Western Builder

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

New Christina River Bridge Gives Commuters and Pedestrians From Both Sides Greater Access to Redeveloped Areas

by: Larry Bernstein
Beams for the new Christina River Bridge in Wilmington, Delaware, are lifted into place.
Beams for the new Christina River Bridge in Wilmington, Delaware, are lifted into place.
The Delaware Department of Transportation’s (DelDOT) Christina River Bridge and approaches project in Wilmington, Delaware, is expected to benefit area residents in multiple ways. DelDOT believes the project – which is essentially complete – to have an economic impact, improve travel in the area, and assist pedestrians.

The west side of the Wilmington riverfront experienced redevelopment starting in the mid-1990’s. The area is home to a convention center (Chase Center On The Riverfront), minor league baseball stadium (Frawley Stadium), and retail establishments (movie theaters, restaurants, etc.). One of the first additions to the redeveloped west side was a Riverwalk. The wide pathway is a heavily used shared use trail that is suitable for walkers, joggers, and bikers.

To date, the redevelopment activity has not extended to the east side of the river. “One of the goals of the project is to connect the east side of the Christina – which has underserved neighborhoods – to the west side for employment, recreation, and shopping opportunities,” said Carey Webb, a Project Manager for design firm RK&K.

In addition to the economic development benefits, the multimodal bridge will also connect to the existing Riverwalk. Bikers and pedestrians will now have direct access from the east side to the shared used path on the west side.

Lastly, traffic backups occur when there are events at the convention center or baseball games at the stadium. The average daily traffic count of the bridge is 5,750. “The bridge will provide some event traffic relief and a more direct route to I-495, a major artery in the area,” said Webb.

The Bridge and Approaches
The centerpiece of the construction is the 470-foot bridge, which carries one lane in each direction. In addition to the two 12-foot lanes and shoulders on each side, there’s a protected 14-foot-wide shared use path on the north side of the bridge exclusively for bikers and pedestrians. It connects to the Riverfront walkway as well as other bicycle/pedestrian facilities in the area.
Volvo CE
Your local Volvo Construction Equipment dealer
Nuss Truck & Equipment

Besides the bridge, the team added 1.75 miles of shared path and 1.3 miles of local complete streets. “Because this is a brand-new bridge, there were no streets and approach roadways to access the crossing,” said Webb. So, some streets were added, while others were reconfigured and widened.

Lastly, the east side saw the addition of a large new intersection with U.S. 13 and the shared paths.

Unique Construction Aspects
One of the requirements was to keep the bridge low, as the stakeholders did not want it protruding high above the river for aesthetic purposes. In addition, DelDOT preferred a concrete bridge for future maintenance considerations.

These project requirements – along with the necessary main span length for river navigation – led to a spliced girder bridge selection, a technique more common to steel bridges. “This is the first precast concrete spliced girder bridge in Delaware, and it looks beautiful,” said Kevin Lindell, a DelDOT Project Manager, who oversaw the project construction from the state’s side.

“Because we had a limited window for the superstructure, we had to design a special girder that’s more typical for a steel bridge but not for this type of bridge,” said Robert Healy of RK&K, who served as the Bridge Design Manager for the project. The girders are thicker over the piers than they are over the mid span. “These haunches made the design of the girders more efficient, as well as adding to the aesthetics.”

To construct the three-span, five-girder bridge, the contractor set the girders over the piers and stabilized them with temporary piling. One end of each girder was attached to a heavy gage steel I-beam.

“This allowed us to connect the post-tension ducts, and high strength concrete to join girders together,” said Nick Hetrick, a Region General Manager for R.E. Pierson, who served as the contractor for the project. “Once the girders became continuous via post-tensioning, we extracted the temporary piers and girders.”

Soil Considerations
The soil on the east side of the bridge is poor – including some hazardous material contamination – and significant ground improvement was required. To remedy this, the team implemented the proprietary controlled modulus column technique, which is designed to improve soils with weak load bearing capacities. Hetrick describes the process, “Reverse augers are drilled in the ground till they reach a pre-determined level. Then, they’re filled with grout as the auger is backed-out, and an embankment is built on top to support the loads.” 

For the west side approach, which is much shorter, the team used polystyrene block embankment to load balance and prevent settlement. There are also precast concrete panel retaining walls, which implemented aesthetic form liners to resemble natural stone. According to Hetrick, once these walls were painted, Riverwalk users had to be convinced it was not real stone.

Another challenge the team faced was the geometry and orientation of the bridge. The profile, or under clearance, is limited and also had a daily 5-foot tidal swing, which made access to the bridge for construction difficult. A temporary trestle was constructed on the west side, and R.E. Pierson’s large marine fleet was used to construct the substructure.

One of the project goals was to allow pedestrians to go directly from the east side of the bridge to the Riverwalk. “We designed it so the end of bridge on west side goes over the existing Riverwalk with a cast-in-place underpass, and then an accessible ramp allows people to go back to grade and get on the pathway,” said Healy.

Keep Moving Forward
The bridge and approaches were originally one contract. However, it was ultimately switched to two because of right-of-way. “We wanted to get started on the bridge while acquiring the necessary right-of-way for the approaches,” said Lindell.

The bridge broke ground in May 2017 and it was opened to traffic in June 2020. Work on the approaches began in fall 2018 and was substantially complete in the summer of 2020. However, the team continues to work on additions and punch list items.

LBX Link Belt Excavators
Your local Link Belt dealer
Hayden-Murphy Equipment Co

The team instantly ran into issues related to utility relocations when work began on the approaches. “The utilities were a critical element as the plan was to relocate the powerlines underground,” said Hetrick. “We did everything we could to keep it on schedule.”

And they made it. “We had a great team that worked hard together,” said Lindell. “Pierson was committed to keep it moving, and RK&K made changes on the fly to keep us moving forward.”

“If we ran into a road-block, we came up with a resolution to keep it going, or adjusted the phases,” said Hetrick.

The minor league baseball season also impacted timing. To not inconvenience traffic around the stadium during the season, the team did road work in the winter.

The federal government supplied 80 percent of the funding for the project and the state paid the remainder. The bridge contract was $30 million. It came in $3 million under budget due to a redesign of the foundation. The approaches contract was for $25 million, but went over budget due to the utility relocations.

Komatsu Dealer Program
Your local Komatsu America Corp dealer
Road Machinery and Supplies Company

With the projects essentially complete, the commuters and pedestrians of Wilmington have greater access to all points around the river. “The new bridge provides a multimodal connection between the redeveloped west side and Riverwalk and the current industrial east side with the hope it will spur economic development,” said Lindell.

Volvo CE
Your local Volvo Construction Equipment dealer
Nuss Truck & Equipment
LBX Link Belt Excavators
Your local Link Belt dealer
Hayden-Murphy Equipment Co
Komatsu Dealer Program
Your local Komatsu America Corp dealer
Road Machinery and Supplies Company