Pacific Builder & Engineer

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Caltrans' $54.6M Project on SR 20 Concludes, Promising Safer Travel

by: Debra Wood
Granite Construction excavated a substantial amount of dirt, hauling 40,000 loads of material for Caltrans’ $54.6 million project along SR 20. (Photo courtesy of Granite Construction)
Granite Construction excavated a substantial amount of dirt, hauling 40,000 loads of material for Caltrans’ $54.6 million project along SR 20. (Photo courtesy of Granite Construction)
A guard rail is installed along the new alignment on SR 20. (Photo courtesy of Caltrans)
A guard rail is installed along the new alignment on SR 20. (Photo courtesy of Caltrans)
Traffic was directed to other roads when road closures were necessary. (Photo courtesy of Caltrans)
Traffic was directed to other roads when road closures were necessary. (Photo courtesy of Caltrans)
The new alignment required cutting through a mountain. (Photo courtesy of Caltrans)
The new alignment required cutting through a mountain. (Photo courtesy of Caltrans)
Crews cut a new alignment through a mountain. (Photo courtesy of Granite Construction)
Crews cut a new alignment through a mountain. (Photo courtesy of Granite Construction)
Granite used heavy machinery to move 845,000 cubic yards of dirt. (Photo courtesy of Granite Construction)
Granite used heavy machinery to move 845,000 cubic yards of dirt. (Photo courtesy of Granite Construction)
Building the new alignment required a significant amount of dirt work. (Photo courtesy of Granite Construction)
Building the new alignment required a significant amount of dirt work. (Photo courtesy of Granite Construction)
Dirt work and grading is completed in preparation for the new road. (Photo courtesy of Granite Construction)
Dirt work and grading is completed in preparation for the new road. (Photo courtesy of Granite Construction)
Construction crews fill in Bear Valley. (Photo courtesy of Granite Construction)
Construction crews fill in Bear Valley. (Photo courtesy of Granite Construction)
The California Department of Transportation (Caltrans) recently completed the $54.6 million Omega Curves Safety Improvement project to straighten State Route 20’s curves and reduce deer-vehicle accidents. About 5,620 vehicles drive on SR 20 in this region daily.

“It turned out amazing,” said Jeff Johnson, Resident Engineer at Caltrans. “We will have a safer road, which is a huge improvement for the traveling public.”

A three-year study found that 39 collisions occurred in two curving sections of S.R. 20 in Nevada County, a higher rate of accidents than the statewide average for similar roads. That led Caltrans to seek a solution. The agency received approval for this project in 2020.

Enhancing Travel Safety
The project modified the vertical and horizontal curves in two sections — White Cloud and Lowell Hill — to bring them up to current standards by increasing the curve radii. White Cloud had two nonstandard curves and Lowell Hill had four nonstandard curves. SR 20 now has a new alignment.

“It will be safer, because they are not coming over a blind curve,” Johnson said.

Crews also widened the shoulders from 8 feet to 10 feet, added two left-turn lane pockets and three turnouts, and widened an existing turnout. The three turnouts allow slower traffic, such as trucks, to pull off the road and let other vehicles safely pass and provide a space for law enforcement to stop.

SITECH
Your local Trimble Construction Division dealer
SITECH Northwest

Work took place in five locations across 14 miles. The first involved adding left-turn lanes; the second, a curve realignment at 4,000 feet of elevation; the third, more left-turn lanes; the fourth, building a turnout for parking; and the fifth, a curve realignment at 5,400 feet of elevation. Crews widened the shoulders in all locations in which work took place.

The project also called for installation of 10 miles of fencing and installation of two 12-foot by 12-foot reinforced concrete boxes — one at White Cloud and one at Lowell Hill — to serve as animal crossings.

“By doing an animal crossing, we reduced the potential for collision with a deer or other animal,” said Jeremy Linder, Public Information Officer for Caltrans District 3.

Caltrans completed design in April 2021.

The Operational Improvement program of the 2020 State Highway Operation and Protection Program (SHOPP) funded the project. SHOPP receives money from the federal and state governments and funds capital improvements that do not add capacity to the system.

Navigating Nature’s Challenges
Granite Construction of Watsonville, California, was awarded the construction contract. Incorporated since 1922, Granite is one of the largest diversified construction and construction materials companies in the United States and is a full-suite civil construction provider. Granite’s Sacramento office handled the Omega Curves Safety Improvement project.

In the two sections reducing the curves, Granite cut through a mountain and forest to build a safer road.

According to Johnson, the rural job site location presented some challenges. “We do not have many new alignments,” he said. “Access is tough, and you have trouble getting employees on a remote job.” Along the 14-mile section, cellphone service was either nonexistent or spotty.

Work could take place only between May and November due to the weather and melting snow, and the weather could vary from one location to the next. Granite had only two summer seasons to complete the work and get the new alignment open.

“The effort to get this project done in two seasons was a huge accomplishment,” Johnson said.

In spring 2022, Granite began the work to log, clear, and prepare the site. Sixty-five acres required clearing, and logs were sent to a mill to turn them into lumber. During the extensive earthwork portion of the job, Granite worked double shifts for five weeks to speed up completion.

While the project was designed in a 3D model, crews could not use GPS due to the remote location. However, the team used total stations to complete the machine-guided work for most of the project.

“We had to set each total station as we went,” said Bill Lauesen, Project Manager with Granite. “And we had to keep moving them because they have a limited line of sight. It was not as fast as GPS would have been.”

Granite also used drones to fly the project and quantify the amount of excavation that had taken place. Comparing the drone footage with the design allowed crews to know how much more excavation or fill was needed.

“That helped us identify a short coming in the excavation early on,” Lauesen said. “It allowed Caltrans to redesign some of the roadway.”

The team used Autodesk Build management software to communicate. They kept submittals, change orders, and requests for information in Autodesk Build.

“That was a huge benefit on the project, because it kept everybody on the same page,” Johnson said. “Everybody in the field had a tablet. The contractor provided the state with four tablets, so we had all the information needed in the field.”

From Blasting to Paving
Crews blasted and removed a minimal amount of hard rock as they straightened out the curves, excavating mountains to fill in valleys. Extensive dirt work also took place. “We were literally moving mountains,” Johnson said.

Crews moved about 845,000 cubic yards of dirt, which equates to 40,000 loads of material. Some of the excavations were 100 feet deep, and the fill was placed 120 feet into the valley. In addition, the project included 120 feet of one-to-one cut slopes and 140 feet of 1.5-to-one cut slopes.

“The sheer amount of dirt was amazing to watch, week in and week out,” Linder said. “And the progress they were making — it was quick and went smoothly. I enjoyed watching the progress.”

Crews also installed a 5-foot by 5-foot, 300-foot-long drainage structure, as well as 2,600 linear feet of drainage pipe. The water flows to creeks in the lower-lying areas.

Granite paved with hot-mix asphalt, which was brought from Sacramento, about 2.5 hours away. About 46,000 tons of asphalt were transported to the project.

Throughout the project, complete closures of the road rarely occurred, but they were necessary when converting traffic from the old alignment onto the new roadway, which had an elevation difference of 20 feet. During the closures, Caltrans directed traffic to other roads. California Highway Patrol officers remained on site to escort any emergency vehicles needing to travel through the construction zone.

“One of the biggest surprises to us, as the contractor, was the amount of traffic on that route,” Lauesen said. Most of the traffic occurred during the summers when the work was taking place.

At other times, one lane of traffic was closed, and a flagman and pilot car escorted traffic through one direction at a time. In addition, periodic traffic holds — with delays lasting up to 45 minutes — were necessary during the blasting.

People living in the area continued to use the road, but through traffic — such as vehicles heading to Lake Tahoe — started using alternative routes.

“Every day, that project threw something new at the team, and we had to be resilient,” Lauesen said. “It was a cool project to build.”

Lauesen praised the teamwork, which enabled resolving issues collaboratively. There were no claims on this project. “The dedication between Granite and Caltrans was great,” he said.

Granite substantially completed the project at the end of 2023, and the road is now open to traffic. Some landscaping and erosion control will wait until 2024.

“Having it done before the snow flies is good,” Johnson said. “This was a once-in-a-career project. It was amazing. We had a great team to work with.”

Metso Minerals - Recycling Eq
Your local Metso Minerals Industries Inc dealer
Westate Machinery Co
PacWest Machinery
Metso Minerals - Recycling Eq
Your local Metso Minerals Industries Inc dealer
Westate Machinery Co
PacWest Machinery