SANIBEL, FL — The Superior-de Moya Joint Venture (JV) team has substantially completed the $328 million Sanibel Causeway restoration project, re-establishing and fortifying the critical 3-mile lifeline between Sanibel Island and mainland Florida that was devastated by Hurricane Ian on September 28, 2022.
"What makes this project special is that we've given this community infrastructure they can rely on through whatever comes next," said Toby Mazzoni, Project Manager at Superior Construction. "We build for the long haul, especially when communities are counting on us most."
When Hurricane Ian destroyed the causeway in 2022, Sanibel and Captiva Islands were completely cut off, paralyzing the tourism-dependent economy and leaving residents stranded. The emergency response team restored temporary access in just 15 days, enabling first responders to reach the islands and allowing residents to begin recovery efforts.
The project marked the Florida Department of Transportation's first phased design-build contract and highlighted the JV team's innovative approach, enabling emergency and permanent repairs to start while the design was still in development. The JV team successfully navigated complex logistics while maintaining traffic flow throughout construction.
"The joint venture team overcame this project’s logistical challenges with tenacity,” Superior Construction CEO Nick Largura said. “Building five seawalls during the hurricane season, railing in high-quality armor stone materials from Alabama and Georgia quarries, and improving resilience, while collaborating with multiple stakeholders on a first-of-its-kind phased design-build contract, is a monumental feat. I’m incredibly proud of this team.”
Your local Bobcat dealer |
---|
Pinnacle Central Co Inc |
At peak construction, the JV team coordinated multiple specialized crews simultaneously: three for pile-driving, four for earthwork, two for storm drainage, six for rebar tying, eight for concrete placement, and three for asphalt paving, all while keeping two lanes of traffic open for island residents and visitors.
The rebuilt causeway now features enhanced storm resilience, including:
- Nearly 750,000 square feet of steel sheet pile wall systems
- Approximately 19,750 linear feet of concrete caps
- 127,996 tons of strategically placed armor stone
- Elevated seawalls from 5 feet to 8 feet
- Advanced stormwater drainage systems throughout the causeway
- 19,500 tons of asphalt pavement
- Innovative scour prevention system
- 6,900 linear feet of various permanent roadway concrete barriers
- 25,000 square feet of fractured fin concrete fascia
The project's resilience was put to the test during construction in 2024 when Hurricanes Debby, Helene, and Milton struck Florida. Completed sections withstood these storms intact, while unfinished areas experienced washouts, providing real-world validation of the JV team's engineering approach.
Your local Trimble Construction Division dealer |
---|
SITECH Mid-South |
SITECH Tri-Rivers |
SITECH South |
The causeway's completion marks a milestone in Sanibel Island's recovery from Hurricane Ian and strengthens the community's defense against future storms. With this infrastructure restored, emergency services can now reliably reach the island, residents have secure mainland access, and tourism-dependent businesses can fully resume operations.