Michigan Contractor & Builder

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Washington State DOT Expands I-90 Through Cascade Range

by: Larry Bernstein
Washington State DOT is partnering with Seattle-based Scarsella Brothers, Inc. to reconstruct areas of I-90 through Cascade Range to better protect wildlife who live in the area.
Washington State DOT is partnering with Seattle-based Scarsella Brothers, Inc. to reconstruct areas of I-90 through Cascade Range to better protect wildlife who live in the area.
Interstate 90 traverses the entire United States. The 3,000-plus mile road runs between Seattle and Boston. The Snoqualmie Pass, which is a little over 50 miles from Seattle via I-90 and situated by the Keechelus Lake, is a mountain pass through which I-90 goes through the Cascade Range. The Washington State Department of Transportation (WSDOT) is working on phase three of a decades-long project called the I-90 – Snoqualmie Pass East – Cabin Creek Interchange to West Easton Interchange.

The project began in 1996 with early scoping and design. Construction work began in 2010. In an ideal world with sufficient funding, the fourth and final phase will wrap up in 2030.

Originally, WSDOT determined that the I-90 Snoqualmie Pass area had road closures too frequently due to snow avalanches. The goal was to reduce those closures.

They approached those responsible for maintaining the Baker-Snoqualmie National Forest since they own the right of way in the area. “We have worked closely with the forest service who wanted all road closure issues addressed and attention to be paid to the wildlife that’s indigenous to the area,” said Brian White, the Region Administrator for WSDOT in the South Central Region.

So, the project grew in scope to include a 15-mile-long corridor. The aim is to improve safety and reliability, reduce congestion, and road closures due to avalanches. This section originally had four lanes, plus a truck driving lane while other nearby slices of I-90 had six lanes.

SITECH
Your local Trimble Construction Division dealer
SITECH Michigan

To meet their aims, WSDOT is adding a new lane in each direction, replacing concrete pavement, stabilizing rock slopes, building wildlife crossings, improving sight distance and traffic safety (to compensate for the sharp unsafe curves in the area), and improving traffic management technology systems. The concrete being replaced is over 50 years old and is at the end of its life span.

Constructing for Wildlife
There are many types of animals living in the area including deer, bears, cougars, and coyotes. The U.S. Forest Service identified I-90 as an obstruction to the movement of wildlife, moving between north and south home ranges. In response to that concern WSDOT address wildlife connectivity as part of the Environmental Impact Statement prepared for the highway improvements.

“The National Forest staff identified the local wildlife as a barrier to movement for the roadway,” White says. “The bridgework we are doing is to allow the wildlife to go over or under I-90.”  

The team is building a total of 15 structures for wildlife to use under the roadway and an additional bridge eight bridges for the wildlife to cross over the road. The first overcrossing was constructed in 2018. To build the overcrossing, contractor crews will use stub walls and precast arches and backfill the wall. There will be dirt, rocks, and trees on the overcrossing to make it look like the rest of the forest. “We monitored to see where the wildlife crosses to determine the ideal locations for the bridges,” White says.

Perhaps, the most challenging element of the program is the 70-foot-tall half-mile-wide wall that the team is building into the hillside. The base will be a soldier pile wall, while the top will be a Mechanical Stabilized Earth wall.

A Critical Route
Washington State is very dependent upon trade. I-90 serves as a lifeline for the state’s trade as it connects to the Port of Seattle and the Port of Tacoma with the rest of the country.

“We need to keep I-90 open and traffic moving to allow agricultural products flowing between the ports and overseas,” White says.

The average daily traffic count in this section is between 25,000 and 30,000 vehicles during the week. Truck traffic accounts for 10 to 15 percent of the vehicles. This number jumps to nearly 50,000 vehicles during holiday weekends, as people travel to the area for recreation. Because of the necessity of the road, the contract stipulates that the team keep two lanes open during peak travel times.

Getting equipment and personnel to the work zone was also a challenge. There are no back roads to move materials around. However, a portion of the project has a detour where the contractor has a good portion of the roadway to construct not under traffic.

White also has noted there’s been lots of excessive speeding and inattention from drivers through the work zone. While this has led to accidents, fortunately, there have been no serious injuries or fatalities.

A Challenging Environment
Seattle-based Scarsella Brothers, Inc. is the general contractor on the project. It’s a challenging project that includes oversight from multiple resource agencies. White also says there are streams throughout the area, and summer rains can leave the project vicinity waterlogged. “This is a challenging environment, and general contractors have lots to deal with when building in this area.”

The budget for this phase of the project is $335 million. The entire project is about $1 billion. The state is funding the project and it’s doing so via revenue from several packages starting in 2005. Although early in the process, the project is on budget so far. White is confident the project will remain on budget but cautions, “We’ve had material costs go up 10 to 20 percent over the life of the project, and labor has gone up quite a bit as well.”

Phase three began in the summer of 2022 and is expected to be complete in fall 2028. It’s currently on schedule.

When this phase and the entire project completes, wildlife will have greater protection. I-90 will have greater capacity in the region, giving commuters more reliability. It will also be more resilient and less prone to avalanches and falling rocks. The economic machine that is I-90 will be future-ready.

Photos courtesy of the Washington State Department of Transportation

SITECH
Your local Trimble Construction Division dealer
SITECH Michigan
SITECH
Your local Trimble Construction Division dealer
SITECH Michigan
SITECH
Your local Trimble Construction Division dealer
SITECH Michigan