For many years, KDOT and area stakeholders have identified the U.S. 83 corridor as important route for improvement. The pavement on this part of the route is approximately 50 years old and has a history of rutting, fatigue cracking, and thermal transverse cracking.
Running one lane in each direction over this span, capacity is also an issue. The average daily traffic in 2016 was 4,450 vehicles and the traffic is projected to reach 6,650 vehicles by 2036.
Approximately one-third of the traffic is from semis and other truck traffic. The area is home to the agricultural industry and is a regular route for those going to and from the feed yards. It was determined that this important freight route was in need of reconstruction due to the poor quality of the road, capacity issues, and limited passing opportunities.
An alternative route is approximately 30 miles away, and with 3-foot shoulders instead of 10-foot shoulders, it’s not as wide so shutting down the road to work on it would have been a significant issue for traffic. Therefore, KDOT decided to do a realignment and reconstruction of U.S. 83.
Your local Trimble Construction Division dealer |
---|
SITECH Allegheny |
SITECH Northeast |
“We’re following the existing roadway and the offset is not very far,” said Schlott. Upon completion, they’ll remove the existing road.
The new road will see passing and turning lanes to improve traffic flow and reduce delays. The passing lanes will cover approximately two miles, while the turn lanes will be installed at some higher traffic side roads that lead to grain elevators and feed lots.
“When you travel on a road with semis, it can be difficult,” said Schlott. Besides the semis associated with the agricultural industry, there’s lots of truck traffic with oversized loads related to wind turbines in the area.
Both of these types of vehicles may be going below the speed limit and passing them is difficult. This leads to slowdowns and backups. The increased length of passing lanes will help keep traffic moving.
The states most recent 10-year transportation plan – Ike – had a whole new set of infrastructure projects. However, “all of the projects that were suspended are moving forward before we focus on new projects as we are determined to fulfill our promises,” said Lisa Knoll KDOT Public Affairs Manager.
Your local Gomaco dealer |
---|
Gomaco -Contact Local |
The construction budget for this project is $24 million and it’s being financed with 80 percent federal funds and 20 percent state funds.
Schlott notes that the project is on budget and he expects it to stay that way. He credits the well-done plans and the way KDOT bids projects. “Our projects are bid line items for every item, so if the plans are accurate then we are normally on budget,” said Schlott.
The only item that differed from the plans so far was the need to install temporary pipes and drainage between roads since a ditch cut into the existing road. The pipes were needed due to the extreme weather the area experienced – 12 inches of rain during a three-week period in July. “We don’t typically get much rain in this part of the state, but when it does rain, it can be quite a bit,” said Schlott.
The contractor on the project is Kansas based, Venture Corporation. They have worked on many state projects and are familiar with KDOT.
Schlott says the project is on schedule or even a bit ahead. The warm fall weather allowed the team to get the work done they needed for the season.
Your local Trimble Construction Division dealer |
---|
SITECH Allegheny |
SITECH Northeast |
The contractor had to work around a challenge to keep the project on schedule.
AT&T had a fiber line and phone line that could not be moved when the project restarted because it was right around when COVID-19 hit. “Even thought the new line had already been installed, since the old line carries 911 they felt they couldn’t shut it down to switch it over,” said Schlott. There was fill around the new line and it could not be cut.
Ultimately, the move occurred in August. The contractor, however, was able to work around where the existing line was and stay on schedule.
When the realignment and reconstruction of the new U.S. 83 is complete, motorists will enjoy improved road conditions and a reduction in traffic delays. Cars will be able to travel at greater speeds and no longer get caught behind trucks and semis, enabling them to travel up and down the lengthy U.S. 83.