Construction News

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Utilizing CMGC Contract, Great Northwest Meets Aggressive Schedule

by: Debra Wood
Crews use a Manitowoc 3900W crane to lift the bridge’s girders into place.
Crews use a Manitowoc 3900W crane to lift the bridge’s girders into place.
Crews work on the decorative center median.
Crews work on the decorative center median.
Crews use Roadtec equipment to pave University Avenue with asphalt.
Crews use Roadtec equipment to pave University Avenue with asphalt.
Crews work on the Chena River Bridge.
Crews work on the Chena River Bridge.
Utilities were moved during the reconstruction of University Avenue.
Utilities were moved during the reconstruction of University Avenue.
Widening the road required new storm drain structures and piping. Having full road closures to expedite the schedule allowed Great Northwest to complete work with less delay and less overall impact to businesses and the public.
Widening the road required new storm drain structures and piping. Having full road closures to expedite the schedule allowed Great Northwest to complete work with less delay and less overall impact to businesses and the public.
Improvements to a primary north-south corridor in Fairbanks, Alaska, University Avenue, aims to reduce congestion, improve access for pedestrians and bicyclists, and increase safety and mobility.

“Over the years, the four-lane, undivided facility had become congested with heavy turning traffic competing with through traffic,” says Northern Region Group Chief Lauren Little, with the Alaska Department of Transportation and Public Facilities (DOT&PF), about the need for the project.

University Avenue connects the University of Alaska Fairbanks with businesses and residential properties. About 17,750 vehicles travel on it daily.

Scope of work
The project entails widening and reconstructing 2.1 miles of University Avenue from the Mitchell Expressway to the Thomas Street intersection. The new road includes a raised center median, left-turn lanes at intersections without traffic signals, the addition of 4.5-foot wide shoulders, and widening of the sidewalks to eight feet on the west side and to six feet on the east side.

“The addition of the raised median for access control, as well as left-turn pockets at median breaks, was important for mobility as well as safety,” Little says.

The project also involves reconstructing the intersections at Geist Road/Johansen Expressway and Airport Way, replacing the Chena River Bridge, relocating driveways and side streets, and improving utilities and drainage. Crews also widened Airport Way/University Avenue.

Hitachi CE
Your local Hitachi dealer
CLM Equipment Co
ASCO Equipment

Work on the corridor improvements began in 2018, and several segments of the job, about 80 percent, have been completed, including intersection improvements, widening of the avenue between Airport Way and Thomas Street, replacement of the bridge, and utility relocations. Alaska’s short construction season contributed to the project duration.

Several engineering firms were involved in the project, including RESPEC, Kinney Engineering and Michael Baker International, all with offices in Anchorage, Alaska.

CMGC Methodology
DOT&PF awarded Great Northwest of Fairbanks a construction manager/general contractor (CMGC) contract, which enabled the construction team to collaborate with designers. Hamilton Construction of Sutton, Alaska, served as the bridge subcontractor and B&B Electric of Fairbanks the primary electrical subcontractor. Hamilton and B&B were part of the CMGC contract, with other subcontractors competitively solicited by Great Northwest. An independent cost estimator reviewed all quotes and rates.

“Great Northwest worked diligently to find ways to meet the aggressive project construction schedule while working around old utility systems, without any claims or significant delays,” Little reports.

Little says she considers the CMGC delivery method the highlight of the approximately $75 million project, which had “languished for years struggling with right-of-way acquisition and utility relocations. We worked as a team to identify areas where we had sufficient right-of-way to just start slowly building improvements, and the momentum built upon itself.”

While this was Great Northwest Project Manager Steve Geraghty’s first CMGC project, he’s become a believer in the delivery method, especially for more complicated projects.

Takeuchi Mfg Ltd
Your local Takeuchi Mfg Ltd dealer
Kirby Smith Machinery
Power Equipment Co

“It has worked really well,” Geraghty reports. “I have no doubt this project would never have been built without CMGC.”

The CMGC approach allowed the team to evaluate various options to ensure crews moved forward with the best solution, he adds.

“We vetted a host of design alternatives, developing cost estimates and schedules for each alternative, so that by the time the final design was reached, we knew without question that we had the best design and the best plan for that design,” Geraghty says. “Another key benefit with CMGC was the ability to identify and order long lead materials ahead of construction, and in some cases ahead of final pricing.”

A Personal Connection
The former Chena River Bridge was narrow and structurally deficient. Geraghty’s father was a partner in the company that originally built the bridge, making this work even more meaningful.

“All of the personal stories tied to the old bridge, makes the replacement neat,” Geraghty says. “The legacy made it a special project for me, and I am very proud to have been part of it.”

The current project replaced the old bridge with a 280-foot long, three-span, decked-bulb tee concrete girder bridge founded on steel pipe pilings, with 36-inch piers and 18-inch abutments. It features pedestrian facilities, a median and shoulders. At 88-foot, four-inches wide, Little reports it “is the widest DOT-owned bridge in Fairbanks. The bridge was constructed over the Chena River and was not considered a marine operation.”

Leica Geosystems Inc
Your local Leica Geosystems Inc dealer
Laser Specialist inc

The Chena River Bridge construction schedule was extremely aggressive, Little adds. “We had commitments to the state park to not impact their boat launch for more than one season, and this property in particular has special federal protections, making that a hard commitment.”

Construction activities
In 2022, crews reconstructed University Avenue from the Mitchell Expressway to Holden Road and Geraghty Avenue between University Avenue and Marlin Street. The work included widening University Avenue, adding a continuous sidewalk on both roads, relocating utilities and improving drainage.

Moving buried utilities, including a lift station, and water and sewer mains, while maintaining service to residents and businesses along the corridor was challenging and required close coordination with local utilities, Geraghty reports. Solutions included delivering potable water in tank trucks during shutdowns, boring a new water main under the river and dewatering to permit installation of deep utilities.

The new pedestrian sidewalks on Geraghty “connect the sidewalks on University Avenue to the new Chena River State Recreation Site entrance on Geraghty Avenue, which was moved with the project due to the median closing off the current entrance on University Ave,” Little says. “The project also constructed a new boat launch, campground enhancements and a new paved boat launch parking lot at the Chena River State Recreation Site.”

The state park had environmental protections, which had to be taken into consideration while under construction.

The DOT&PF closed roads during construction. “Due to the tight urban nature of the work and having to work around and install new very deep utility systems, this was the safest and [had the] least impact to the public,” Little says. “Without closures the work would have taken a minimum of an extra year per work package to complete, and in some areas was not technically feasible.”

Vogele
Your local Wirtgen America dealer
Kirby Smith Machinery
Power Equipment Co

Maintaining pedestrian and vehicle traffic has presented challenges for the team. “We were able to show the state the full closures were a better option for limiting the impact to the public,” Geraghty says.

The 2022 work included a full closure of Geraghty Avenue and full closure of University between 19th Avenue and the Mitchell Expressway and a lane closure on southbound University Avenue for most of the construction season. The closures were needed to complete the work in one season and dig the five-foot to eight-foot deep excavations that were needed to remove poor soils associated with an old slough channel, according to the DOT&PF.

The project is scheduled for completion in October 2023. Little reports feeling proud of the teamwork among the project stakeholders and relationships built and sustained with property owners along the corridor.

“We started with a diverse group of individuals and built a team that moved mountains along this corridor,” Little says. “I’m also proud of the quality of product we’ve provided for the residents and road users in Fairbanks. In addition to being highly functional, the fit and finish is exceptional.”

Photos courtesy of Alaska Department of Transportation and Public Facilities

Case  - CE
Your local Case Construction Equipment Inc dealer
ASCO Equipment
Wirtgen America Inc
Your local Wirtgen America dealer
Kirby Smith Machinery
Power Equipment Co
Leica Geosystems Inc
Your local Leica Geosystems Inc dealer
Laser Specialist inc
Vogele
Your local Wirtgen America dealer
Kirby Smith Machinery
Power Equipment Co