Dixie Contractor

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Missouri DOT Rehabs 14 Bridges on I-55 in St. Louis

by: Debra Wood
Crew members for KCI reconstruct one of several I-55 bridges between I-44 and Lindbergh in St. Louis.
Crew members for KCI reconstruct one of several I-55 bridges between I-44 and Lindbergh in St. Louis.
With many mainline bridges on Interstate 55 in the St. Louis area in need of major rehabilitation, the Missouri Department of Transportation (MoDOT) bundled 14 of them into one $63 million contract.

“By bidding this work together, we can improve coordination, reduce length of impacts to the travelling public and reduce costs,” says Scott Washausen, MoDOT Resident Engineer for the St. Louis City Area Team. “Work like this done a few bridges at a time would have taken many years. By bundling and staging all of this work together, we were able to condense the construction schedule down to 2.5 years.”

The work takes place along an 11-mile stretch between Lindbergh and the I-44/I-55 interchange in St. Louis. Average daily traffic volumes on I-55 – a major commuting corridor in this area – range from 80,000 to 92,000, including significant truck traffic.

The bridges were built between 55 and 60 years ago and needed significant repairs. The project also included removing a pedestrian bridge and upgrading 6.5 miles of median barrier wall.

“Since these bridges are on the mainline of I-55, the work is very impactful,” Washausen says. “The scope of work needed on this corridor was extensive, and it is best to get it done as quickly as possible, rather than have repeated impacts on the same interstate corridor over an extended period of time.”

Doosan Infracore Portable Pwr
Your local Bobcat dealer
Pinnacle Central Co Inc

Jacobs, EFK Moen, and CMT, all with offices in St. Louis, designed the project.

Demolition Starting at the Top
KCI of St. Louis, founded in 1922 as a carpentry firm, received the construction contract. The company expanded into heavy civil work in 1984, and earthwork and utility work in 2016. KCI self-performs most of its concrete work. It began work on the I-55 bridges in spring 2022 on the northern end of the project limits.

“We did require the demolition of some of the bridge decks to be cut and picked off from the top when there were vulnerable systems below like the River Des Peres or an active bike lane nearby,” Washausen says.

None of the bridges required foundation work. Crews installed new steel girders on two of the seven spans on each northbound and southbound bridge over the River Des Peres. All work on the river bridge has been accomplished from above, with no marina operation.

“We needed to change the type of hinges at the abutments from rocker to plate hinges, which necessitated new girders for the first and last spans of each directional bridge,” Washausen explains.

Crews are placing ultra-high-performance concrete when installing bridge joints. “This material is relatively new to our industry and will help prevent joint failures that can often create short-notice emergencies for our maintenance team,” Washausen says.

Challenging Aspects of the Project
Maintaining traffic presented challenges for the team. Three crossovers were needed to completely close one side of the highway at a time. Two lanes of traffic in each direction operate on half of the interstate lanes, Washausen reports.

“Traffic switching requires ramp closures, but the phasing we are using aims to reduce this as much as possible and keep any needed closures reduced to as few months as possible,” Washausen says. “We have found it works best for traffic flow to keep lane widths more than 11.5 feet, even if it means sacrificing a third lane. Two lanes can move a lot of traffic if they have sufficient width and comfortable shoulders.”

In areas close to residential homes, crews work during daytime hours due to possible noise concerns. Crews maintained access to major commercial districts.

“Public perception has been an issue,” Washausen says. “With long stretches of one side of the highway closed, people can’t see the bridge work due to the bank of the roadway in some phases. We had customers complain that they wanted the other side of the highway open at night or on weekends when we weren’t working, but they couldn’t see that some of the bridges had been removed down to the girders and others were completely undriveable.”

Completed Work
“Inside the northernmost crossover the crews have completed a redeck on 2nd Street and two latex overlays on the northbound side,” Washausen says. “Both directions of traffic have now been moved to the northbound lanes and the same work is occurring on the southbound side in this crossover area.”

At the second crossover to the south, crews are working on the first redeck over River Des Peres and one overlay. Work on the bridges over Union Pacific Railroad will begin shortly. Additionally, crews have completed two overlays at the Virginia and Bates bridges. KCI removed the pedestrian bridge during a weekend, full closure of the interstate. About 75 percent of the median barrier wall replacement has taken place.

Future Construction
Work has yet to begin on the third crossover, which has two re-decks over Gravois Creek and Green Park Road, which includes a bicycle/pedestrian path.

Overlays are under way at 4500 Broadway and Gasconade. The overlay at Bayless is scheduled to begin soon.

The replacement of the bridge deck over the Grant’s Trail bicycle and pedestrian path will be phased to keep the trail open, although the road, which parallels the trail underneath may need temporary closures. MoDOT will close the Carondelet Connector multi-use path for about a year as work on the Union Pacific railroad bridge takes place.

“In this case, a suitable detour was available nearby along low-stress roadways and will be a signed detour during construction,” Washausen says.

Under a separate contract, MoDOT plans to resurface the highway in the spring of 2024. The phased work is expected to continue for two years.

“The citizens of Missouri have asked us to take care of the system we have so that it continues to serve our communities into the future,” Washausen concludes. “Work like this that maintains bridges and keeps them in good structural condition but does not change the form of the roadway is often overlooked, but we know it is important…We are proud to upgrade this vital corridor for the future.”

Photos courtesy of the Missouri Department of Transportation

Epiroc
Your local Atlas Copco CMT USA dealer
Power Equipment Co
Epiroc
Your local Atlas Copco CMT USA dealer
Power Equipment Co
Komatsu Dealer Program
Your local Komatsu America Corp dealer
Linder Industrial Machinery
Power Equipment Co