrading Blanco Road and LP 1604 to an innovative intersection
  • Accommodations for bicyclists and pedestrians, water quality protection, and other highway features
  • All improvements are located within the existing right of way and easements


Segment 1: Loop 1604 from SH 16 (Bandera Road) to I-10
  • Anticipated Completion: 2024
  • Estimated Cost: $148 million


Segment 2: Loop 1604 and I-10 Interchange
  • Anticipated Start: 2022
  • Anticipated Completion: 2027
  • Estimated Cost: $291 million


Segment 3: Loop 1604 from I-10 to US 281
  • Start: Late summer 2021
  • Anticipated Completion: 2025
  • Estimated Cost: $234 million


Segment 4: Loop 1604 from US 281 to Redland (Unfunded)
  • Anticipated Letting Date: 2025
  • Anticipated Start: TBD
  • Anticipated Completion: TBD
  • Estimated Cost: $130 million


Segment 5: Loop 1604 from Redland to I-35 (Unfunded)
  • Anticipated Letting Date: TBD
  • Anticipated Start: TBD
  • Anticipated Completion: TBD
  • Estimated Cost: $265 million