Three major projects currently underway in Angelina and Nacogdoches counties include:
Sacyr Construction USA LLC, of Miami, Florida, is serving as contractor for the project that will extend from FM 2108 to 1.15 miles south of White Oak Creek. The relief route will meet interstate design standards and will serve as the hurricane evacuation route and will move vehicular traffic along the US 59 corridor.
Current work includes clearing and removing stumps and dirt work on the north and south ends of the project. Crews continue to build header embankments at Mockingbird Lane. Crews have also begun installing bridge foundations. Utilities continue to be moved, and concrete columns will be set at Mockingbird Lane. Loggers also continue logging operations moving south to Conner Road and will continue hauling through Lumberjack Drive.
Work continues in newly constructed southbound lanes of US 69 between FM 844 and BW Horton Road. Concrete is being set for a new bridge in southbound lanes just north of Zavalla near First Street. Northbound lanes between FM 1270 and Zavalla also has crews working with the application of prime, chip seal, and hot mix. Detours are being placed near FM 1270 and BW Horton Road with lane closures anticipated in coming days.
Work is also continuing from FM 1270 to the Jasper County line that will continue construction of a four-lane divided highway. Drewery Construction Co., of Nacogdoches, Texas, is serving as contractor for the $37.5-million project. It is scheduled to be completed in early 2023, weather permitting. Current work includes clearing south of Earnest Smith Road and includes dirt and structure work for new northbound lanes between FM 1270 and Chambers Road.
The work will include the construction of overpasses at Spradley Street, existing US 59, and Old Lufkin Road and the construction of frontage roads for SL 224 between SH 7 and BU 59. The project was designed to meet interstate standards and will extend from SH 7 West on SL 224 to 1.2 miles south of Spradley Street on US 59.
Upcoming work includes placing embankment and topsoil near the south end of the project. Preparing right of way and cement stabilization near US 59 is continuing. Bridge work also continues with placing southbound deck panels and overhangs. Crews are tying steel and placing bridge railing in northbound lanes.