Constructioneer

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Rehabbed Pavement to Provide Smoother Ride on California State Route 23

by: Larry Bernstein
Night work takes place on a section of SR 23 northwest of Los Angeles.
Night work takes place on a section of SR 23 northwest of Los Angeles.
Concrete work takes place at night on SR 23.
Concrete work takes place at night on SR 23.
Workers break up a lane of SR 23 near the Tierra Rejada Road exit.
Workers break up a lane of SR 23 near the Tierra Rejada Road exit.
The off ramp at Janss Road before reconstruction
The off ramp at Janss Road before reconstruction
The off ramp at Janss Road after reconstruction
The off ramp at Janss Road after reconstruction
Reconstruction on SR 23 required excavating old lanes.
Reconstruction on SR 23 required excavating old lanes.
An excavated lane near Tierra Rejada Road
An excavated lane near Tierra Rejada Road
SR 23 construction required some lane and exit closures near Moorpark.
SR 23 construction required some lane and exit closures near Moorpark.
California’s State Route 23 runs between the Santa Clara River and the Pacific Coast Highway in Malibu. This area, which is northwest of Los Angeles, includes Ventura County. The California Department of Transportation (Caltrans) is currently working on a stretch of SR 23 in Ventura County that connects Thousand Oaks, Moorpark, and Simi Valley.

SR 23 is a six-lane highway. In the area where the project is taking place, the average daily traffic count is approximately 116,000 vehicles, with nearly 4 percent being truck traffic. The project came about when the Caltrans Pavement Condition Survey (PCS) Inventory indicated that the existing pavement on an 8.1-mile stretch of SR 23 had minor structural problems, including cracks, potholes, and distressed slabs. The report noted that continued deterioration of the pavement will decrease ride quality. Caltrans conducted a field investigation that confirmed PCS’s findings.

The SR 23 project will replace pavement on the outer two lanes of the highway to provide a service life of 40 years. In addition to the pavement work, the team is rehabbing the on- and off-ramps, connectors, and adjacent shoulders. Finally, slabs will be replaced on the inner lane in both directions where needed.

Existing curb ramps will be upgraded in 36 locations to comply with the Americans with Disabilities Act and approach slabs and bridge rails will be replaced at five locations. Signal lights will also be upgraded.

Pandemic Challenges
The SR 23 project began in the summer of 2020. The pandemic was raging and lockdowns were prevalent. Like all construction projects in progress during this difficult time, the SR 23 project faced challenges.

“Complying with the statewide mandates and keeping the team onsite and healthy was a challenge for the contractor,” says Jim Medina, a Public Information Officer for Caltrans – District 7. “It was essential to do so for the safety of the team and to keep the project moving forward as scheduled.”

Gomaco
Your local Gomaco dealer
Gomaco -Contact Local

Regarding infrastructure projects, the pandemic had some positive elements. “California’s temporary stay-at-home requirement significantly reduced daily traffic,” Medina says. “Crews were allowed to begin work earlier in the evening because the commuter rush hour was greatly reduced.” The extended overnight hours increased productivity.

A Local Contractor
The prime contractor for the project is Security Paving Company of Westlake Village, California. The family-owned business has been around since 1949 and has an office in a neighboring city to the project site.

“It was a beneficial because the company is very familiar with the community,” Medina says.

Security Paving Company has worked on several Caltrans projects in the past. “We have a good working relationship with Security Paving,” Medina says. “They’re professional, responsive, and have the manpower to meet the schedule the department sets.”

The project began in July 2020 and was scheduled to be complete this fall. However, Security Paving has managed to accelerate the schedule. The anticipated completion date for the project is several months ahead of schedule, with most work expected to be complete by March before proceeding with punch list items. “Security Paving was able to make great progress in the early stages of the project when traffic was significantly lower than normal,” Medina says.

Another way the team moved the project forward was by having a concrete batch plant located and operating in the highway median. “This allows trucks convenient in and out access to the highway,” says Medina. It also cuts down on the extra traffic and minimizes disturbances on SR 23 and surrounding roadways.

SITECH
Your local Trimble Construction Division dealer
SITECH Northeast
SITECH Allegheny

Throughout construction, three lanes in each direction have remained open, along with an auxiliary lane incorporated to shift traffic patterns as needed during construction. However, Medina notes, the contractor has periodically had to close lanes and or ramps for extended periods, including 55-hour weekend closures.

State Funded by SB 1
The $76.6 million project is almost entirely funded – $75.9 million – by Senate Bill (SB) 1, the Road Repair and Accountability Act of 2017. SB 1 provides $5 billion annually in transportation funding that is shared equally between the state and local agencies. The funds were generated by raising the gas tax, diesel tax, and vehicle registration fees. Federal transportation funds covered the remaining $700,000 of the project.

According to the bill’s website, “This bill created the Road Maintenance and Rehabilitation Program to address deferred maintenance on the state highway system and the local street and road system. The bill required the California Transportation Commission to adopt performance criteria, consistent with a specified asset management plan, to ensure efficient use of certain funds available for the program.”

“Road projects progress through construction phases more quickly based on the availability of SB 1 funds, including projects that are partially funded by SB 1,” Medina says.

When the SR 23 project is complete, the repairs will extend the life of the pavement, provide a smoother and safer ride, and require minimal maintenance expenditure by the department. The road will also be more reliable due to the upgraded drainage systems. Pedestrians can appreciate the ADA curbs. This is one stretch of highway that Caltrans and commuters can be confident in the service for a long time.

Gomaco
Your local Gomaco dealer
Gomaco -Contact Local
Gomaco
Your local Gomaco dealer
Gomaco -Contact Local
Gomaco
Your local Gomaco dealer
Gomaco -Contact Local