TxDOT's Beaumont District will be reconstructing and expanding I-10 and US 69 where they converge in Beaumont, Jefferson County, Texas, as part of the 10/69 Interchange Projects. The proposed project is anticipated to improve mobility, reduce congestion, and also improve emergency evacuation.
Overall improvements for the interchange projects include:
- Widening the I-10/US 69 roadway in each direction from four to six lanes between the Cardinal Drive and Eastex Freeway interchanges
- Widen approaches to the Cardinal Drive and Eastex Freeway interchanges on I-10 and US 69 from two to three lanes
- Adding new frontage roads for continuity throughout the project limits
- Relocating I-10 ramps and constructing two-lane direct connectors in each direction where I-10 and US 69 converge
- Removing the Maury Meyers Bridge (Liberty/Laurel Overpass) to address a height constraint for freight and includes upgrading drainage to meet current design standards
This project will be constructed and funded as two separate construction projects: the Eastex Interchange is scheduled to go to construction in summer 2024 and the Cardinal Drive Interchange is scheduled to go to construction in summer 2022. Schedule times are estimates only and are subject to change.
- Environmental clearance obtained: Summer 2020
- Right-of-way acquisition: Summer 2022
- Construction start: Summer 2024
- Construction completion: Anticipate 60-month construction duration
- Construction cost: $320 million
Project construction will include:
- Widening of the freeway from four to six main lanes and reconstructing the interchange from Hollywood Overpass, east to 7th Street
- Constructing frontage roads
- Constructing sound walls
- Constructing retaining walls
- Constructing 15 bridges
- Environmental clearance: Summer 2020
- Right-of-way acquisition: No right-of-way required
- Construction start: Summer 2022
- Construction completion: Anticipate 60-month construction duration
- Construction cost: $300 million
Project construction will include:
- Widening of the freeway from four to six main lanes and reconstructing the interchange from CR 131 (Walden Road) east to Hollywood Overpass
- Constructing frontage roads
- Constructing retaining walls
- Constructing 19 bridges: The number of bridges to be constructed has increased from 13 bridges to 19 bridges. In addition, 12 out of the 13 planned bridges will need to be lengthened to meet TxDOT design criteria.